Draft for Public Meeting: IMC 2574 Inspection of the Advanced Power Reactor Operational Readiness Strategic Performance Area
ML25210A582
Person / Time
Issue date: 07/31/2025
From: O'Bryan P
NRC/NRR/DANU/UARP
To:
References
Download: ML25210A582 (1)


Text

NRC INSPECTION MANUAL NRR INSPECTION MANUAL CHAPTER 2574 INSPECTION OF THE OPERATIONAL READINESS STRATEGIC PERFORMANCE AREA OF THE ADVANCED REACTOR CONSTRUCTION OVERSIGHT PROGRAM (ARCOP)

Effective Date: TBD

Issue Date: xx/xx/xx i

2574 TABLE OF CONTENTS 2574-01 PURPOSE................................................................................................................... 2 2574-02 OBJECTIVES.............................................................................................................. 2 2574-03 APPLICABILITY.......................................................................................................... 2 2574-04 DEFINITIONS.............................................................................................................. 3 2574-05 RESPONSIBILITIES AND AUTHORITIES.................................................................. 3 05.01 Director, Office of Nuclear Reactor Regulation NRR............................................. 4 05.02 Regional Administrator, Host Region.................................................................... 4 05.03 Director, Division of Operating Reactor Safety (DORS), Host Region................... 4 05.04 Director, ARCOP Project Office (NRR/APO).......................................................... 4 05.05 Director, RII Division of Operating Reactor Safety (DORS).................................. 5 05.06 Director, Office of Nuclear Security and Incident Response (NSIR)..................... 5 2574-06 REQUIREMENTS........................................................................................................ 5 2574-07 GUIDANCE.................................................................................................................. 6 07.01 Inspection and Audit Scoping Guidance............................................................... 6 07.02 Creating an Operational Readiness Inspection and Audit Plan............................. 6 07.03 Status of Operational Programs........................................................................... 11 07.04 Noncompliances, Enforcement, and Assessment................................................ 11 07.05 Response to Significant Issues or Events............................................................ 11 2574-08 REFERENCES.......................................................................................................... 11 : Inspection Procedures for Operational Programs.......................................... Att1-1 : Response to Significant Issues or Events..................................................... Att2-1 : Revision History for IMC 2574........................................................................ Att3-1

Issue Date: xx/xx/xx 2

2574 2574-01 PURPOSE To define the inspection and audit program for the operational readiness strategic performance area during construction of advanced power reactors. Advanced reactors include SMRs and microreactors incorporating both LWR and non-LWR technologies, and large LWR or non-LWRs with enhanced safety features.

2574-02 OBJECTIVES 02.01 To provide site-specific inspection and auditing scoping guidance for operational programs identified in a combined operating license (COL), manufacturing license (ML),

construction permit (CP), or operating license (OL) application for an advanced power reactor.

02.02 To assess if a licensee conforms to and correctly implements the preoperational testing portion of the Initial Test Program (ITP) or the Post-Construction Inspection, Testing, and Analyses Program (PITAP).

02.03 To coordinate implementation of the inspection program for the security and safeguards strategic performance area with Inspection Manual Chapter, IMC 2203 (Official Use Only

- Security Related Information), Security Inspection Program for Advanced Reactor Construction, which describes the inspection scope for security inspections.

2574-03 APPLICABILITY 03.01 This IMC is applicable to the fabrication, manufacture, and construction of all commercial advanced nuclear reactors, including SMRs and microreactors incorporating both light water reactor (LWR) and non-LWR technologies, and large LWR or non-LWRs with enhanced safety features. Activities under this IMC may begin when an application for the manufacture or construction of an advanced power reactor facility has been submitted to the NRC and accepted/docketed by the NRC for review.

03.02 This includes applications for a CP, LWA, COL, or ML.This IMC remains in effect until the NRC makes a finding that the acceptance criteria in the COL are met, per 10 CFR 52.103(g), or until an OL is issued for the facility.

03.03 The requirements identified in this IMC are applicable to all advanced power reactor designs. However, plant-specific inspection and auditing plans and inspection procedures (IPs) may differ depending upon the plants design basis and licensing requirements. Some licensees may be exempt from certain regulations and therefore exempt from some operational program requirements. Licensees may also have additional design-specific program requirements not identified in this IMC. When determining the operational readiness inspection and audit scope for a specific project, NRC staff shall consider all operational programs applicable to the licensee.

Issue Date: xx/xx/xx 3

2574 2574-04 DEFINITIONS Applicable ARCOP definitions are in Inspection Manual Chapter 2570, Advanced Reactor Construction Oversight Program General Guidance and Basis Document. For readers convenience, some relevant definitions are also listed below.

a. Audit. A review of an operational program prior to its implementation. A review of an operational program after its implementation is an inspection.
b. Fundamental Safety Functions (FSFs). A set of high-level functions that serve to limit the release of radioactive materials to within established limits over the entire range of licensing basis events. FSFs are discussed in various references, such as in Nuclear Energy Institute (NEI) 18.04, revision 1, "Risk-Informed Performance-Based Technology Inclusive Guidance for Non-Light Water Reactor Licensing Basis Development, (endorsed by Regulatory Guide 1.233). The FSFs are:
1. Control of Heat Generation (Reactivity and Power Control),
2. Control of Heat Removal (including reactor and spent fuel decay heat and heat generated from waste stores), and
3. Radionuclide Retention.
c. Noncompliance. The failure to adhere to a legally binding requirement or a non-legally binding commitments and standards. Legally binding requirements include regulations, technical specifications, license conditions, and NRC Orders. Non-legally binding commitments and standards include commitments made to the NRC, self-imposed requirements to establish and maintain quality, and requirements specified in procurement contracts.
d. Project Vendor. A non-licensed entity that fabricates nearly complete reactor plants or significant portions of safety-significant system modules under contract to an NRC licensee, NRC permit holder, or an applicant for an NRC license or permit.
e. Very Low Safety Significance Issue Resolution (VLSSIR). A process used to discontinue inspection or audit of an issue involving an open question that has ambiguity in the licensing basis, design basis, or applicability of regulatory requirements in which: (1) the resolution of the issue would require considerable staff effort; and (2) the agency has chosen to not expend further effort to resolve the question because the issue would be no greater than Green under the ARCOP or SL IV under the traditional enforcement process, if resolved.

2574-05 RESPONSIBILITIES AND AUTHORITIES The final organizational structure for ARCOP implementation has not been determined.

Current ARCOP IMC drafts are modeled after the organization implemented for the cROP.

Changes will be made to roles and responsibilities if/when future NRC organizational changes are made.

Issue Date: xx/xx/xx 4

2574 05.01 Director, Office of Nuclear Reactor Regulation NRR

a. Concurs with the decision of the Director, ARCOP Project Office (APO), the Regional Administrator of Region 2 (construction inspection organization), and the Regional Administrator (RA) of the host region, that the status of operational and security programs supports the approval of reactor operations. This decision is made at the final assessment meeting described in IMC 2572, Assessment Program for Advanced Reactor Construction Projects.

05.02 Regional Administrator, Host Region

a. Coordinates with the APO Director to inform the NRR Office Director that the status of operational and security programs supports the approval of reactor operations for reactor facilities built in their regions as part of the reactor project final assessment described in IMC 2572.
b. Ensures sufficient host region resources are available to implement the operational and security program inspection and audit plans for advanced power reactor facilities built in their regions.
c. Approves the decision to conduct a reactive inspection (Special Inspection Team (SIT) or Augmented Inspection Team (AIT)) at advanced reactor facilities under construction in the host region.

05.03 Director, Division of Operating Reactor Safety (DORS), Host Region

a. Implements this IMC for advanced reactor facilities built in their region.
b. Coordinates with APO to develop the site-specific operational program inspection and audit plan.
c. Ensures that inspections and audits are documented in accordance with IMC 0618, Advanced Power Reactor Inspection Reports.
d. Dispositions inspection noncompliances per IMC 2571, Dispositioning Advanced Power Reactor Construction Noncompliances, and perform program assessments per IMC 2572.
e. Notifies the host region RA and the Director of APO when the operational readiness inspection and audit plan is complete for an advanced reactor facility being built in their region.
f.

Using the guidance in Attachment 2 of this IMC, recommends to the RA of the host region the decision whether to conduct a reactive inspection for significant events that occur at advanced reactor facilities located in the host region.

05.04 Director, ARCOP Project Office (NRR/APO)

a. Coordinates with the host region RA to inform the NRR Office Director that the status of operational and security programs supports the approval of advanced reactor operations as part of the reactor project final assessment described in IMC 2572.

Issue Date: xx/xx/xx 5

2574

b. Coordinates with the host region to provide technical assistance and inspection and audit support where needed to complete inspection and audit of operational programs in the site-specific operational readiness inspection and audit plans.
c. Provides overall program direction for the ARCOP.
d. Develops and directs the implementation of policies, programs, and procedures for the ARCOP.
e. Provides interpretations and support for information contained in this IMC.
f.

Provides resolution for identified gaps in ARCOP IMC directions and guidance.

g. Ensures that APO coordinates with the host region in development of the site-specific operational readiness inspection and audit plan.
h. Concurs with the decision to conduct a reactive inspection at advanced power reactor facilities under construction.

05.05 Director, RII Division of Operating Reactor Safety (DORS)

a. Ensures coordination between RII DORS and the host region to participate in inspections of the preoperational testing portion of the ITP or PITAP.
b. Provide inspection and audit resources and technical assistance to the host region (if required) for the preoperational testing portion of the ITP or PITAP.
c. Using the guidance in Attachment 2 of this IMC, recommends to the host regions RA, whether to conduct a reactive inspection for significant events that occur at advanced reactor facilities.

05.06 Director, Office of Nuclear Security and Incident Response (NSIR)

a. Provides technical assistance and inspection and audit support to the host region to complete security and safeguards inspections at advanced power reactor facilities under construction.
b. Maintains inspection procedures and inspection and audit guidance for security and safeguards inspections at advanced power reactor facilities under construction.
c. Using the guidance in Attachment 2 of this IMC, recommends to the host regions RA, whether to conduct a reactive inspection for significant security-related events that occur at advanced reactor facilities.

2574-06 REQUIREMENTS 06.01 Inspections and audits of operational programs shall occur in accordance with the site-specific operational readiness and audit plan.

06.02 A site-specific operational readiness and audit plan shall be developed for each advanced power reactor construction project.

Issue Date: xx/xx/xx 6

2574 2574-07 GUIDANCE 07.01 Inspection and Audit Scoping Guidance This IMC establishes uniform operational program inspection and audit scoping methodology for advanced power reactors under construction. Attachment 1 lists operational programs and inspection procedures that are generally applicable to an advanced power reactor facility. The specific operational program requirements for each advanced reactor are expected to vary and are provided in the licensing basis.

Therefore, not all operational programs listed in Attachment 1 may be applicable at each advanced power reactor project. NRC staff should consult the licensing basis to compile a list of applicable operational programs for each project and specify appropriate IPs for inspection and auditing of each inspected or audited program in the operational program inspection and audit scoping plan.

Operational program inspection and audit scope should be adjusted for units under construction at sites where there is an operating unit of similar design and operational requirements. This adjustment gives the licensee credit for existing operational programs where appropriate. In addition, most operational program inspections and audits should not be repeated for nth-of-a-kind (NOAK) unit(s). For those operational programs that include additional inspection and audit scope for NOAK units, inspection or audit should only focus on the differences between the program as applied to the initial unit and the NOAK unit(s).

IMC 2203 describes inspection scoping for advanced reactor security and safeguards programs. IMC 2203 inspection scoping guidance is used to scope security and safeguards inspections.

Some operational programs are inspected under IMC 2573, Inspection of the Advanced Power Reactor Quality of Reactor Plant Construction Strategic Performance Area. For example, equipment qualification programs, such as the environmental qualification (EQ) program, are inspected during IMC 2573 inspections. These programs should not be scoped for inspection under this IMC.

07.02 Creating an Operational Readiness Inspection and Audit Plan The APO staff will create, the host region DORS director will concur with, and the APO Director will approve, an operational program inspection and audit scope for each advanced power reactor being deployed (e.g., manufactured microreactors) or constructed. The process of creating a site-specific operational readiness inspection and audit plan includes identifying the applicable site-specific operational programs; determining through a risk-informed and performance-based screening approach the operational program inspection and audit requirements; and determining the most efficient method and time to conduct operational program inspections and audits.

a. Identifying the Required Site-Specific Operational Programs.

The required operational programs are listed in the FSAR (Part 52), or in the OL application (Part 50). Operational program requirements may also be included in an ML or a CP. Attachment 1 lists the operational programs from Chapter 13.4 of the Standard Review Plan (SRP). Some advanced reactors may not require all of these programs or may require additional operational programs not listed in Attachment 1.

Issue Date: xx/xx/xx 7

2574

b. Operational program inspection and audit scoping considerations.

The NRC staff decides which operational programs will be inspected and audited, and the timing for inspections and audits, using the risk-informed and performance-based methods described in this section. The word audit is used instead of inspection when the operational program is being reviewed prior to its implementation. NRC staff use IPs to conduct audits, but since the programs are not required by a license prior to their implementation, enforcement is not applicable to issues of concern identified during audits. Instead, NRC staff will provide an audit report to the licensee or permit holder that includes a list of observations that would represent program noncompliances if the program was implemented.

1. Risk-informed.

The NRC staff should risk-inform operational program inspection and audit scoping.

This may be done by applying the risk triplet questions for the individual operational programs:

(a)

What can go wrong if the operational program is implemented incorrectly?

(b)

How likely is this?

(c)

What are the consequences?

2. Performance-based.

Performance-based operational program inspection and audit opportunities are situations where execution of the operational program can be directly observed, as opposed to only reviewing implementation documents. For example, observation of emergency planning drills, inspection of installed program hardware, and observing preoperational tests of SSCs are examples of performance-based inspections and audits. Inspectors may combine performance-based inspections and audits with document reviews but should use performance-based inspection and audit observations to inform documents chosen for review, where possible.

3. Other operational program scoping considerations.

(a)

The program is in use at a co-located operating reactor.

(b)

The licensee has implemented fleetwide operational programs.

(c)

The licensee has prior experience implementing operational programs at other reactor plant facilities.

(d)

The program is accredited by an independent 3rd-party organization.

(e)

The degree of overlapping program attributes with other programs.

(f)

The likelihood of inspection or audit identifying significant noncompliances.

(g)

The operational program is inspected under IMC 2573 or another IMC.

Issue Date: xx/xx/xx 8

2574

c. Guidance for determining if an operational program should be included in the ARCOP inspection and audit scope.

NRC staff should use the process described in this section to determine if an operational program should be included in the ARCOP inspection and audit scope. Other risk-informed, performance-based scoping methodologies may be used if appropriate. Figure 1 demonstrates how risk-informed, performance-based inspection and audit scoping may be performed for operational programs for advanced power reactors under construction.

Figure 1. Operational Program Inspection and Audit Scoping Process

1. Can the NRC be reasonably assured of safety without inspecting the operational program during construction?

Inadequate implementation of some operational programs, for various reasons, may not pose a significant risk to the public, plant workers, or the environment during construction or during early operations of the reactor plant. After performing a risk-Can the NRC be reasonably assured of safety (Risk-Informed) without evaluating the OP during construction?

Consider not performing an inspection or audit of the OP during construction Is there a performance-based inspection or audit opportunity during construction?

If risk supports, consider not performing an inspection or audit of the OP during construction Consider lessons learned from past performance and perform an inspection or audit of the OP during construction.

No No Yes Yes

Issue Date: xx/xx/xx 9

2574 informed evaluation of the program as discussed above, the NRC staff may choose not to include these operational programs in the ARCOP inspection and audit scope.

2. Is there a performance-based inspection or audit opportunity during construction?

Some operational programs, or aspects of operational programs, may not have informative performance-based inspection or audit opportunities during construction.

For example, the contamination controls portion of the Radiation Protection operational program has little performance-based opportunity for inspection or audit until reactor operation produces potentially radioactive contamination. Staff should identify the performance-based inspection and audit opportunities for each operational program and should consider omitting those operational programs, or subprograms, that do not have performance-based inspection or audit opportunities during construction from the ARCOP inspection and audit scope. This decision should also be risk-informed such that unacceptable risk associated with program noncompliance is avoided.

3. Consider lessons learned from past performance and perform an inspection or audit of the operation program during construction.

When the risk evaluation for an operational program indicates that the NRC should perform an inspection or audit, and there are adequate performance-based inspection and audit opportunities, then the operational programs should be included in the ARCOP inspection and audit scope. Each operational program inspection and audit should be informed by inspection and audit experience and modified as appropriate to the specific reactor project. This may include adding to, or subtracting from, existing IP guidance.

d. When to perform operational program inspections and audits The NRC inspection and audit strategy for operational programs should be performance-based so that inspections and audits verify the implementation of the program to the extent possible. This generally requires that inspections occur after the programs implementation milestones. However, a risk-informed decision to audit an operational program prior to its implementation may be appropriate for some programs.

Program inspections and audits should be scheduled to optimize the value of the inspections and audits regardless of when the inspection or audit is scheduled in relation to licensing actions. However, since implementation of programs are not required until their implementation milestones, licensees may not be ready for pre-implementation program audits until just before the programs implementation.

e. Modifying the operational program inspection and audit scope.

The NRC staff may modify operational program inspection and audit scope as inspections and audits are completed and the results are assessed (see IMC 2572 for assessment guidance). Planned inspections and audits may be reduced or the scope of planned inspections and audits may be reduced if the licensee demonstrates that they are compliant with the program requirements already inspected and audited and the scope of the completed inspections and audits is sufficient to provide reasonable assurance that other program attributes are also compliant.

Issue Date: xx/xx/xx 10 2574

f.

Importance of the preoperational testing portion of the ITP (LWRs) or the PITAP (Non-LWRs).

The ITP and the PITAP are particularly important in providing assurance that construction and installation of equipment in reactor facilities have been accomplished in accordance with design and licensing requirements. Regulatory Guide 1.68, Initial Test Programs for Water-Cooled Nuclear Power Plants, describes the general scope and depth that the NRC staff considers acceptable for ITPs for LWRs. Similarly, interim staff guidance (ISG) DANU-ISG-2022-06, Post-construction Inspection, Testing, and Analysis Program, describes the general scope and depth that the NRC considers acceptable for testing of non-LWRs.

The ITP and the PITAP are operational programs that include of preoperational and initial startup tests. Preoperational testing consists of those tests conducted following completion of construction of SSCs, but prior to startup. Initial startup testing consists of those test activities that are performed during and following fuel loading. Initial startup tests include activities such as fuel loading, precritical tests, initial criticality, low-power tests, and power-ascension tests. Preoperational testing will be inspected under ARCOP during construction and initial startup testing will be inspected under a separate IMC for each reactor design.

Due to the importance of ITP or PITAP testing, the NRC oversees it in three ways:

1. The first review of the ITP or PITAP is the safety evaluation review for the COL or OL application. This review is a programmatic review of the licensees implementation plan, and the staff uses either RG 1.68 (LWR) or DANU-ISG-2022-06 to verify adequate SSC testing scope and methodologies.
2. The second review of the ITP or PITAP is inspection of pre-operational testing through observation of construction testing or review of construction testing records during vertical slice inspections conducted under IMC 2573. The vertical slice inspections are part of the inspection scope of the Quality of Reactor Plant Construction strategic performance area developed in accordance with IMC 2573.
3. The third layer of the ITP or PITAP oversight is direct observation of system testing after construction of systems, or significant portions of systems, is complete. These inspections may be performed as part of a dedicated inspection area in the project-specific inspection scoping matrix developed per IMC 2573 or scoped separately using the inspection scoping strategy described in this IMC and is performed near the end of construction. Inspections should cover a sampling of risk-significant system tests that were not inspected in the vertical slice inspections, or that test multiple risk-significant systems.
g. Security programs.

IMC 2203 provides guidance for roles and responsibilities associated with inspection of the security and safeguards strategic performance area. IMC 2203 also provides a list of security programs that may be applicable to advanced reactor construction. Some COL licensees and OL applicants may be exempt from certain regulations and therefore exempt from some security and safeguards requirements. Licensees and applicants may also have design-specific requirements for security and safeguards. NSIR, in coordination with the host region and APO, should select those security and safeguards

Issue Date: xx/xx/xx 11 2574 programs to be excluded from the security and safeguards inspection plan dependent upon the plants design and licensing basis.

h. Use of IPs The IPs listed in Attachment 1 may not be completely appropriate for some reactor plant designs. NRC staff may need to supplement, or omit, portions of the IPs. Additional inspection and audit guidance may be taken from other IPs, temporary instructions, or from approved site-specific inspection and auditing planning documents. It is not the intent of this IMC that all sections of the IPs be completed if they are not compatible with specific reactor plant designs. In addition, all sections of the IPs need not be completed to fulfill the objectives of the IPs. If in doubt of the need to complete specific sections of IPs, inspectors should discuss the inspection and audit activities with their supervisors.

07.03 Status of Operational Programs The staff should inform the Director, NRR of the status of the operational programs as part of the final assessment results performed in accordance with IMC 2572. This status report is not meant to be a detailed report on the status of NRC inspections and audits of the programs. Instead, it is meant to inform the Director, NRR of the status of implementation of the programs as required by their license and FSAR.

07.04 Noncompliances, Enforcement, and Assessment NRC staff uses IMC 2571 to screen and characterize operational program noncompliances and IMC 0618 to document operational program findings prior to the transition to operations. Program noncompliances identified after the transition to operations will be dispositioned, documented, and assessed using the appropriate reactor operations oversight process.

07.05 Response to Significant Issues or Events Guidance for responding to significant events at advanced reactor project vendors, manufacturers or construction facilities is contained in Attachment 2 of this IMC.

2574-08 REFERENCES 10 CFR Part 52, Early Site Permits; Standard Design Certifications; and Combined Licenses for Nuclear Power Plants 10 CFR 50.34, Contents of applications; technical information.

RG 1.206, Combined License Applications for Nuclear Power Plants RG 16.8, Initial Test Programs for Water-Cooled Nuclear Power Plants SECY-05-0197, Review of Operational Programs in a Combined License and General Emergency Planning Inspections, Tests, Analyses, and Acceptance Criteria SECY-06-0114, Description of the Construction Inspection Program for Plants Licensed under 10 CFR Part 52

Issue Date: xx/xx/xx 12 2574 IMC 0618, Advanced Power Reactor Inspection Reports IMC 2200, Security Inspection Program for Construction IMC 2200, App. A, Security Construction Inspection Program IMC 2570, Advanced Reactor Construction Oversight Process (ARCOP) General Guidance and Basis Document.

IMC 2571, Dispositioning Advanced Power Reactor Construction Noncompliances, IMC 2572, Assessment of Advanced Reactor Construction Projects.

IMC 2573, Inspection of the Advanced Power Reactor Quality of Construction Strategic Performance Area END List of Attachments: : Inspection Procedures for Operational and Security Programs : Response to Significant Issues or Events : Revision History for IMC 2574

Issue Date: xx/xx/xx Att1-1 2574 : Inspection Procedures for Operational Programs TABLE 1 Program Requirement Inspection Procedures Preservice Inspection / Inservice Inspection 50.55a(g)

ARCOP inspection procedures are in development. Not all operational programs will require their own IPs.

Inservice Testing 50.55a(f)

Environmental Qualification 50.49 Reactor Vessel Material Surveillance 50.60, App. H Preservice Testing 50.55a(f)

Containment Leak Rate Testing 50.54(o)

Issue Date: xx/xx/xx Att1-2 2574 Program Requirement Inspection Procedures Fire Protection 50.48 Process and Effluent Monitoring 50.34(b)(3),

Part 50, App. I Radiation Protection Part 20, Subpart B Non-licensed Plant Staff Training Program 50.120 52.79(a)(33)

Reactor Operator Training 52.79(a)(33), 55.13, 55.31, 55.41, 55.43, 55.45 Reactor Operator Requalification 52.79(a)(34) 50.34(b) 50.54(i)

Issue Date: xx/xx/xx Att1-3 2574 Program Requirement Inspection Procedures 55.59 Emergency Preparedness 50.34(b)(6)(v),

50.47, 50.54(q),

50.54(t)

Security (including training, vehicle and personnel access control, FFD, safeguards contingencies, cyber security, SNM Material Control and Accounting, and Part 37) 50.34(c) 50.34(d) 50.34(e) 50.54(p)(1) 50.54(v)

Part 26, Subpart K 73.54(b)

Part 74, Subpart B Part 37 Quality Assurance (Operation)

Part 21 50.54(a)

Part 50, Appendix B Maintenance Rule 50.65 Motor-Operated Valves 50.55a(b)(3)(ii)

Issue Date: xx/xx/xx Att1-4 2574 Program Requirement Inspection Procedures Startup Testing portion of Initial Test Program 50.34 52.79(a)(28)

Issue Date:

Att2-1 2574 : Response to Significant Issues or Events This attachment provides guidance for responding to significant events at advanced power reactor construction, project vendor, or manufacturing sites subject to the advanced reactor construction oversight program (ARCOP). A significant event is a radiological, safeguards, security, or other event that poses an actual or potential hazard to public health and safety, common defense and security, property, or the environment (ref. Management Directive (MD) 8.3, NRC Incident Investigation Program).

The NRC uses deterministic criteria to decide if a reactive inspection (Special Inspection Team (SIT) or Augmented Inspection Team (AIT)) should be conducted at a manufacturing, project vendor, or construction site. Since irradiated fuel is typically not present at these sites, there is no radiological threat to the public. Therefore, an Incident Investigation Team (IIT) should be not appropriate for events at these sites. MD 8.3 defines the authorities, responsibilities, and basic requirements of personnel investigating significant events.

Upon notification of a significant event, the cognizant inspection organization (Region II construction inspection organization for on-site construction events, the host region for manufacturer, project vendor, operational readiness, or security events) staff should perform the initial review to assess the significance of the event and the level of response required. The cognizant inspection organization staff should also ensure that APO staff are promptly notified of the event. APO staff will assist the cognizant inspection organization as necessary.

If the event meets one or more criteria for an SIT listed below, the host region Regional Administrator (RA), in consultation with the Director, APO and the Director of the cognizant inspection division, makes the decision to initiate an SI or not. The cognizant inspection division will recommend to the host region RA the SIT leader and members.

If the event meets one or more of the AIT criteria, APO staff will coordinate with the appropriate technical branches to provide input into the decision to dispatch an AIT or not. If the event has security-related aspects, then the Division of Preparedness and Response (DPR) in NSIR should also be consulted. The host region RA consults with the Director of NRR and, if applicable, the Director of NSIR to decide on the appropriate response. Per MD 8.3, if consensus cannot be attained, then the Executive Director of Operations (EDO) makes this decision.

In addition to criteria listed in MD 8.3, the following are additional criteria considered in evaluating what type of response, if any, is appropriate:

a. Any significant weather-related event or natural disaster (hurricanes/tornados, earthquakes, fire, flooding, etc.) that may have significant impact on structures, systems, and components (SSCs), or that may invalidate completed ITAAC. The staff should consider the use of either an SIT or AIT depending on the type and amount of damage the facility sustained. The purpose of either would be to monitor and assess the licensees actions to recover damaged or potentially damaged safety-significant SSCs.

If the event involves the loss or damage of special nuclear material (SNM) or sources, coordination with state and local governments should be part of the response and should generally result in an AIT.

b. Any significant security-related issue (e.g., loss or theft of SNM, or potential tampering/sabotage). Either an SIT or AIT should be considered depending on the complexity and significance of the issue. Issues such as the loss or theft of SNM or

Issue Date:

Att2-2 2574 confirmed tampering or sabotage should generally result in an AIT. Issues such as potential tampering, multiple FFD issues, or an unauthorized, actual discharge of a weapon should generally result in an SIT.

c. Onsite accidents resulting in significant damage to safety-significant SSCs or invalidating ITAAC (e.g., crane collapse, train or other significant vehicle accident). Consideration of either an SIT or AIT is appropriate depending on the type and amount of damage sustained. As with responses to weather events discussed above the purpose of either would be to monitor the licensees recovery from damaged safety-significant SSCs or SSCs related to ITAAC.
d. Significant offsite or onsite industrial events that impact the site (e.g., hazardous chemical spill, nearby chemical plant or refinery fire, etc.). An SIT may be appropriate if there is a possibility of significant impact on constructed items or materials.

Consideration of whether airborne chemical fumes could have an adverse impact on risk significant SSCs or other program elements with ITAAC or material in storage should be given. For instance, chlorine gas that contacts stainless steel items may be detrimental.

The purpose of the inspection would be to ensure that the licensee has conducted an adequate evaluation of any potential impacts, including extent of condition. Generally, an AIT would not be warranted.

e. Stop work order issued by the licensee for which the underlying quality issue(s) are not already fully understood. The use of an SIT may be appropriate to ensure that the NRC fully understands the underlying issues. Generally, an AIT would not be warranted.
f.

Plant strike. The use of an SIT may be appropriate to review and/or monitor licensee actions to ensure that malicious mischief is not taking place that could impact the quality of construction. Generally, an AIT would not be warranted.

g. Potential financial impact on programs or quality of work. A r eview of the licensees quality oversight of construction activities with an SIT may be appropriate to determine if degradation of quality or programs is occurring. Inspection or review of the licensees finances is not appropriate. Generally, an AIT would not be warranted.
h. Significant safety conscious work environment (SCWE) issues or allegations which do not have a specific performance aspect that could be addressed thorough the IMC 2572 assessment process or independent licensee action. The use of an SIT may be appropriate. Generally, an AIT would not be warranted.
i.

Any significant issue not covered by the above that NRC management judges to warrant additional inspection beyond what can be accomplished through adjustments to the baseline inspection scope. The use of an SIT may be appropriate. The use of an SIT is generally not appropriate for quality assurance breakdowns. Instead, the use of focused baseline inspections should be considered for these issues.

If an advanced reactor under construction is co-located with an operating facility, NRC oversight organizations should coordinate the response if the event affects both the reactor under construction and the operating reactor. Coordination is important to ensure that any response to an event at a construction site does not have an adverse impact on the operating site.

Inspectors responding to an event at a construction site should be sensitive to potential impacts

Issue Date:

Att2-3 2574 to the operating facility and promptly communicate those to the NRC operations oversight staff for the facility.

Exhibit 1 provides a form for cognizant inspection organization staff to use when documenting the decision to perform a reactive inspection based on evaluation of the criteria listed in MD 8.3 and above. As noted in Exhibit 1, cognizant inspection organizations may customize the form to fit specific organizational protocols, but the criteria should not be changed.

a. If none of the deterministic criteria were met, briefly document the key points of discussion in the Remarks section that were the principal focus areas of the evaluation.

Also, state that no criteria were met in the Response Decision section of the form.

b. If one or more of the criteria were met, briefly indicate the basis for each in the Remarks section of the applicable criteria.
c. Use the Response Decision section to provide the basis for deciding whether to conduct an inspection, and which level of inspection is recommended. M a i n t a i n a r e c o r d o f the decision by placing the evaluation results in Agencywide Documents Access and Management System (ADAMS).
d. Whenever an SIT or AIT is planned, the host region should also notify the licensee of its intentions once a final decision is made.
e. NRC staff planning and conducting the SIT or AIT should follow the process outlined in MD 8.3.

Issue Date:

Att2-4 2574 IMC 2574, Exhibit 1: Decision Documentation for a Construction SI/AIT SITE:

EVENT/ ISSUE DATE:

EVALUATION DATE:

Brief Description of the Event/Issue:

Significant Weather-Related, Natural Disaster, or Man-Made Event Y/N SI Deterministic Criteria Significant damage to safety-significant SSCs or SSCs related to ITAAC.

Remarks:

Y/N AIT Deterministic Criteria Extensive damage to safety-significant SSCs or SSCs related to ITAAC.

Remarks:

Involved a loss or damage to SNM Remarks:

Involved a loss or damage to radiological sources resulting in dose to an individual in excess of applicable regulatory limits.

Remarks:

Significant Security-Related Event Y/N SI Deterministic Criteria Potential tampering or sabotage Remarks:

Unauthorized, actual discharge of a weapon Remarks:

Multiple FFD issues Remarks:

Other (explain in remarks)

Remarks:

Y/N AIT Deterministic Criteria Loss or theft of SNM Remarks:

Confirmed tampering or sabotage Remarks:

Other (explain in remarks)

Remarks:

Issue Date:

Att2-5 2574 Onsite Event Resulting in Significant Damage to Safety-Significant SSCs Y/N SI Deterministic Criteria Significant damage to safety-significant SSCs or SSCs related to ITAAC.

Remarks:

Y/N AIT Deterministic Criteria Extensive damage to safety-significant SSCs or SSCs related to ITAAC.

Remarks:

Significant Offsite or Onsite Industrial Event Y/N SI Deterministic Criteria Possibility of significant impact on stored or constructed items or materials.

Remarks:

Y/N AIT Deterministic Criteria Other/if yes, then provide rationale in remarks block.

Remarks:

Stop Work Order Issued by the Licensee or Permit Holder Y/N SI Deterministic Criteria Stop work order for which the underlying issues are not fully understood.

Remarks:

Y/N AIT Deterministic Criteria Other/ if yes, then provide rationale in remarks block.

Remarks:

Plant Strike Y/N SI Deterministic Criteria Plant strike Remarks:

Y/N AIT Deterministic Criteria Other/ if yes, then provide rationale in remarks block Remarks:

Potential Financial Impact on Programs/Quality Y/N SI Deterministic Criteria Potential financial impact on programs or quality Remarks:

Y/N AIT Deterministic Criteria Other/ if yes, then provide rationale in response decision block Remarks:

Issue Date:

Att2-6 2574 Significant SCWE Issue or Allegation Y/N SI Deterministic Criteria Significant SCWE issue or allegation that cannot be addressed through IMC 2572 or independent licensee action Remarks:

Y/N AIT Deterministic Criteria Other/ if yes, then provide rationale in remarks block.

Remarks:

Other Significant Event Y/N SI Deterministic Criteria Other criteria listed in MD 8.3 or a significant issue not covered and judged by management to warrant additional inspection or follow up.

Remarks:

Y/N AIT Deterministic Criteria Other/ if yes, then provide rationale in remarks block.

Remarks:

RESPONSE DECISION Using the above information and other key elements of consideration as appropriate, document the response decision to the event or issue, and the basis for the decision.

Decision and Details of the Basis for the Decision:

Cognizant Inspection Division Review (Director or designated representative):

Date:

APO Review (Director or designated representative):

Date:

Host Region RA, or designated representative, Approval:

Date:

Note: The above tables are provided as examples only. Cognizant inspection organizations have discretion to modify these tables in their implementing procedures or office instructions.

Issue Date: xx/xx/xx Att3-1 2574 : Revision History for IMC 2574 Commitment Tracking Number Accession Number Issue Date Change Notice Description of Change Description of Training Required and Completion Date Comment Resolution and Closed Feedback Form Accession Number (Pre-Decisional, Non-Public Information)

N/A ML25210A571 Draft version to support public meeting on 8/26/2025 TBD TBD