ML25027A457

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000285/2024-004
ML25027A457
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 02/05/2025
From: Jeremy Groom
NRC/RGN-IV/DRSS
To: Via T
Omaha Public Power District
Shared Package
ML25027A457 List:
References
EA-RIV-2024-0050 IR 2024004
Download: ML25027A457 (1)


See also: IR 05000285/2024004

Text

February 4, 2025

EA-RIV-2024-0050

Troy Via, Chief Operations Officer

and Vice President Utility Operations

Omaha Public Power District

Fort Calhoun Station

Mail Stop FC-2-4

9610 Power Lane

Blair, NE 68008

SUBJECT:

FORT CALHOUN STATION - NRC INSPECTION

REPORT 050-00285/2024-004

Dear Troy Via:

This letter refers to the U.S. Nuclear Regulatory Commission (NRC) decommissioning

inspection conducted on December 9-11, 2024, at the Fort Calhoun Station near Blair,

Nebraska. The purpose of the inspection was to examine activities conducted under your

license as they relate to public health and safety, the common defense and security, and

compliance with the Commissions rules and regulations, and with the conditions of your

license. Within these areas, the inspection consisted of selected examination of procedures and

representative records, observation of activities, and interviews with personnel. Specifically, the

inspectors reviewed your implementation of decommissioning activities; fire protection program;

and solid radioactive waste management and transportation of radioactive materials program.

The inspection results are documented in the enclosure to this letter. The NRC inspectors

discussed the preliminary results of the decommissioning inspection with members of your staff

on December 11, 2024, at the conclusion of the onsite portion of the inspection. A final exit

briefing was conducted with your staff via videoconference on January 22, 2025.

Based on the results of this inspection, one apparent violation was identified and is being

considered for escalated enforcement action in accordance with the NRC Enforcement Policy.

The Enforcement Policy is available on the NRCs website at http://www.nrc.gov/about-

nrc/regulatory/enforcement/enforce-pol.html. The apparent violation involves the failure to

design and prepare radioactive materials for shipment so that, under conditions normally

incident to transportation, the radiation level does not exceed 200 millirem per hour at any point

on the external surface of the package, as required by Title 49 of the Code of Federal

Regulations (49 CFR) 173.441. Pursuant to 10 CFR 71.5, licensees who deliver licensed

material to a carrier for transport must comply with the requirements of the U.S. Department of

Transportation regulations in 49 CFR Parts 171 through 180.

T. Via

2

In addition, since your facility has not been the subject of escalated enforcement actions within

the last 2 years, and based on our understanding of your corrective actions, a civil penalty may

not be warranted in accordance with Section 2.3.4 of the Enforcement Policy. The final decision

will be based on you confirming on the license docket that the corrective actions previously

described to the NRC staff have been or are being taken.

Before the NRC makes its enforcement decision, we are providing you an opportunity to:

(1) respond to the apparent violation addressed in this inspection report within 30 days of the

date of this letter or (2) request a pre-decisional enforcement conference (PEC). If a PEC is

held, it will be open for public observation and the NRC will issue a press release to announce

the time and date of the conference. Please contact Mr. Jeffrey Josey at 817-200-1249 or

Jeffrey.Josey@nrc.gov within 10 days of the date of this letter to notify the NRC of your

intended response to either provide a written response or participate in a PEC. A PEC should

be held within 30 days of the date of this letter.

If you choose to provide a written response, it should be clearly marked as a Response to

Apparent Violation in NRC Inspection Report (05000285/2024-004); EA-RIV-2024-0050 and

should include: (1) the reason for the apparent violation or, if contested, the basis for disputing

the apparent violation; (2) the corrective steps that have been taken and the results achieved;

(3) the corrective steps that will be taken; and (4) the date when full compliance will be

achieved. Your response may reference or include previously docketed correspondence, if the

correspondence adequately addresses the required response. To the extent possible, your

response should not include any personal privacy or proprietary information so that it can be

made available to the public without redaction.

Additionally, your written response should be sent to the U.S. Nuclear Regulatory Commission,

ATTN: Document Control Center, Washington, DC 20555-0001, with a copy to the Director,

Division of Radiological Safety & Security, Region IV, 1600 East Lamar Boulevard Arlington,

TX 76011, and emailed to R4Enforcement@nrc.gov, within 30 days of the date of this letter. If

an adequate response is not received within the time specified or an extension of time has not

been granted by the NRC, the NRC will proceed with its enforcement decision or schedule a

PEC.

If you choose to request a PEC, the conference will afford you the opportunity to provide your

perspective on these matters and any other information that you believe the NRC should take

into consideration before making an enforcement decision. The decision to hold a PEC does not

mean that the NRC has determined that a violation has occurred or that enforcement action will

be taken. This conference would be conducted to obtain information to assist the NRC in

making an enforcement decision. The topics discussed during the conference may include

information to determine whether a violation occurred, information to determine the significance

of a violation, information related to the identification of a violation, and information related to

any corrective actions taken or planned.

In presenting your corrective actions, you should be aware that the promptness and

comprehensiveness of your actions will be considered in assessing any civil penalty for the

apparent violations. The guidance in NRC Information Notice 96-28, Suggested Guidance

T. Via

3

Relating to Development and Implementation of Corrective Action, may be helpful in preparing

your response (Agencywide Documents Access and Management System (ADAMS) Accession

No. ML061240509).

Since the NRC has not made a final determination in this matter, a Notice of Violation is not

being issued for the apparent violation at this time. Please be advised that the characterization

of the apparent violation described in the enclosed inspection report may change as a result of

further NRC review. You will be advised by separate correspondence of the results of our

deliberations on this matter.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure,

a copy of this letter, its enclosure, and your response, if you choose to provide one, will be

made available electronically for public inspection in the NRC Public Document Room or in the

NRCs ADAMS, accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

If you have any questions regarding this inspection report, please contact Mr. Jeffrey Josey of

my staff at 817-200-1249.

Sincerely,

Jeremy R. Groom, Director (Acting)

Division of Radiological Safety and Security

Docket No. 050-00285

License No. DPR-40

Enclosure:

Inspection Report 050-00285/2024-004

Electronic Distribution via Listserv

Signed by Groom, Jeremy

on 02/04/25

ML25027A457

SUNSI Review: ADAMS:

Non-Publicly Available Sensitive

Keyword:

By: ESM

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

HP:DIOR

SHP:DIOR

TL:ACES

C:DIOR

NAME

EMcManus

SAnderson

BAlferink

JJosey

SIGNATURE

/RA/ E

/RA/ E

/RA/

/RA/

DATE

01/27/25

01/27/25

01/29/25

01/29/25

OFFICE

RC

OE

D:DRSS

NAME

DCylkowski

DBradley

JGroom

SIGNATURE

/RA/ E

/RA/ E

/RA/ E

DATE

01/29/25

01/31/25

02/04/25

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.

050-00285

License No.

DPR-40

Report No.

050-00285/2024-004

Licensee:

Omaha Public Power District

Facility:

Fort Calhoun Station

Location:

9610 Power Lane

Blair, Nebraska

Inspection Dates:

December 9-11, 2024

Exit Meeting Date:

January 22, 2025

Inspectors:

Eric S. McManus, Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Stephanie G. Anderson, Senior Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Accompanied By:

Tiffany N. Rushing, Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Approved By:

Jeffrey E. Josey, Chief

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Attachment:

Supplemental Inspection Information

2

EXECUTIVE SUMMARY

Fort Calhoun Station

NRC Inspection Report 050-00285/2024-004

This U.S. Nuclear Regulatory Commission (NRC) inspection was a routine, announced

inspection of decommissioning activities being conducted at the Fort Calhoun Station.

Decommissioning Performance and Status Reviews at Permanently Shutdown Reactors

The inspectors observed decommissioning work in progress and concluded that the work

was being conducted with an emphasis on industrial and radiological safety. Critical

positions in the organizational structure were staffed. No major changes in the schedule

were identified that had an impact on the decommissioning trust fund. The licensee

continued to identify problems and implement its corrective action program in accordance

with quality assurance program requirements. (Section 1.2)

Fire Protection Program at Permanently Shutdown Reactors

The licensee implemented the fire protection program in accordance with applicable

regulatory and procedure requirements. (Section 2.2)

Solid Radioactive Waste Management and Transportation of Radioactive Materials

In accordance with procedural instructions, Post-Shutdown Decommissioning Activities

Report (PSDAR) commitments, and regulatory requirements, the licensee is adequately

controlling radioactive materials and radioactive sources. (Section 3.2)

Apparent Violation

One apparent violation was identified for the Fort Calhoun Stations failure to properly prepare

and ship a package containing radioactive material in a manner that assured, under conditions

normally incident to transport, the radiation level does not exceed 200 millirem per hour at any

point on the external surface of the package, as required by Title 49 of the Code of Federal

Regulations (49 CFR) 173.441. Pursuant to 10 CFR 71.5, licensees who deliver licensed

material to a carrier for transport must comply with the requirements of the U.S. Department of

Transportation regulations in 49 CFR Parts 171 through 180. Specifically, the licensee shipped

a package containing radioactive materials (i.e., crushed concrete, metal debris, and lagoon

liner) such that when the package arrived at its destination on November 14, 2024, radiation

levels of approximately 765 mrem/hr were measured on the side of the railcar, exceeding the

regulatory requirement of 200 mrem/hr.

3

Report Details

Summary of Site Status

Fort Calhoun Station (FCS) permanently ceased power operations in 2016. In accordance with

Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(9), an application for a license

termination must be accompanied or preceded by the license termination plan (LTP). The

licensee submitted its proposed LTP to the NRC in August 2021. The NRC conducted an

acceptance review and submitted two requests for additional information to the licensee. The

licensee subsequently submitted a revised LTP to the NRC in December 2023 (ML23346A152).

The NRC approved the LTP by license amendment dated January 31, 2024 (ML24019A167).

Since the previous inspection, the licensee conducted Final Status Surveys (FSS) of land areas

and the auxiliary building, continued demolition of the containment building interior, and

transported the containment demolition rubble for offsite disposal.

During the inspection, the licensee continued to decommission the interior of the containment

building. The waste material generated, including radioactive concrete and metal support

components, were transferred to the Waste Processing Structure (WPS) for sorting and

subsequent shipment to a disposal site. In addition, the licensee continued to conduct

radiological assessments, remedial action support surveys, and FSS at several locations around

the site.

1

Decommissioning Performance and Status Reviews at Permanently Shutdown

Reactors (IP 71801)

The inspectors observed site activities, reviewed selected records, and interviewed site

personnel to:

Evaluate the status of decommissioning and verify whether the licensee was

conducting decommissioning and maintenance activities in accordance with

regulatory and license requirements.

Maintain awareness of work activities to assess licensee control and conduct of

decommissioning.

Evaluate select licensee decommissioning staffing, personnel qualifications, and

training requirements, including that of the contracted workforce, to ensure that

license requirements were met, as applicable to the current decommissioning

status.

Identify and document the status, progress, and changes that potentially impact

decommissioning financial assurance, to supplement information for the

Financial Assurance Branch to support and ensure a thorough financial analysis

review of the annual decommissioning trust fund reported by the licensee.

1.2

Observations and Findings

a.

Status of Decommissioning

The inspectors conducted site tours, in part, to observe decommissioning activities in

progress. Inside containment, heavy equipment continued to remove the demolished

floor and walls and transport the removed materials to the WPS for sorting and loading

into railcar gondolas. Inside the WPS, the containment debris was crushed, surveyed,

4

sorted, and loaded into railcar gondolas for shipment to an out-of-state disposal site.

Outside of containment, work in progress included radiological surveys of various areas

around the site. Discharges of processed liquid was paused to protect the processing

and discharge equipment from freezing during the winter. The inspectors observed

licensee surveys were being conducted in accordance with the instructions provided in

Section 5 of the LTP. Finally, the inspectors validated that the licensee had updated the

Defueled Safety Analysis Report (DSAR) and had appropriately identified and stored

records important to decommissioning as defined in 10 CFR 50.75(g).

b.

Decommissioning Operations

The inspectors conducted a detailed review of shipping and survey records associated

with the loading of radioactive material being prepared for shipment. The inspectors also

observed surveys of heavy equipment moved to and from radiologically controlled areas.

The inspectors observed the sorting and handling of crushed containment concrete and

debris.

The inspectors conducted independent radiological assessments during site tours using

a hand-held survey meter, a Radeye G gamma survey meter (Serial Number 30901,

calibration due date January 19, 2025). The inspectors confirmed that radiological

postings and survey results were consistent with regulatory requirements.

During tours of the Containment Waste Structure (CWS) and WPS, the inspectors noted

appropriate use of radiation protection instruments and air samplers to minimize

employee exposures to radioactive contamination. Ventilation systems were in service to

control airflow within the structures. The RP technician response to portal monitor alarms

was observed; RP technicians responded and performed surveys in accordance with

licensee procedures to validate portal monitor alarms were not due to personnel

contamination events. The decommissioning work was being conducted with an

emphasis on industrial and radiological safety.

c.

Decommissioning Staffing and Training

The inspectors reviewed the organizational chart and confirmed that all critical positions

had been filled. The inspectors reviewed training records and lesson plans for the

licensees transportation broker training program. Initial training and refresher training

was conducted in accordance with regulations and licensee procedures. See the

evaluation details in transportation section (Section 3.2.b) of this report.

d.

Decommissioning Planning, Scheduling, and Cost Assessment

The inspectors interviewed senior licensee management and reviewed the licensees

decommissioning strategy and schedule, in part, to ensure there were no major changes

that would impact the decommissioning trust fund. No major changes were identified

during the inspection that would have a significant impact on the trust fund.

5

e.

Problem Identification and Resolution

Section 16 of the Quality Assurance Topical Report, revision 18, requires the licensee to

implement a corrective action program. The inspectors reviewed the most recent list of

corrective action Condition Reports (CR) issued since the last inspection in this program

area. No CRs of significance were identified.

1.3

Conclusions

The inspectors observed decommissioning work in progress and concluded that the

work was being conducted with an emphasis on industrial and radiological safety.

Critical positions in the organizational structure were staffed. No major changes in the

schedule were identified that had an impact on the decommissioning trust fund. The

licensee continued to identify problems and implement its corrective action program in

accordance with quality assurance program requirements.

2

Fire Protection Program at Permanently Shutdown Reactors (IP 64704)

2.1

Inspection Scope

The inspectors reviewed documents and interviewed plant personnel to assess the

licensees performance in the following areas:

Assessed whether the licensee has an effective decommissioning fire protection

program that is maintained and implemented to address the potential for fires

that could result in the release or spread of radioactive materials.

Verified that, in the absence of spent fuel in the spent fuel storage pool, the

decommissioning fire protection program ensures adequate protection from the

fire-induced release of radioactive material from contaminated plant areas and

combustible waste products.

Performed plant tours to assess field conditions and the storage of combustible

materials.

2.2

Observations and Findings

a.

Fire Protection Program

Title 10 CFR 50.48(f) states, in part, that the licensee shall maintain a fire protection

program to address the potential for fires that could cause the release or spread of

radioactive materials onsite or result in a localized radiological hazard. The inspectors

reviewed the licensees fire protection program for compliance with regulatory and

license requirements. The inspectors reviewed the fire protection program as defined

by procedure CC-FC-211, Fire Protection Program, revision 14.

Regulatory Guide 1.191, Fire Protection Program for Nuclear Power Plants During

Decommissioning and Permanent Shutdown, describes the methods acceptable to

the NRC for complying with the NRCs regulations for fire protection programs for

licensees in decommissioning. This regulatory guide is referenced in the licensees

implementing procedures, and the inspectors compared the licensees fire protection

program to the guidance provided in the regulatory guide.

6

The licensees fire protection program records included a fire hazards analysis. This

document provided an analysis of the various plant areas and the fire protection

requirements for those areas. The licensee also developed a detailed decommissioning

fire plan procedure, FCSD-FP-100, Decommissioning Fire Plan, revision 9, that

described onsite fire response staffing, onsite fire response organization responsibilities,

pre-fire plans for the ISFSI Operating Facility and ISFSI area, and fire report preparation

after reportable fires.

The inspectors reviewed one assessment that evaluated the fire protection program in

accordance with 10 CFR 50.48(f)(2). The assessments showed that the fire protection

program was adequate at the site.

b.

Fire Protection Systems and Equipment

The inspectors reviewed the licensees ability to rapidly detect, control, and extinguish

fires. At this stage in decommissioning, the licensee has no automatic fire detection

systems and no automatic fire suppression systems within the deconstruction area at

the plant. The inspectors toured the CWS and the WPS and verified the fire

extinguishers were located according to the pre-fire plans. The fire extinguishers

monthly and annual surveillances were completed satisfactorily.

c.

Control of Combustible Materials and Ignition Sources

To prevent fires from occurring, the licensee established and implemented

administrative procedures for fire prevention control of transient combustible material

and control of ignition sources. The inspectors conducted site tours to confirm that

procedure controls were being implemented. The inspectors concluded that the

licensee was effectively controlling combustible materials around ignition sources in

these areas in accordance with procedure requirements.

d.

Organization

The inspectors reviewed the fire response organization at the site. Fire response

training is provided for all individuals assigned fire watch duties. The inspectors also

reviewed the memorandum of understandings with the offsite fire brigades, as they are

the primary responders in the case of a fire at the site.

e.

Problem Identification and Resolution

The inspectors reviewed a sample of CRs, and assessed the licensee is identifying

problems and entering them into their corrective action program appropriately.

2.3

Conclusions

The licensee implemented the fire protection program in accordance with

applicable regulatory and procedure requirements.

7

3

Solid Radioactive Waste Management and Transportation of Radioactive Materials

(IP 86750)

3.1

Inspection Scope

The inspectors observed site activities, reviewed documents, and interviewed site

personnel to verify the effectiveness of the licensees programs for processing, handling,

storage, and transportation of radioactive materials.

3.2

Observations and Findings

a.

Radioactive Material Storage and Control

The inspectors toured areas where radioactive materials are stored. Radioactive

material storage areas toured included the containment, radiologically controlled areas

adjacent to the containment structure, CWS, WPS, and waste processing equipment

storage areas. Sorting of containment rubble in the WPS identified concrete debris and

metal with high radiation levels. Inspectors observed the control and storage of the

higher radiation level material in a high radiation area vault located within the WPS. All

areas containing radioactive material were controlled, posted, and maintained in

accordance with regulations and licensee procedures.

The inspectors also reviewed procedures for and toured the area where Category 2

material was controlled in accordance with 10 CFR Part 37. The material were sources

used to calibrate radiation protection survey instruments. The licensee procedures,

physical barriers, and security personnel were sufficient to ensure control of the sources.

The licensee had not transferred or replaced the sources since the last inspection. RP

technicians demonstrated how the sources are verified intact and leak checked. RP

technicians also provided records of source inspections and leak checks.

b.

Radioactive Waste Processing

No active liquid waste processing occurred during this inspection and processed liquid

discharges were paused due to low outdoor temperatures. The inspectors toured the

areas where liquid waste storage, processing, and discharge equipment were located.

Liquid waste was being accumulated in storage tanks while liquid waste discharges were

suspended. All equipment associated with liquid processing was posted and controlled

in accordance with regulations. The equipment was also being maintained to prevent

damage or leaks caused by freezing temperatures.

In the WPS, the inspectors observed processing of demolition rubble from the

containment interior. Large concrete sections were crushed to smaller pieces or dust.

Metal debris was separated from the crushed debris and materials with higher radiation

levels were segregated for separate shipment. The inspectors noted adequate health

physics controls in all areas including the use of protective clothing, RP instruments and

air samplers to monitor employee exposures to radioactive contamination. The

inspectors also noted good use of industrial safety practices. Craft and RP personnel

worked together effectively to ensure safety while working near heavy equipment, large

rubble, and material with higher exposure rates.

8

c.

Transportation of Radioactive Materials

The inspectors reviewed training records and lesson plans for the licensees broker

training program. The inspectors performed a detailed audit training of records for two

certified brokers and ensured all training was up to date when the brokers signed

records for radioactive material shipments. Initial training and refresher training were

conducted in accordance with regulations and licensee procedures.

Apparent Violation

The inspectors performed a focused review of the November 6, 2024, radioactive

material shipment (Shipping Manifest Number 1072-07-0875) from FCS to the Clive

Disposal Facility (CDF) in Clive, UT.

Title 10 CFR 71.5 requires each licensee who delivers licensed material to a carrier for

transport to comply with the requirements of the DOT regulations in 49 CFR Parts 171

through 180. 49 CFR 173.441(a) requires in part, with exceptions not applicable here,

that each package of radioactive materials offered for transportation be designed and

prepared for shipment so that under conditions normally incident to transportation the

radiation level does not exceed 200 millirem per hour (mrem/hr) at any point on the

external surface of the package.

Contrary to the above, on November 6, 2024, the licensee failed to prepare a package of

radioactive material such that, under normal conditions incident to transport, the

radiation level did not exceed 200 mrem/hr at any point on the external surface of the

package. Specifically, the licensee shipped a package containing radioactive materials

(i.e., crushed concrete, metal debris, and lagoon liner) such that when the package

arrived at its destination on November 14, 2024, radiation levels of approximately

765 mrem/hr were measured on the side of the railcar, exceeding the regulatory

requirement of 200 mrem/hr.

Upon identification, CDF immediately notified FCS, then notified the Director of the Utah

Division of Waste Management and Radiation Control (Utah Event Report ID Number:

UT 240008, on November 15, 2024) and the NRC Operations Center (Event # 57440, on

November 25, 2024).

The immediate corrective actions taken by the licensee and its contractor included the

following actions. The contractor stopped all loading and shipment of loaded railcars

until further notice. CDF conducted an investigation to determine the cause of the high

contact dose rate and identified a small piece of concrete in the pile reading

approximately 986 mrem/hr on contact and 700 mrem/hr at 30 cm away. FCS

documented the issue in its corrective action program (CR-2024-00198) and conducted

an Apparent Cause Analysis (ACA). The FCS ACA stated that the small piece of

concrete migrated within the container during transport to the side of the container

resulting in an increased radiation level accessible on the external surface of the

railcar. Also, per the ACA, a review of the process steps identified that there were no

procedural requirements to be more intrusive in the debris piles to locate pieces that

may have higher dose rate readings, and the most logical reasoning for not catching the

986 mrem/hr piece of concrete is that it was buried in the larger pile(s) being loaded.

FCS conducted an evaluation to determine the maximum dose received by unmonitored

9

members of the public during shipment. The licensee determined that no member of the

public could have received a dose greater than 1 mrem while the railcar was in transit.

FCS revised the container loading work instruction WI-2021-109, DWP-2021-011 Waste

Processing Structural Operations, revision 3, which changed the order in which differing

material types are loaded into the container and reduced the radiation level limit from

700 mrem/hr to 50 mrem/hr for individual concrete debris permitted to be loaded into the

LSA-1 containers. The revised procedure also added steps to perform radiation surveys

of crushed concrete. Prior to the work instruction revision, this material was only

surveyed prior to crushing.

The inspectors arrived onsite after the work instruction was revised. The inspectors

reviewed the licensee container loading procedures used prior to the apparent violation

and validated that all applicable procedures were followed during preparation and

loading of the rail shipment. The inspectors observed the implementation of the revised

work instruction during loading of railcars at the WPS. The inspectors observations

validated that the revised work instruction appeared to be effective in preventing

additional railcars from exceeding the DOT external radiation limit. The inspectors

observed that RP technician surveys were effective in identifying crushed concrete with

radiation levels greater than 50 mrem/hr and craft personnel were removing the higher

reading material to ensure it was not loaded into the railcars. After all corrective actions

were implemented, FCS resumed shipment of railcars loaded with containment interior

crushed rubble.

The licensees failure to prepare a package of radioactive material such that, under

normal conditions incident to transport, the radiation level did not exceed 200 mrem/hr

at any point on the external surface of the package, is identified as an apparent violation

of 10 CFR 71.5 (05000285/2024-004-01)

d.

Problem Identification and Resolution

The inspectors conducted a review of CRs issued since the last inspection of this area.

The inspectors review and interviews with RP personnel validated that the licensee

appears effective at identifying problems and implementing corrective actions.

3.3

Conclusions

In accordance with procedural instructions, PSDAR commitments, and regulatory

requirements, the licensee is adequately controlling radioactive materials and radioactive

sources. In the area of radioactive material transportation, one apparent violation of DOT

regulations was identified that is being considered for escalated enforcement. The

violation involved the licensees failure to prepare a package of radioactive material for

transportation such that, under conditions normally incident to transportation, the

radiation level did not exceed 200 mrem/hr at any point on the external surface of the

package.

10

4

Exit Meeting Summary

The inspectors presented the preliminary inspection results to the licensees

management and other members of the licensees staff at the conclusion of the onsite

inspection on December 11, 2024. A final exit meeting was held with the licensees

senior management and staff on January 22, 2025. The inspectors asked if any

materials examined were proprietary. No proprietary information was removed from the

site.

Attachment

SUPPLEMENTAL INSPECTION INFORMATION

KEY POINTS OF CONTACT

Licensee and Contractor Personnel

B. Pearson, Regulatory Assurance & Emergency Planning Manager

K. Daughenbaugh, ISFSI Shift Supervisor

T. Uehling, Director Site Decommissioning

A. Hansen, Regulatory Assurance

C. Heimes, Manager ISFSI Site Security

A. Kodra, Project Manager FSS, EnergySolutions

J. Emich, Waste Project Manager

T. Maine, Plant Manager

J. Nowak, Project Director, EnergySolutions

D. Whisler, RP & Chemistry Specialist

J. Hoffman, Chemistry Specialist

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000285/2024-004-01

AV

Radioactive Material Shipment Package Dose Rate

Exceeded (49 CFR 173.441)

Closed

None

Discussed

None

INSPECTION PROCEDURES USED

IP 71801

Decommissioning Performance and Status Reviews at Permanently Shutdown

Reactors

IP 64704

Fire Protection Program at Permanently Shutdown Reactors

IP 86750

Solid Radioactive Waste Management and Transportation of Radioactive

Materials

LIST OF ACRONYMS

ADAMS

Agencywide Documents Access and Management System

ACA

Apparent Cause Analysis

AV

Apparent violation

CDF

Clive Disposal Facility

CFR

Code of Federal Regulations

CWS

Containment Waste Structure

CR

Condition Report

DOT

U.S. Department of Transportation

DSAR

Defueled Safety Analysis Report

FCS

Fort Calhoun Station

FSS

Final Status Survey

IP

Inspection Procedure

ISFSI

Independent Spent Fuel Storage Installation

2

LTP

License Termination Plan

NRC

Nuclear Regulatory Commission

PEC

Pre-Decisional Enforcement Conference

PSDAR

Post-Shutdown Decommissioning Activities Report

RP

Radiation Protection

WPS

Waste Processing Structure