IR 05000302/2024002

From kanterella
(Redirected from ML25071A202)
Jump to navigation Jump to search
Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 NRC Inspection Report No. 05000302/2024002
ML25071A202
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/13/2025
From: Eve E
NRC Region 1
To: Reid B
ADP CR3
References
IR 2024002
Download: ML25071A202 (1)


Text

March 13, 2025

SUBJECT:

ACCELERATED DECOMMISSIONING PARTNERS (ADP) CR3, LLC, CRYSTAL RIVER UNIT 3 - NRC INSPECTION REPORT NO. 05000302/2024002

Dear Billy Reid:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection under Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program, at the permanently shut down Crystal River Nuclear Plant Unit 3 (CR3). The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and the conditions of your license. The inspection consisted of observations by the inspectors, interviews with site personnel, a review of procedures and records, and plant walkdowns. The results of the inspection were discussed with you and other members of your staff on January 29, 2025, and are described in the enclosed report.

Within the scope of this inspection, no violations of more than minor safety significance were identified.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter, its enclosure, and your response, if any, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.

No reply to this letter is required. Please contact Storm Veunephachan of my staff, at 610-337-5366, if you have any questions regarding this matter.

Sincerely, Elise Eve, Team Leader Decommissioning Team Decommissioning, ISFSI, and Reactor Health Physics Branch Division of Radiological Safety and Security

Docket No.

05000302 License No. DPR-72 cc w/encl: Distribution via ListServ Enclosure:

Inspection Report No. 05000302/2024002 ELISE EVE Digitally signed by ELISE EVE Date: 2025.03.13 13:34:17 -04'00'

ML25071A202 OFFICE DRSS/RI

DRSS/RI

NAME SVeunephachan/sv EEve/ee

DATE 03/013/2025 03/13/2025

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Nos.

05000302

License Nos.

DPR-72

Report Nos.

05000302/2024002

Licensee:

Accelerated Decommissioning Partners CR3, LLC (ADP)

Facility:

Crystal River Unit 3 (CR3)

Location:

Crystal River, FL

Inspection Dates:

July 1, 2024 - December 31, 2024

Inspectors:

Storm Veunephachan, Senior Health Physicist

Decommissioning, ISFSI, and Reactor Health Physics Branch

Division of Radiological Safety and Security

Gunnar Eklund, Health Physicist

Decommissioning, ISFSI, and Reactor Physics Branch

Division of Radiological Safety and Security

Approved By:

Elise Eve, Team Leader

Decommissioning Team

Decommissioning, ISFSI and Reactor Health Physics Branch

Division of Radiological Safety and Security

EXECUTIVE SUMMARY

Accelerated Decommissioning Partners CR3, LLC (ADP)

Crystal River Unit 3

NRC Inspection Report No. 05000302/2024002

An announced decommissioning inspection was completed on December 31, 2024, at the

permanently shutdown Crystal River Unit 3 (CR3). The inspection included a review of

design changes and modifications, corrective actions, occupational radiation exposure,

safety conscious work environment, financial assurance, decommissioning performance

and status reviews, fire protection, effluent monitoring, final status surveys, and solid

radioactive waste management and transportation of radioactive materials. The inspection

consisted of observations by the inspectors, interviews with site personnel, a review of

procedures and records, and plant walkdowns. The NRC's program for overseeing the

safe decommissioning of a shutdown nuclear power reactor is described in Inspection

Manual Chapter (IMC) 2561, Decommissioning Power Reactor Inspection Program.

Based on the results of this inspection, no violations of more than minor safety significance

were identified.

REPORT DETAILS

1.0

Background

On February 20, 2013, Duke Energy sent a letter [Agency Documentation and

Management System Accession Number ML13056A005] to the NRC certifying the

permanent cessation of power operations and permanent removal of fuel from the

reactor. This met the requirements of Title 10 of the Code of Federal Regulations

(10 CFR) 50.82(a)(1)(i) and 50.82(a)(1)(ii). On June 14, 2019, the NRC received a

license transfer application [ML19170A209] and conforming amendment request filed

by the Duke Energy Florida (DEF), LLC on behalf of itself and Accelerated

Decommissioning Partners (ADP) CR3, LLC. The application sought NRC approval of

the direct transfer of Facility Operating License No. DPR-72 for CR3 and the general

license for the CR3 ISFSI from the current holder, DEF to ADP CR3, which is a wholly

owned subsidiary of ADP, LLC, which the NRC approved on April 1, 2020

[ML20069A023]. On October 1, 2020, ADP and Duke Energy successfully completed

the transaction.

CR3 was inspected under the Actively Decommissioning (DECON), No Fuel in the

Spent Fuel Pool category as described in IMC 2561 during this inspection period.

2.0

Active Decommissioning Performance and Status Review

The inspectors performed on-site decommissioning inspection activities on August

12 - 16, 2024, October 21 - 24, 2024, December 09 - 12, 2024 and supplemented by

in-office reviews and periodic phone calls. The inspection consisted of observations by

the inspectors, interviews with site personnel, a review of procedures and records, and

site walk-downs.

2.1

IP 40801, Problem Identification and Resolution at Permanently Shutdown Reactors

a. Inspection Scope

The inspectors assessed the implementation and effectiveness of ADPs Corrective

Action Program (CAP) by reviewing a sampling of issues, non-conformances, and any

conditions adverse to quality that were entered into the CAP. The inspectors reviewed

a representative selection of CAP documents to determine if a sufficiently low threshold

for problem identification existed, if follow-up evaluations were of sufficient quality, and

if ADP assigned timely and appropriate prioritization for issue resolution commensurate

with issue significance. The inspectors attended several management review

committee meetings to determine if ADP management was engaged in issue

disposition and resolution. Additionally, the inspectors interviewed site personnel

responsible for the CAP. The inspectors reviewed site audits for the past year to

determine if they were thorough and that corrective actions were initiated if necessary.

The inspectors interviewed the Employee Concerns Program representatives and

several employees to assess site safety culture.

b. Observations and Findings

The inspectors determined that issues had been identified, entered into the CAP, and

evaluated commensurate with their safety significance through document review and

discussion. The inspectors noted adequate management engagement during

management review committee meetings. The inspectors determined that the quality

assurance organization was sufficiently independent and that the audits and self-

assessments conducted included appropriate scrutiny of licensee performance. The

inspectors verified that audits were performed by qualified individuals independent of

the organization being audited and that management reviewed the audits, self-

assessments, and associated corrective actions. The inspectors verified that the audits

and self-assessments were performed in the appropriate timeframe and any

weaknesses identified were captured within the CAP. The inspectors determined that

the site had an appropriate focus on a safety conscious work environment and that

employees were free to raise concerns.

c. Conclusions

No violations of more than minor significance were identified.

2.2

IP 71801 Decommissioning Performance and Status Reviews at Permanently

Shutdown Reactors

a. Inspection Scope

The inspectors reviewed documentation and met with ADP management to discuss

staffing, status of decommissioning and upcoming activities, among other topics to

verify whether the licensee had conducted activities in accordance with regulatory and

license requirements. The inspectors performed several plant walk-downs to assess

field conditions and decommissioning activities by assessing material condition of

structures, systems, and components, housekeeping, system configurations, and

worker level of knowledge or procedure use and adherence. These walk-downs

included all levels of the reactor building, auxiliary building, waste loadout area and

select final status survey units. The inspectors observed select pre-job briefs for reactor

building demolition and waste loadout.

The inspectors reviewed documentation and discussed with ADP and Duke Energy the

overall financial status of decommissioning for Crystal River and evaluated the use of

decommissioning trust funds to determine if they were appropriately used in

accordance with regulatory requirements. The inspectors also discussed any significant

changes to the estimated cost for, and any potential significant delays to, the

decommissioning schedule.

b. Observations and Findings

The inspectors noted that during this inspection period, ADP prepared for and began

internal reactor building demolition and finishing internal auxiliary building demolition.

The inspectors observed staging and preparation for reactor coolant bleed tank

dismantlement and removal and preparations for open air demolition for the auxiliary

building. This included conducting walk-downs across all levels of the auxiliary building

where there has been scabbling and other decontamination efforts. The inspectors also

reviewed the multi-phase auxiliary building demolition plan. The inspectors observed

open air demolition of the auxiliary building once internal demolition was completed.

The inspectors observed internal demolition of the D-rings for the reactor building. This

was completed by conducting walk-downs and observing the work area and observing

the waste loadouts for the debris. The inspectors observed final large bore piping

removal inside the reactor building. The inspectors reviewed the reactor building

demolition plans. The inspectors noted that, for the areas of the plant toured, the

material condition and housekeeping were adequate. The inspectors determined that

staffing was appropriate for the current stage of decommissioning and training

programs were being appropriately implemented.

The inspector reviewed financial assurance documentation, including the annual report

on the status of decommissioning funding and met with ADP and Duke Energy staff to

determine whether the funds were used as expected and if any changes could

significantly impact the sites decommissioning financial assurance. The inspectors

determined that the licensee has used funds in accordance with regulatory

requirements and have no significant deviations from the decommissioning schedule.

c. Conclusions

No violations of more than minor significance were identified.

2.3

IP 83750, Occupational Radiation Exposure at Permanently Shutdown Reactors

a. Inspection Scope

The inspectors observed activities, reviewed documentation, and interviewed

personnel associated with occupational radiation exposure to determine the adequacy

of protection of worker health and safety. The inspectors conducted site walk-downs to

verify and assess radiological postings and contamination boundaries. The inspectors

observed RP technicians performing job coverage and surveys to determine if

implementation of radiological work controls, training and skill level, and

instrumentation were sufficient for the activities being performed. The inspectors

reviewed radiation work permits to determine if radiation work activities were pre-

planned effectively to limit worker exposure. The inspectors reviewed the radiation

protection survey plan to prepare for open air demolition of the auxiliary building and

the open-air demolition air sampling plan. The inspectors reviewed dose records to

determine if occupational doses were within regulatory limits. The inspectors observed

several instrument source checks and calibrations to assess function and proper use of

the instruments. The inspectors reviewed bioassay procedures and compensatory

measures.

The inspectors reviewed documentation and conducted walk-downs of select sealed

sources to ensure ADP maintained adequate controls. These reviews included leak

test records and physical verification checks.

b. Observations and Findings

The inspectors verified technician training and qualifications were up to date. The

inspectors verified that radiological work was planned, and post job reviews were

performed as needed and were effective in limiting worker exposure and occupational

dose was acceptable for the scope of the radiological activities performed. The

inspectors determined that RP (Radiation Protection) staff effectively controlled work

activities, survey records were clear and complete, and RP technicians used

appropriate instruments for the surveys. The inspectors verified technician training and

qualifications were up to date. The inspectors determined that the licensee

performance of source and calibration checks were adequately performed, and the

staff conducting these activities was sufficiently knowledgeable of the instruments and

the site procedures. The inspectors notably observed source checks of handheld

radiation instrumentation as well as personnel monitoring instrumentation to prevent

the release of radioactive material. The inspectors interviewed RP staff for bioassay

methods and measurements. The inspectors noted that there had been no required

bioassay measurements taken but reviewed all bioassay procedures and

compensatory measures. The inspectors determined that the sites sealed sources

were leak tested with the appropriate frequency and were controlled adequately.

The inspectors observed the smearing and surveying of trucks exiting the radiological

controlled area and unloading of concrete debris to ensure there was no spread of

radioactive material. The inspectors conducted walk-downs of the air sampling stations

located around the open-air demolition of the auxiliary building and the dust mitigation

efforts by multiple misters. The inspectors determined the radiological surveying of

trucks was adequate to control the release of radioactive material and the air sampling

stations were positioned in accordance with the sites air sampling plan for open air

demolition.

c. Conclusions

No violations of more than minor significance were identified.

2.4

IP 83801, Inspection of Remedial and Final Surveys at Permanently Shutdown

Reactors

a. Inspection Scope

The inspectors reviewed documentation related to Final Status Surveys (FSS) that

included remediation plans for select areas and at-risk FSS areas. The inspectors

observed remediation and final status surveying of a select area and observed

radiation instrumentation source checks and chain of custody controls.

b. Observations and Findings

The inspectors observed piping removal and subsequent final status surveying. The

inspectors note that this is at-risk and is demarcated as such within the survey plans

until final license termination plan approval. The inspectors determined that the

instruments used for final status surveying were adequately source checked with

adequate chain of custody controls.

c. Conclusions

No violations of more than minor significance were identified.

2.5

IP 84704, Radioactive Waste Treatment, and Effluent and Environmental Monitoring

a. Inspection Scope

The inspectors reviewed activities and documentation associated with radioactive

effluent control and site radiological environmental monitoring program (REMP) to

assess the effectiveness of site radiological programs. The inspectors reviewed liquid

effluent batch release permits, licensee audits, the annual radioactive effluent release

report, and the annual radiological environmental operating report. The inspectors

toured selected environmental monitoring stations to determine the adequacy of

location of instrumentation and observed sampling of groundwater and collection of air

monitor samples. The inspectors conducted walk-downs of selected effluent release

treatment system and monitoring points and reviewed 10 CFR 50.75(g) recordkeeping

practices and selected records. The inspectors conducted walkdowns of the effluent

treatment system modified in the prior inspection period and reviewed under the 10 CFR 50.59 process applicability determination.

b. Observations and Findings

The inspectors verified that effluent releases to the environment had been properly

controlled, monitored, and quantified as required by NRC regulations. The inspectors

verified that the long-term groundwater monitoring report, the annual radioactive

effluent release report, and the annual radiological environmental operating report

demonstrated that calculated doses were below regulatory dose criteria listed in 10 CFR 50, Appendix I. The inspectors verified that ADP maintained records as required

by 10 CFR 50.75(g) and had the ability to promptly access specific records requested

by the inspectors. Additionally, the inspectors verified effluent sampling equipment

were checked, calibrated, and maintained as specified in the ODCM. The inspectors

verified sampling stations were accessible and as described in the ODCM. The

inspectors verified the ODCM has been updated from its current revision. The

inspectors verified the effluent treatment system was adequately described and

modified to treat radioactive effluents for batch releases.

c. Conclusions

No violations of more than minor significance were identified.

2.6

IP 86750, Solid Radioactive Waste Management and Transportation of Radioactive

Materials

a. Inspection Scope

The inspectors observed activities, interviewed personnel, performed walkdowns, and

reviewed documentation to assess the licensees programs for handling, storage, and

transportation of radioactive material. The inspectors observed workers handling and

packaging radioactive waste and performed walk-downs of radioactive waste storage

locations, including the waste loadout area, temporary radioactive material storage in

the reactor building and auxiliary building. The inspectors observed personnel

surveying, labeling, and placarding vehicles used for transporting radioactive waste

and reviewed work packages for shipments of radioactive waste. The review included

records of shipment packaging, surveying, labeling, marking, placarding, vehicle

checks, and emergency instructions to determine compliance with NRC and

Department of Transportation (DOT) regulations. The inspectors reviewed training

records to determine if radwaste personnel were qualified to implement the site solid

radwaste program.

b. Observations and Findings

The inspectors determined that solid radioactive waste was adequately stored and

monitored and worker radwaste training and qualifications were up to date. The

inspectors determined that radioactive waste shipping paperwork was properly

completed, and ADP and ADP contractor personnel were knowledgeable of their duties

and responsibilities. The inspectors determined that radioactive waste shipped was

properly described, classified, packaged, marked, and labeled, and was in proper

condition for transport. The inspectors determined that ADPs radwaste shipments

were in compliance with NRC and DOT regulations. Specifically, the inspectors

reviewed the radioactive waste shipment packages for the reactor coolant bleed tanks.

c. Conclusions

No violations of more than minor significance were identified.

4.0 Exit Meeting Summary

On January 29, 2025, the inspectors presented the inspection results to Billy Reid, Site

Vice President, and other members of the ADP organization. No proprietary information

was documented in this report