Response to NRC Request for Additional Information, Dated October 23, 2024, Regarding the License Renewal Application, Environmental Requests for Additional Information – Environmental Review
ML24326A274
Person / Time
Site: Clinton Constellation icon.png
Issue date: 11/21/2024
From: Wilson C
Constellation Energy Generation
To:
Office of Nuclear Reactor Regulation, Document Control Desk
Shared Package
ML24326A273 List:
References
RS-24-119
Download: ML24326A274 (1)


Text

200 Energy Way Kennett Square, PA 19348 www.constellation.com RS-24-119 10 CFR 50 10 CFR 51 10 CFR 54 November 21, 2024 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

Response to NRC Request for Additional Information, dated October 23, 2024, regarding the Clinton Power Station, Unit 1, License Renewal Application, Environmental Requests for Additional Information - Environmental Review

References:

1.

Letter from Christopher D. Wilson, Constellation Energy Generation, LLC to U.S.

NRC, Application for Renewed Operating License, dated February 14, 2024 (ML24045A024).

2.

Letter from NRC to Christopher D. Wilson, Constellation Energy Generation, LLC, Clinton Power Station, Unit 1 - Summary of the 2024 Environmental Audit related to the Review of the License Renewal Application Environmental report (EPID Number: L-2024-LNE-0000), Enclosure 2, dated October 23, 2024 (ML24283A166).

In Reference 1, Constellation Energy Generation, LLC (CEG) submitted the License Renewal Application (LRA) for the Clinton Power Station, Unit 1 (CPS). In Reference 2, the NRC requested additional information to support the NRC Staff's review of the CPS LRA Environmental Report (Appendix E to the LRA).

Enclosure A to this letter contains a response to each of the NRC questions for CPS LRA Environmental Review Requests for Confirmation of Information (RCI) and Requests for Additional Information (RAI). Supporting documents and materials, if any, have been incorporated into the response to the RCI/RAI requesting them.

November 21, 2024 U.S. Nuclear Regulatory Commission Page 2 If you have any questions, please contact Mrs. Iba Ello-Fletcher, Licensing lead, License Renewal Projects, at 779-231-5462 or via email at Iba.ElloFletcher@Constellation.com.

This letter and its enclosures contain no regulatory commitments. I declare under penalty of perjury that the foregoing is true and correct. Executed on the 21st day of November 2024.

Respectfully, Christopher D. Wilson Director, License Renewal Constellation Energy Generation, LLC

Enclosures:

A.

Clinton Power Station, Unit 1. Responses to NRC License Renewal Application, Environmental Review, Requests for Confirmation of Information (RCI) and Requests for Additional Information (RAI) cc: NRC Regional Administrator, Region III NRC Senior Resident Inspector - Clinton Power Station NRC Project Manager (Safety Review), NRR-DNRL NRC Project Manager (Environmental Review), NRR-DNRL NRC Project Manager, NRR-DORL - Clinton Power Station Illinois Emergency Management Agency - Division of Nuclear Safety Wilson, Christopher D Digitally signed by Wilson, Christopher D Date: 2024.11.21 14:29:38 -05'00'