ML25356A091

From kanterella
Jump to navigation Jump to search

Transmittal Email Completeness and Withholding Forms for the GNF-A TR Satisfaction of Limitation and Condition 3 for NEDC-33353P, Revision 0
ML25356A091
Person / Time
Site: 99901376
Issue date: 12/22/2025
From: Ekaterina Lenning
Licensing Processes Branch
To: Schichlein L
Global Nuclear Fuel
References
EPID L-2025-TOP-0036
Download: ML25356A091 (0)


Text

From:

Ekaterina Lenning To:

"Schichlein, Lisa (GE Vernova, GCCH)"

Cc:

Halac, Kent E (GE Vernova, GCCH); Michael Marshall; Scott Krepel; Jeremy Dean

Subject:

Transmittal Email NRC Forms 898 and 897 for GNF-A "Satisfaction of Limitation and Condition 3 for NEDC-33353P, Revision 0, Licensing Topical Report Application of GNF-Ziron to GNF Fuel Designs" Date:

Monday, December 22, 2025 3:44:00 PM

Dear Ms. Schichlein,

By letter dated October 3, 2025, Global Nuclear Fuel - Americas (GNF-A), submitted Satisfaction of Limitation and Condition 3 for NEDC-33353P, Revision 0, Licensing Topical Report Application of GNF-Ziron to GNF Fuel Designs (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25276A020), to the U.S.

Nuclear Regulatory Commission (NRC) and requested that the NRC provides a response back to GNF-A confirming that Limitation and Condition 3 for the topical report for NEDC-33353P, Revision 0, Licensing Topical Report Application of GNF-Ziron to GNF Fuel Designs, has been satisfied. The NRC staff performed the acceptance review of the submittal and determined that the NRC staff will perform uncomplicated confirmation review of this submittal. The schedule and effort outlined in the NRC form 898 takes into consideration the NRCs goal of a 15 percent improvement in timeliness and resources.

Please note that the NRCs current review priorities and available technical resources may be subject to change. If modifications to these dates are deemed necessary, we will provide revisions/updates to this information. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date of significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. The review schedule milestones and estimated review costs were discussed and agreed upon between you and the NRC staff on December 22, 2025.

The NRC form 898, Topical Report Completeness Determination, documents the NRC staff acceptance review results. The NRC Forms 898, Topical Report Completeness Determination, and 897, Withholding Determination Form, for the GNF-A submittal Satisfaction of Limitation and Condition 3 for NEDC-33353P, Revision 0, Licensing Topical Report Application of GNF-Ziron to GNF Fuel Designs, can be located in ADAMS at Accession Nos. ML25356A090 and ML25356A089, respectively.

I also shared copies of the approved forms with you via NRC secure external sharing portal.

This email will be declared in ADAMS as Agency Official Record of the transmittal.

If you have any questions, please feel free to contact me via phone 301-415-3151 or via email Ekaterina.Lenning@nrc.gov.

Sincerely, Ekaterina Lenning, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Docket No. 99901376

ML25356A081 (Package)

ML25356A091 (Email)

ML25356A089 (Withholding Determination NRC 897 Form)

ML25356A090 (Completeness Determination NRC 898 Form)

OFFICE NRR/DORL/LLPB/

PM NRR/DORL/LLPB/

LA NRR/DSS/SFNB/

BC NRR/DORL/LLPB/

BC(A)

NAME ELenning DHarrison SKrepel MMarshall DATE 12/22/2025 12/22/2025 12/22/2025 12/22/2025