Kairos Power LLC - Notification of Excavations for Hermes Safety-Related Structures
ML25121A227
Person / Time
Site: Hermes File:Kairos Power icon.png
Issue date: 05/01/2025
From: Hastings P
Kairos Power
To: Mark King
Office of Nuclear Reactor Regulation, Document Control Desk
References
KP-NRC-2505-001
Download: ML25121A227 (1)


Text

KP-NRC-2505-001 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE 2101 Rexford Rd, Suite 300E Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211 May 1, 2025 Docket No. 50-7513 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Attention:

Michael King, Acting Director Office of Nuclear Reactor Regulation

Subject:

Kairos Power LLC Notification of Excavations for Hermes Safety-Related Structures

Reference:

Letter, Nuclear Regulatory Commission (NRC) to Kairos Power LLC, Kairos Power LLC -

Issuance of Construction Permit for Hermes Test Reactor, December 14, 2023 (ML23338A254)

Subsequent to the issuance of the Hermes Construction Permit CPTR-6 (vis the referenced letter), Kairos Power has been preparing the Hermes site for construction activities associated with safety-related structures. This letter transmits the notification required by the construction permit condition 3.D. to notify the Director of the Office of Nuclear Reactor Regulation, or the Directors designee, once excavations for safety related structures are open for examination by the NRC.

As described in several audit meetings with NRC staff, the actual foundation design for the Hermes test reactor includes drilled piers that connect the foundation base mat to sound rock and will be part of the safety-related structures. The excavation for the first drilled pier began today, Thursday, May 1, 2025, and is expected to be available for examination on Monday, May 5, 2025. Subsequent excavations for the remaining drilled piers will be completed over approximately the next three months, subject to construction schedule variability. Kairos Power will remain in close contact with NRC project management to coordinate any requested examinations and inspections.

If you have questions or need additional information, please contact Michael Ellett at ellettmic@kairospower.com or (704) 247-6310, or Drew Peebles at peebles@kairospower.com or (704) 275-5388.

Sincerely, Peter Hastings, PE Vice President, Regulatory, Quality, and Public Affairs

KP-NRC-2505-001 Page 2 xc:

Gregory Bowman, Deputy Director for New Reactors Jeremy Bowen, Director, Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU)

Jonathan Greives, Deputy Director, DANU Mehdi Reisi Fard, Deputy Director, DANU Joshua Borromeo, Chief, NRR Advanced Reactor Licensing Branch Louis McKown, Chief, Region II Reactor Projects Michael Orenak, Project Manager, NRR Advanced Reactor Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Cayetano Santos Jr., Project Manager, NRR Advanced Reactor Licensing Branch Anthony Ponko, Senior Construction Project Inspector, Region II Engineering Branch 3