Licensee Performance Review, Nuclear Fuel Services, Inc., Public Meeting Slides
ML25136A296
Person / Time
Issue date: 05/07/2025
From: Lindsey Cooke, Nicholas Peterka
NRC/RGN-II/DFRSS
To:
References
Download: ML25136A296 (1)


Text

Licensee Performance Review U.S. Nuclear Regulatory Commission - Region II Division of Fuel Facility Radiological Safety and Security May 7, 2025, 6:00 PM Unicoi County Courthouse, Erwin, TN Nuclear Fuel Services, Inc.

Nicholas Peterka, U.S. NRC Nicholas.Peterka@nrc.gov 404-997-4556 Lindsey Cooke, U.S. NRC lindsey.cooke@nrc.gov 404-997-4836

LICENSEE PERFORMANCE REVIEW Discuss Licensee Performance Address Findings and Performance Meet with NRC Inspectors 2

AGENDA

  • Opening Remarks/ Introductions
  • Discussion of Current Licensee Performance
  • Question & Answer with Public
  • Closing Remarks/ Adjourn Meeting 3

LICENSED ACTIVITIES Nuclear Fuel Services, Inc.

Possess Special Nuclear Material Process and develop uranium products Operate on-site laboratories Treat and discharge plant effluents 4

NRC Inspection Program 5

NRC Core Inspection Program Safety Operations Radiological Controls Facility Support Safeguards Other Areas Resident Inspector NRC Inspectors Category 1 Fuel Facility Category I Fuel Facility

References:

Inspector Manual Chapter 2600 (ADAMS ML20211L835)

Inspector Manual Chapter 2600, Appendix B (ADAMS ML21043A178)

NRC FUEL CYCLE OVERSIGHT Incident Response Enforcement Performance Assessment Allegations Investigations Inspections 6

LICENSEE PERFORMANCE REVIEW PROCESS Emergent Performance or Generic Safety Issues Assessment Inspection Program Adjustment Inputs NRC Review Results NRC Response Other NRC Actions

  • Inspection Results
  • Previous Performance
  • Safety Significance
  • Trends
  • Cross Cutting Issues
  • Corrective Actions No Performance Issues
  • Core Insp. Program
  • Inform the Public Area Needing Improvement (ANI)
  • More Inspections
  • LPR Frequency
  • Inform the Public Or Performance Areas Plant Events Safety Significance Assessment Reactive Inspections Inspection Follow-up 7

LICENSEE PERFORMANCE AREAS

  • Safety Controls
  • Supporting Safety Programs Operational Safety
  • Criticality Controls
  • Criticality Incident Response Criticality Safety
  • Prevention, Detection, &

Mitigation

  • Supporting Fire Safety Programs Fire Protection Safety Operations 8

LICENSEE PERFORMANCE AREAS

  • Members of the Public
  • Plant Workers Radiation Protection
  • Program Implementation
  • Liquid and Gaseous Effluents Effluent Control &

Environmental Protection

  • Processing, Handling, Storage

& Transportation of Waste Waste Management

  • Receipt, Packaging & Delivery of Radioactive Materials Transportation Radiological Controls 9

LICENSEE PERFORMANCE AREAS

  • Configuration Management Program
  • Request for NRC Approval Plant Modifications

LPR RESULTS 2-Year Assessment Period January 1, 2023 - December 31, 2024 11

Inspection Results SAFETY OPERATIONS Two Severity Level 4 Violations FACILITY SUPPORT No violations SAFEGUARDS Two Severity Level 4 Violations RADIOLOGICAL CONTROLS No violations OTHER AREAS No violations 12

LPR RESULTS No program adjustment warranted, or ANI identified No NRC Identified Violations > SL IV Performance Areas No cross-cutting issues No need for additional focus by the NRC currently NRC Follow-up No safety-significant issues No security-significant issues 13

LPR SUMARY

  • NFS conducted activities safely and securely
  • No areas needing improvement were identified in the performance assessment areas
  • NRC will maintain the core (routine) inspection program for the next performance assessment cycle (January 1, 2025 - December 31, 2026) 14