U.S. NRC Support for Navys Planned Deployment of Reactors to Power Domestic Bases and Surrounding Communities November 12, 2024
NRC Mission Statement License and regulate the Nations civilian use of radioactive materials to provide reasonable assurance of adequate protection of public health and safety and to promote the common defense and security and to protect the environment.
ADVANCE Act: Licensing and regulation to be conducted in a manner that is efficient and does not unnecessarily limit - (1) the civilian use of radioactive materials and deployment of nuclear energy or (2) the benefits of civilian use of radioactive materials and nuclear energy technology to society.
www.nrc.gov/about-nrc.html
10 CFR Part 52 Vogtle AP-1000, NuScale Early Site Permit, COL, Design Certification, Manuf. License 10 CFR Part 53 New licensing framework under development Technology-inclusive, risk-informed, performance-based framework Flexible Reactor Licensing Pathways 10 CFR Part 50 Large majority of operating power reactor and NPUF fleet Construction Permit + Operating License Licensing Process Brochure (NUREG/BR-0298)
10 CFR Part 50:
Two-Step Licensing Process Construction Permit Application Public Hearing Construction Permit Construction Begins Operating License Application Public Hearing Opportunity Operating License Operation Begins Construction Permit Operating License
5 This process may involve the following:
Combined License (COL)
Early Site Permit (ESP)
Design Certification (DC)
Standard Design Approval (SDA)
Manufacturing License 10 CFR Part 52:
Single Process with Multiple Components
10 CFR Part 53:
Transformative Regulatory Framework https://www.nrc.gov/reactors/new-reactors/advanced/modernizing/rulemaking/part-53.html
- Technology Inclusive
- Consequence-Oriented Requirements
- Explicit Consideration of Defense in Depth
- Expanded Use of Graded Performance Requirements Part 53
- Prescriptive Requirements
- Optimized for Specific Technology
- Augmented for Operating Experience
- Conservative Assumptions
& Analyses Parts 50/52 vs
Pre-Application Engagement De-risk review of future license application Learn technology, address regulatory issues early, resolve technical questions, provide clarity on regulatory expectations, help map out long lead activities Areas of focus: fuel qualification, material qualification, novel safety features, regulatory applicability, novel policy issues, implementation of regulations, coordination with other agencies, site-specific environmental attributes Readiness assessment
~ 3-6months ahead of a planned submittal Staff reviews draft application for completeness and offers specific feedback on any data needs or apparent gaps ML23277A139 - See Appendix A (pages 65-76 of the pdf) 20+
3 Potential applications by 2027 Applications under current review 15+
100+
Entities actively engaged in pre-application activities Topical Reports and white paper reviews completed 60+
8 Guidance documents issued NRC/CNSC joint reports issued
8 Pre-Application Activities Reactor Licensing Reviews Fuel Fabrication (TRISO-X) 8 Familiarity with Potential Vendors https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with.html
Activity Reactor Type Milestone Part 50 - Construction Permit All 36 months Environmental Impact Statement All 24 months Part 50 - Operating License Non-LWR 36 months Topical Reports All 24 months
- Informed by technology, licensing pathway and sequencing, application quality, pre-application engagement, and applicant needs
- Demonstrated success (all under budget)
- Kairos Hermes 1 CP (18 months)
- Abilene Christian University MSRR CP (18 months eff.)
- Kairos Hermes 2 CP (10 months)
- TerraPower Natrium CP review schedule (27 months)
- Priority to support national defense need NEIMA Generic Milestones*
Efficient NRC Reviews www.nrc.gov/about-nrc/generic-schedules.html
- ADVANCE Act directs NRC to provide the most efficient metrics and schedules reasonably achievable
- Update NRC mission and amendments to AEA
- Strategies/guidance for microreactor regulation
- Expedited licensing for brownfield sites
- Expedited process for qualifying COL applications
- Improvements to oversight and inspection program ADVANCE Act - Continued Evolution https://www.nrc.gov/about-nrc/governing-laws/advance-act.html