May 8, 2025 Gayle Elliott, Director Licensing and Regulatory Affairs Framatome Inc.
3315 Old Forest Road Lynchburg, VA 24501
SUBJECT:
THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS ACCEPTANCE FOR THE REVIEW OF FRAMATOMES TOPICAL REPORT, ANP-10323, REVISION 1, SUPPLEMENT 1P, REVISION 0, ONE GALILEO: FUEL ROD THERMAL-MECHANICAL METHODOLOGY FOR PRESURRIZED WATER REACTORS (EPID L-2025-TOP-0015)
Dear Gayle Elliott:
By letter dated April 1, 2025 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML25092A022), Framatome, Inc. (Framatome) submitted Topical Report (TR) ANP-10323, Revision 1, Supplement 1P, Revision 0, One GALILEO: Fuel Rod Thermal-Mechanical Methodology for Pressurized Water Reactors, for U.S. Nuclear Regulatory Commission (NRC) staffs review and approval. As stated in your letter, the ANP-10323, Revision 1, Supplement 1P, Revision 0 (One GALILEO) replaces legacy fuel performance models with updated benchmarked models, which can be incorporated into the utility-specific reload design process. Framatome is requesting approval of the TR by May 2026. A pre-submittal meeting was held on November 12, 2024 (ADAMS Accession No. ML24312A023).
The NRC staff has found that ANP-10323, Revision 1, Supplement 1P, Revision 0, contains sufficient information to begin its detailed technical safety review. Planned milestones, estimated level of effort and schedule assumptions are provided below. To facilitate the review, the NRC staff plans to conduct an audit by August 29, 2025 (tentative), and issue Requests for Additional Information (RAIs) by October 10, 2025, the draft safety evaluation (SE) by April 24, 2026, and final SE by August 30, 2026, as annotated in the enclosed schedule. The draft SE completion date assumes 60 days for RAI responses and may be adjusted, if necessary, to accommodate any delays in the submittals. The enclosed schedule includes planned milestones dates for the overall review.
The NRC staff will notify Framatome if the Advisory Committee on Reactor Safeguards (ACRS) plans to review this TR. If the ACRS review is needed, the NRC staff estimates that the subcommittee and full committee meetings would occur in June 2026, and July 2026, respectively to facilitate this effort. The specific meeting dates will be confirmed and scheduled later if an ACRS review of this TR is deemed necessary.
Additionally, the NRC staff estimates that it will require approximately 800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> to complete the safety review. Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff-hours will be billed accordingly.
If you have any questions regarding the TR review, please contact me at 301-415-6695 or via email at Ngola.Otto@nrc.gov.
Sincerely,
/RA/
Ngola A. Otto, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902041
Enclosure:
Initial Review Schedule
Enclosure Initial Review Schedule Milestone Planned Date Initial Submittal April 1, 2025 Acceptance June 2, 2025 Conduct Audit August 29, 2025 Issue Requests for Additional Information (RAIs) to Framatome October 10, 2025 Response to RAIs December 12, 2025 Issue Draft Safety Evaluation (SE)
April 24, 2026 Advisory Committee on Reactor Safeguards (ACRS)
Subcommittee Meeting June 2026 ACRS Full Committee Meeting July 2026 Issue Final SE to Framatome August 30, 2026
SUBJECT:
THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS ACCEPTANCE FOR THE REVIEW OF FRAMATOMES TOPICAL REPORT, ANP-10323, REVISION 1, SUPPLEMENT 1P, REVISION 0, ONE GALILEO: FUEL ROD THERMAL-MECHANICAL METHODOLOGY FOR PRESURRIZED WATER REACTORS (EPID L-2025-TOP-0015) DATED MAY 8, 2025 DISTRIBUTION:
PUBLIC RidsACRS_MailCTR Resource RidsNrrLADHarrison Resource RidsOgcMailCenter Resource RidsNrrDorlOd Resource RidsNrrDssSFNB RidsNrrDorlLlpb Resource RidsNrrDssResource SKrepel, NRR JRankin, NRR JMessina, NRR PRaynaud, NRR GGeorge, NRR NOtto, NRR EXTERNAL DISTRIBUTION:
Morris.Byram@Framatome.com ADAMS Accession Number: ML25121A135
- e-Concurrence NRR-004 OFFICE NRR/DORL/LLPB/PM*
NRR/DORL/LLPB/LA*
NRR/DSS/SFNB/BC*
NRR/DORL/LLPB/BC (A)*
NAME Notto DHarrison SKrepel JRankin DATE 5/6/2025 5/7/2025 5/7/2025 5/8/2025 OFFICE NRR/DORL/LLPB/PM NAME Notto DATE 5/8/2025 OFFICIAL RECORD COPY