Mr. Rod L. Penfield Site Vice President Vistra Operations Company LLC Perry Nuclear Power Plant Mail Stop A-PY-A290 10 Center Road Perry, OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1 - SAFETY EVALUATION FOR THE LICENSE RENEWAL APPLICATION (EPID NO. L-2023-RNW-0002)
Dear Rod L. Penfield:
By letter dated July 3, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No.ML23184A081), Energy Harbor Nuclear Corporation submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for renewal of Facility Operating License No. NFP-58 for Perry Nuclear Power Plant, Unit 1 (Perry), pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants. Effective March 1, 2024, the facility operating license for Perry was transferred from Energy Harbor Nuclear Generation LLC (owner) and Energy Harbor Nuclear Corporation (operator) to Energy Harbor Nuclear Generation (owner) and Vistra Operations Company LLC (operator) (ML24057A092). Upon the completion of this license transfer, Vistra Operations Company LLC (Vistra or the applicant) assumed the responsibility for all licensing actions under NRC review at the time of the transfer and requested that the NRC continue its review of those actions (ML24054A498). Energy Harbor Nuclear Corporation and Vistra further supplemented the Perry license renewal application (LRA) by letters dated June 27, 2024 (ML24180A010), July 24, 2024 (ML24206A150), August 7, 2024 (ML24220A270), September 5, 2024 (ML24249A123), October 21, 2024 (ML24295A352), November 8, 2024 (ML24312A368),
December 19, 2024 (ML24354A265), January 27, 2025 (ML25027A327), and April 22, 2025 (ML25112A167).
The NRC staff determined that the Perry LRA was complete and acceptable for docketing as communicated by letter dated September 22, 2023 (ML23256A359) and noticed in the Federal Register on September 29, 2023 (88 FR 67373).
The NRC staff has reviewed the Perry LRA and has developed the enclosed Safety Evaluation Related to the License Renewal of Perry Nuclear Power Plant, Unit 1, hereinafter referred to as the Safety Evaluation (SE). The SE reflects the NRC staffs safety review of the LRA, as supplemented, through January 27, 2025.
The next milestone for this project is the Advisory Committee on Reactor Safeguards Full Committee meeting.
May 29, 2025
R. Penfield If you have any questions regarding this matter, please contact the license renewal project manager, Mr. Vaughn Thomas, by e-mail at Vaughn.Thomas@nrc.gov.
Sincerely, Michele Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No. 50-440
Enclosure:
SE cc w/encl: Listserv Signed by Sampson, Michele on 05/29/25
PKG: ML25147A108 LTR: ML25147A109 SE: ML25148A362 Via E-Concurrence NRR-106 OFFICE DEX/ELTB:BC*
DEX/ESEB:BC*
DSS/SCPB:BC*
DRA/APLB:BC*
NAME JPaige**
ITseng**
MValentin**
EDavidson**
DATE 10/16/2024 3/26/2025 10/28/2024 10/30/2024 OFFICE DSS/SNSB:BC*
DNRL/NVIB:BC*
DNRL/NPHP:BC*
DNRL/NCSG:BC*
NAME PSahd**
ABuford**
MMitchell**
SBloom**
DATE 12/12/2024 1/24/2025 10/22/2024 5/05/2025 OFFICE OGC (NLO)*
DNRL:D*
DNRL/NLRP:PM*
DNRL/NLRP:LA*
NAME MCarpentier**
MSampson**
VThomas (ltr)
KBratcher (ltr)
DATE 5/21/2025 5/23/2025 5/23/2025 5/28/2025 OFFICE OGC (NLO)*
DNLR/NLRP:BC*
DNRL:D*
NAME JWachutka (ltr)
ANeuhausen MSampson DATE 5/27/2025 5/28/2025
{date:short}}