ML25059A254
| ML25059A254 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 02/28/2025 |
| From: | Sterio A Constellation Energy Generation |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| JAFP-25-0015 | |
| Download: ML25059A254 (1) | |
Text
Constellation.
James A. FitzPatrick NPP P.O. Box 110 JAFP-25-0015 February 28, 2025 Lycoming, NY 13093 Alexander Sterio Site Vice President - JAF U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555
Subject:
Reference:
Dear Sir or Madam:
James A FitzPatrick Nuclear Power Plant Renewed Facility Operating License No. DPR-59 NRC Docket No. 50-333 Closure of Interim Report of a Deviation or Failure to Comply Associated with General Electric Thermal Overload Relay, Model CR124G011, Part Number DD317A7861P003 JAF letter, Interim Report of a Deviation or Failure to Comply Associated with General Electric Thermal Overload Relay, Model CR124G011, Part Number DD317 A7861 P003, JAFP-24-0063, dated November 25, 2024 On November 25, 2024, James A. FitzPatrick Nuclear Power Plant (JAF) submitted an interim report in accordance with 10 CFR 21.21 (a)(2) (Reference).
This letter is being provided to update the status of the interim report and the completion of the evaluation. The condition discussed in the Reference was evaluated to not cause a substantial safety hazard based on its potential effect on safety functions at JAF.
Therefore, this condition is determined to not be reportable in accordance with 10 CFR 21.21.
There are no new regulatory commitments contained in this letter. Should you have any questions regarding this submittal, please contact Mark Hawes, Regulatory Assurance, at (315) 349-6659.
Sincerely,
~e~eitl~
Site Vice President AS:CT:mh cc: next page
cc:
Director, Office of Nuclear Reactor Regulation NRC Region I Administrator NRC Resident Inspector NRC Project Manager JAFP-25-0015 Page 2 of 2