Ame Centrifug rating May 28, 2025 ACO 25-0043 ATTN: Document Control Desk John W. Lubinski, Director Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Julio Lara, (Acting) Regional Administrator U.S. NRC Region II Marquis One Tower 245 Peachtree Center Avenue N.E., Suite 1200 Atlanta, GA 30303 American Centrifuge Plant; Docket Number 70-7004; License Number SNM-2011 Description of Change for the Fundamental Nuclear Material Control Plans for the American Centrifuge Plant
Dear John Lubinski and Julio Lara:
In accordance with 10 Code ofFederal Regulations (CFR) 70.32(c)(2)(ii), American Centrifuge Operating, LLC (ACO) hereby submits to the U.S. Nuclear Regulatory Commission a description of change for the Fundamental Nuclear Material Control Plan for the American Centrifuge Plant (NR-3605-0005) and Addendum I of the Fundamental Nuclear Material Control Plan for the American Centrifuge Plant - HALEU Demonstration (NR-3605-0005B) as Enclosure 1 of this letter.
The changes noted in Enclosure 1 have been reviewed in accordance with 10 CFR 70.32 and have been determined not to decrease the effectiveness of the Fundamental Nuclear Material Control Plan.
If you have any questions regarding this matter, please contact me at (740) 897-3859.
Sincerely,
~t'~tJi Kelly L. Fitch Regulatory Manager American Centrifuge Operating, LLC 3930 U.S. Route 23 South - P.O. Box 628 Piketon, OH 45661 N01SSZD f'l& NO 2-Ms s
\\<-. &-N - \\ I
John W. Lubinski and Julio Lara May 28, 2025 ACO 25-0043, Page 2 cc:
S. Ani, NRC HQ J. Downs, NRC HQ Y. Faraz, NRC HQ A. Ford, DOE Idaho L. Pitts, NRC Region II M. Reim, DOE-NE D. Woodyatt, NRC HQ to ACO 25-0043 Description of Change for Fundamental Nuclear Material Control Plan/or the American Centrifuge Plant (NR-3605-0005) and Addendum 1 of the Fundamental Nuclear Material Control Plan for the American Centrifuge Plant - HALEU Demonstration (NR-3605-0005B)
Information Contained Within Does Not Contain Export Controlled Information Reviewing Official :
Lori Hawk / ACO Date:
5/27/2025 to ACO 25-0043 Description of Change for Fundamental Nuclear Material Control Plan/or the American Centrifuge Plant (NR-3605-0005) and Addendum 1 of the Fundamental Nuclear Material Control Plan/or the American Centrifuge Plant-HALEU Demonstration (NR-3605-000SB)
PCE Numbers PCE 25-0035 PCE 25-0061 Rev.
0 0
Description/Reason for the Chane:e
Title:
Revision to CSE-CAS-001, (U) Nuclear Criticality Safety Evaluation for the Centrifuge Cascade; LA-3605-0003A, Addendum I of the Integrated Safety Analysis Summary for the American Centrifuge Plant - HALEU Demonstration; LA-3605-0003AG, (U) Classified Information Supporting Addendum I of the Integrated Safety Analysis Summary; NR-3605-0005B, Addendum I of the Fundamental Nuclear Material Control Plan for the American Centrifuge Plant -
HALEU Demonstration; and LA-3605-0002, Environmental Report for the American Centrifuge Plant Description of Change: Revised NCSE-CAS-001 to allow the use of foreign feed material in the centrifuge cascade; and provide additional details about centrifuge movement, removal, installation, and storage of centrifuges. Revised LA-3605-0003A to update Item Relied on For Safety (IROFS) controls. Revised NR-3605-0005B to no longer prohibit special nuclear material from foreign facilities. Revised LA-3605-0003AG to append IROFS wording; clarify design basis fire exemption for riser piping; correct formatting of Safety Function for IROFS; add new IROFS to support centrifuge movement; clarify portable item spacing exemptions; update credited barrier summaries for Events 5.2.1 thru 5.2. 13, 5.2.16 thru 5.2.25, 5.2.27, and 5.2.28; add new credited barrier summary in Table G-2-1; add three NCSEs to the references; made formatting changes; remove unneeded blank pages; and correct a typographical error in ANSI Nl4. I. Revised LA-3605-0002 to no longer prohibit UF6 feed from non-US origin.
Reason for the Change: Clarify NCSE and licensing documentation.
Approval Date 2/20/2025
Title:
Revision to NR-3605-0005, Fundamental uclear Material Control Plan for 3/27/2025 the American Centrifuge Plant; and NR-3605-0005B, Addendum I of the Fundamental Nuclear Material Control Plan for the American Centrifuge Plant -
HALEU Demonstration Description of Change: Revised NR-3605-0005 to change Independent Audit to Independent Assessment to align Quality Assurance Program Description requirements (includes change of terminology such as audit to assessment and auditors to assessors); add contractor to the personnel establishing mass values for Change to SSC?
No No Documents Modified Due to Chane:e NCSE-CAS-001 Rev. 7 LA-3605-0003A Sections 7.3.6.1.1 and 7.3.6.1.3 LA-3605-0003AG Cover Blank, Inside Cover and Blank (G-1 and G-2), ULOEP Blank (G-4), Sections G.7.3.6.1.1, G.7.3.6.1.3, Table G-2-1, References NR-3605-0005B Section I 0.3 LA-3605-0002 Sections 4.2.3.2.1.2 and 4.2.3.2.1.8.1 NR-3605-0005 Sections 4.1,
5.1.1.1.3, 6.3.1. 7.1, 8.1, 13.1 and 13.2 NR-3605-0005B Sections 7.1 and 8.1 ISA Summary Update Reau ired?
Yes No
Documents ISA Change Modified Summary PCE Approval to Due to Update Numbers Rev.
Description/Reason for the Change Date SSC?
Change Required?
secondary standards; change "each inventory period that it is used" to "annually" for the secondary calibration instrumentation calibration frequency; add clarification for the Material Handlers responsibilities; clarify the use of ideal or non-ideal gas law equations to calculate the amount of gas present in a section of the process: and change supplier to augmented staff for the personnel providing Nuclear Material Control and Accountability assessment services.
Reason for the Change: Clarify licensing documentation.