LaSalle County Station Technical Specification 3.3.7.1 Proposed Change NRC Pre-Submittal Meeting December 9th, 2025

1. Purpose

2. Background

3. Reason for Request and Current Requirements
4. Proposed Change
5. License Amendment Request Submittal Schedule
6. Feedback / Questions Agenda l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 1

-Discuss proposed change and its technical basis

-Summarize the drivers for the proposed change

  • Discuss desired submittal and review schedule
  • The CRAF System provides a radiologically controlled environment to ensure the habitability of the control for the safety of the operators under all plant conditions.

-Shared system for the Unit 1 and Unit 2 control room

-Two independent CRAF subsystems are each capable of maintaining a habitable environment in the control room following a design basis accident (DBA) without exceeding the dose criteria of 10 CFR 50.67

  • The CRAF system instrumentation has 4 trip systems - 2 per intake

-There are 2 trip systems per CRAF subsystem

-Either trip system can initiate a CRAF subsystem (1 out of 2 logic)

-A trip system is comprised of 2 radiation detectors and 2 monitors

-Total of 8 detectors and 8 monitors (4 per CRAF subsystem)

  • Both detectors and monitors in a trip system must receive a high radiation signal to actuate the trip unit (2 out of 2 logic)

Background

l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 3

  • CRAF subsystem initiation logic:

Background (continued) l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 4

Detector A Detector B Detector C Detector D Monitor A Monitor B Monitor C Monitor D AND AND Trip System A Trip System B OR CRAF Subsystem

  • Current radiation monitors in the CRAF system have been experiencing an increased rate of spiking.

-A modification to the monitors to address the spiking has been approved and installed on 1 of 8 monitors.

-Obsolescence issues with the current monitor resulted in significant delays and ability to modify the remaining detectors.

-LaSalle County Station has approved installing new monitors but due to the long lead-time, the monitors will not be available for installation until Summer 2027.

Reason for Request and Current Requirements l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 5

  • TS 3.3.7.1 currently only allows channels to be placed in trip.

-If more than one channel on the same trip unit is placed in trip, the CRAF subsystem will start.

-Otherwise, the CRAF subsystem would be declared inoperable, requiring entry into TS 3.7.4, Control Room Area Filtration (CRAF) System, which is a 7-day shutdown Limiting Condition for Operation (LCO).

  • Due to the long lead-time of replacement radiation monitors, there is a chance where 2 channels on the same trip unit are inoperable prior to replacement parts available.

-This would result in running the safety-related CRAF subsystem only to meet a TS required action or entering a shutdown LCO.

Reason for Request and Current Requirements (continued) l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 6

  • The proposed TS change makes the following changes to TS 3.3.7.1:

-An additional Required Action is added to Condition A to declare the associated trip system inoperable with a Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

-A new Condition B is added for when one trip system of a CRAF subsystem is inoperable. The required action is to restore the trip system to operable within 21 days.

-Existing Condition B is changed to Condition C and new proposed Condition B is added to the Condition statement.

  • The purpose of these changes is to prevent running the safety-related CRAF subsystem only to meet a TS required action or entering the shutdown LCO in TS 3.7.4 if the CRAF subsystem is declared inoperable.
  • The proposed changes will allow time to make repairs to the trip system and return at least one channel of a trip system to operable.
  • The proposed TS change will still require at least one trip system to remain operable and manual initiation of the CRAF subsystem will be maintained.

Proposed Change l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 7

Proposed Change (continued) l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 8

Proposed Change (continued) l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 9

  • Plan submittal of the LAR to the NRC is on or before December 31, 2025
  • Requested approval is 2 months from submission.
  • The reason for the expedited approval is to prevent running the safety-related CRAF subsystem only to meet a TS required action or entering the shutdown LCO in TS 3.7.4 if the CRAF subsystem is declared inoperable.

License Amendment Request Submittal Schedule l LaSalle County Station Technical Specification 3.3.7.1 Proposed Change 10