Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2025005 and 05000316/2025005)
ML25234A214
Person / Time
Site: Cook, 07200072  
Issue date: 08/25/2025
From: Nestor Feliz-Adorno
NRC/RGN-III/DORS/ERPB
To: Ferneau K
Indiana Michigan Power Co
References
IR 2025005
Download: ML25234A214 (1)


Text

Kelly Ferneau Executive VP and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106

SUBJECT:

UPDATED INSPECTION PLAN FOR DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 (REPORT 05000315/2025005 AND 05000316/2025005)

Dear Kelly Ferneau:

The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for Donald C. Cook Nuclear Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025 (ML25042A278), the NRC determined that a broad, comprehensive review of the ROP is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented.

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

August 25, 2025

K. Ferneau 2

Please contact me at 630-829-9739 with any questions you have regarding this letter.

Sincerely, Néstor J. Féliz Adorno, Chief Engineering and Reactor Projects Branch Division of Operating Reactor Safety Docket Nos. 05000315, 05000316 and 07200072 License Nos. DPR-58 and DPR-74

Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Feliz-Adorno, Nestor on 08/25/25

K. Ferneau 3

Letter to Kelly Ferneau from Néstor J. Féliz Adorno dated August 25, 2025.

SUBJECT:

UPDATED INSPECTION PLAN FOR DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 (REPORT 05000315/2025005 AND 05000316/2025005)

DISTRIBUTION:

Rodney Clagg RidsNrrDorlLpl3 RidsNrrPMDCCook Resource RidsNrrDroIrib Resource Jack Giessner Mohammed Shuaibi Diana Betancourt-Roldan John Pelchat Jared Heck Jennifer Dalzell R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML25234A214

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RIII NAME NFéliz Adorno:sw DATE 08/25/2025 OFFICIAL RECORD COPY

Site Inspection Activity Plan D.C. Cook 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Security Baseline Inspection 1

1,2 7/7/2025 7/24/2025 IP 71130.07 000739 Security Training Functional Engineering Inspection - Fire Protection - DCC 3

1,2 7/14/2025 7/31/2025 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Security Baseline Inspection - DCC 1

1,2 8/25/2025 8/29/2025 IP 71130.14 000743 Review of Power Reactor Target Sets Inservice Inspection Unit 2 - DCC 1

2 9/22/2025 10/17/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Radiation Protection Baseline Inspection - DCC 1

1,2 9/22/2025 9/26/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 9/22/2025 9/26/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 9/22/2025 9/26/2025 IP 71124.04 000728 Occupational Dose Assessment Eplan and EAL Changes Review - DCC 1

1,2 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Cyber Security Inspection - DCC 4

1,2 12/1/2025 12/5/2025 IP 71130.10 000741 Cybersecurity Security Baseline Inspection DCC 1

1,2 1/26/2026 1/30/2026 IP 71130.01 000733 Access Authorization 1,2 1/26/2026 1/30/2026 IP 71130.08 000740 Fitness-For-Duty Program D.C. Cook 2026 Initial License Examination 7

1 2/22/2026 2/28/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV) 1 6/7/2026 6/13/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV) 1 7/5/2026 7/18/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

DC Cook 2026 Biennial Licensed Operator Requalification Inspection 2

1 3/9/2026 3/13/2026 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Radiation Protection Baseline Inspection - DCC 2

1,2 4/6/2026 4/10/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 4/6/2026 4/10/2026 IP 71124.04 000728 Occupational Dose Assessment 1,2 4/6/2026 4/10/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security Baseline Inspection DCC 1

1,2 5/18/2026 5/22/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Prepared on 8/20/2025 9:42:16 AM 1 of 4

Site Inspection Activity Plan 1,2 5/18/2026 5/22/2026 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations Emergency Preparedness Baseline Inspection / Performance Indicator Verification - DCC 1

1,2 6/8/2026 6/12/2026 IP 71114.02 000717 Alert and Notification System Testing 1,2 6/8/2026 6/12/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 6/8/2026 6/12/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 6/8/2026 6/12/2026 IP 71151 001397 Performance Indicator Verification Comprehensive Engineering Team Inspection - DCC 7

1,2 7/6/2026 7/24/2026 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Security Baseline Inspection DCC 1

1,2 8/3/2026 8/7/2026 IP 71130.02 000734 Access Control 1,2 8/3/2026 8/7/2026 IP 71130.09 001656 Security Plan Changes 1,2 8/3/2026 8/7/2026 IP 71151 001338 Performance Indicator Verification Inservice Inspection Unit 1 - DCC 1

1 9/21/2026 10/9/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Radiation Protection Baseline Inspection - DCC 2

1,2 9/21/2026 9/25/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 9/21/2026 9/25/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 9/21/2026 9/25/2026 IP 71124.04 000728 Occupational Dose Assessment 1,2 9/21/2026 9/25/2026 IP 71151 000746 Performance Indicator Verification Security Baseline Inspection DCC 1

1,2 9/28/2026 10/2/2026 IP 71130.14 000743 Review of Power Reactor Target Sets EAL & EPlan Changes Review - DCC 1

1,2 11/1/2026 12/31/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Problem Identification and Resolution - DCC 4

1,2 11/16/2026 12/4/2026 IP 71152B 000747 Problem Identification and Resolution Security Baseline Inspection - DCC 1

1,2 1/11/2027 1/15/2027 IP 71130.02 000734 Access Control 1,2 1/11/2027 1/15/2027 IP 71130.09 001656 Security Plan Changes D.C. Cook Unit 2 Inservice Inspection 1

2 3/22/2027 4/23/2027 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Radiation Protection Baseline Inspection - DCC 2

1,2 4/19/2027 4/23/2027 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 4/19/2027 4/23/2027 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 4/19/2027 4/23/2027 IP 71124.04 000728 Occupational Dose Assessment Functional Engineering Inspection Placeholder - DCC 3

Prepared on 8/20/2025 9:42:16 AM 2 of 4

Site Inspection Activity Plan 1,2 6/7/2027 6/25/2027 IP 71111.21N 000714 Focused Engineering Inspections (FEI Placeholder)

Prepared on 8/20/2025 9:42:16 AM 3 of 4

Site Inspection Activity Plan D.C. Cook 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count ISFSI Security Inspection 1

5/18/2026 5/22/2026 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations Prepared on 8/20/2025 9:42:16 AM 4 of 4