Transmittal Letter for Renewed License
ML25160A141
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 07/07/2025
From: Michele Sampson
NRC/NRR/DNRL/NLRP
To: Penfield R
Vistra Operations Company
Shared Package
ML25160A130 List:
References
Download: ML25160A141 (1)


Text

Mr. Rod L. Penfield Site Vice President Vistra Operations Company LLC Perry Nuclear Power Plant Mail Stop A-PY-A290 10 Center Road Perry, OH 44081-0097

SUBJECT:

ISSUANCE OF RENEWED FACILITY OPERATING LICENSE NO. NPF-58 FOR PERRY NUCLEAR POWER PLANT, UNIT 1

Dear Rod L. Penfield:

The U.S. Nuclear Regulatory Commission (NRC) has issued Renewed Facility Operating License No. NPF-58 to Vistra Operations Company LLC for Perry Nuclear Power Plant, Unit 1 (Perry). The NRC issued the renewed facility operating license upon completion of its review of your application dated July 3, 2023 (ML23184A081), as supplemented by letters dated June 27, 2024 (ML24180A010), July 24, 2024 (ML24206A150), August 7, 2024 (ML24220A270), September 5, 2024 (ML24249A123), October 21, 2024 (ML24295A352),

November 7, 2024 (ML24312A368), December 19, 2024 (ML24354A265), and January 27, 2025 (ML25027A327).

Renewed Facility Operating License No. NPF-58 for Perry, Unit 1 expires at midnight on November 7, 2046.

The technical basis for issuing the renewed facility operating licenses for Perry is set forth in Safety Evaluation Report Related to the License Renewal of Perry Nuclear Power Plant, Unit 1, issued on May 29, 2025 (ML25148A362). Enclosure 1 to this letter contains the Renewed Facility Operating License No. NPF-58 and Technical Specifications for Perry, Unit 1.

No changes were made to the Technical Specifications as a result of this license renewal.

The NRC staffs evaluation of the environmental review impacts of continued operation under the renewed licenses is provided in the record of decision (ML25160A138) provided in to this letter and in NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 61, Regarding License Renewal of Perry Nuclear Power Plant, Final Report issued on April 30, 2025 (ML25113A032). provides a copy of the related notice of issuance of the renewed license (ML25160A139), as sent to the Office of the Federal Register for publication.

July 7, 2025

R. Penfield If you have any questions regarding this matter, please contact the license renewal project manager, Mr. Vaughn Thomas, by email at Vaughn.Thomas@nrc.gov.

Sincerely, Michele Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosures:

1.

Perry Nuclear Power Plant, Unit 1, Renewed Facility Operating License and Technical Specifications 2.

Record of Decision 3.

Copy of Draft Federal Register Notice cc: Listserv Signed by Sampson, Michele on 07/07/25

Package: ML25160A130 Letter: ML25160A141 Renewed License, Unit 1: ML25160A140 Record of Decision: ML25160A138 Federal Register Notice: ML25160A139

  • via eConcurrence NRR-106 OFFICE PM: DNRL: NLRP*

LA: DNRL: NRLB*

PM: DORL BC DORL*

NAME VThomas KBratcher SWall IBerrios DATE 06/09/2025 06/10/2025 06/13/2025 06/13/2025 OFFICE BC: NMSS*

BC: DNRL*

OGC (NLO)*

BC: DNRL*

NAME SKoenick ANeuhausen MCarpentier MSampson DATE 06/10/2025 06/13/2025 06/21/2025 07/01/2025 OFFICE OD: NRR (A)

D: DNRL*

NAME GBowman MSampson DATE 07/02/2025 Perry Nuclear Power Plant, Unit 1 Renewed Facility Operating License:

ADAMS Accession No. ML25160A140 Technical Specifications:

ADAMS Accession No. ML25160A140 The Technical Specifications did not change as a result of the renewal of the license for Perry Nuclear Power Plant, Unit 1.

Perry Nuclear Power Plant, Unit 1 License Renewal Record of Decision ADAMS Accession No. ML25160A138 Copy of the Draft Federal Register Notice of Renewed Facility Operating License Perry Nuclear Power Plant, Unit 1 ADAMS Accession No. ML25160A139