From:
Yawar Faraz To:
Fitch, Kelly L Cc:
Shana Helton; Samuel Bazian; Diana Woodyatt; Leonard Pitts; Noel Pitoniak; Ravi Penmetsa; Ryan Ruppert; Christine Pineda; Mauri Lemoncelli; Charles Teal; Ravi Penmetsa; Kimyata Morgan-Butler; Robert Sun; Jenny Weil; Bradley Davis; Steve McCarthy; James Hammelman; Eben Allen; Suzanne Ani; Patricia Jehle; Thomas Vukovinsky; Christine Saah Nazer; Reim, Michael; Joseph Goodridge; Snider, Mathew D
Subject:
NRC"s acceptance for detailed review of ACO"s license amendment request for Phase III HALEU operations at the ACP in Piketon OH Date:
Monday, February 10, 2025 1:07:00 PM
Dear Kelly L. Fitch,
The U.S. Nuclear Regulatory Commission (NRC) staff has completed an acceptance review of the submittal from American Centrifuge Operating, LLC., dated December 19, 2024 (ML24366A069),
requesting for the continued high-assay low-enriched uranium (HALEU) operations (Phase III) at the American Centrifuge Plant in Piketon, Ohio. We have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your request has been assigned Enterprise Project Identifier (EPID) L-2025-LLA-0000. Please reference that EPID number and Docket Number 70-7004 in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Although the NRC staff is prioritizing the review of your submittal - based on our preliminary review, projection of current review schedules, and available resources, we now anticipate completing our review by June 23, 2025. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require up to 400 staff hours, which corresponds to about $126,800.00
($317.00/hr.). This estimate could change based on future submittals particularly related to the HALEU contract between American Centrifuge Operating and the Department of Energy. We will promptly communicate any significant changes to this estimate.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this e-mail will be available for public inspection in the NRC Public Document Room (PDR) or electronically from the Publicly Available Records System component of the Agencywide Documents access and Management System (ADAMS). The PDR is currently open Monday-Friday by appointment only. To schedule an appointment, you may submit your request to the PDR via email at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays. The ADAMS database is accessible from the NRC Web site at http://www.nrc.gov/
Yawar H. Faraz, Senior Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission, MS T-4A60 Washington DC 20555 Ph: 301-415-7220