U.S. Nuclear Regulatory Commission Verification Letter for Westinghouse Electric Company Topical Report WCAP-18904-P/NP-A, Revision 0, Critical Power Experiments and D6 CPR Correlation for TRITON11 Fuel
ML25339A128
Person / Time
Site: Westinghouse
Issue date: 12/11/2025
From: Marshall M
Licensing Processes Branch
To: Ewing J
Westinghouse
References
EPID L-2025-TOP-0054
Download: ML25339A128 (0)


Text

December 11, 2025 Mr. Jerrod Ewing Manager, Operating Plants Licensing Westinghouse Electric Company 1000 Westinghouse Drive, Building 1 Cranberry Township, PA, 16066

SUBJECT:

U.S. NUCLEAR REGULATORY COMMISSION VERIFICATION FOR WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-18904-P/NP-A, REVISION 0, CRITICAL POWER EXPERIMENTS AND D6 CPR CORRELATION FOR TRITON11 FUEL (PROPRIETARY/NON-PROPRIETARY) (EPID L-2023-TOP-0054)

Dear Mr. Ewing:

By letter dated November 11, 2025 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25318A740), Westinghouse Electric Company (Westinghouse) submitted to the U.S. Nuclear Regulatory Commission (NRC) the approved versions (-A) of Topical Report (TR) WCAP-18904-P/NP-A, Revision 0, Critical Power Experiments and D6 CPR Correlation for TRITON11 Fuel (Proprietary/Non-proprietary). Westinghouse has done so in accordance with our request to publish -A proprietary and non-proprietary versions of the TR, as detailed in the NRC final safety evaluation (SE) transmittal letter dated August 6, 2025 (ML25121A021), for the TR WCAP-18904-P/NP, Revision 0, Critical Power Experiments and D6 CPR Correlation for TRITON11 Fuel.

The NRC staff has completed its verification review of the -A version of the TR. The NRC staff verified that the submitted TR WCAP-18904-P/NP-A, Revision 0, Critical Power Experiments and D6 CPR Correlation for TRITON11 Fuel, is acceptable for referencing in licensing applications for nuclear power plants to the extent specified and under the limitations and conditions delineated in the NRC final SE and the TR. The -A version, TR WCAP-18904-P/NP-A, Revision 0, Critical Power Experiments and D6 CPR Correlation for TRITON11 Fuel, is now approved for use in future licensing actions.

If you have any questions, please contact the Project Manager for the review, Ekaterina Lenning at 301-415-3151 or via electronic mail at Ekaterina.Lenning@nrc.gov.

Sincerely,

/RA/

Michael L. Marshall, Jr., Acting Branch Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902038

ML25339A128 OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DSS/SFNB/BC NRR/DORL/LLPB/BC(A)

NAME ELenning DHarrison SKrepel MMarshall DATE 12/5/2025 12/10/2025 12/9/2025 12/11/2025