MONTHYEARML24142A4532024-05-20020 May 2024 Request for Nuclear Regulatory Commissions (NRC) Approval of the Volunteer Transportation Package Project stage: Request ML24194A1192024-07-16016 July 2024 Cover Letter: Request for Supplemental Information for the Model No. Volunteer Package Project stage: Other ML24194A1202024-07-16016 July 2024 Enclosurequest for Supplemental Information and Observation Model No. Volnteer Package Project stage: Other ML24235A5512024-08-22022 August 2024 NAC International, Inc., Safety Analysis Report Rsi Responses, Revision 24B Project stage: Other ML24235A5492024-08-22022 August 2024 Responses to the NRCs Request for Supplemental Information for the Volunteer Transportation Package Project stage: Supplement ML24247A0812024-09-0606 September 2024 Application for the Model No. Volunteer Package - Acceptance Letter Project stage: Acceptance Review ML25042A5462025-02-12012 February 2025 Letter - Request for Additional Information for the Review of the Volunteer Package Project stage: RAI ML25042A5472025-02-12012 February 2025 Enclosure 1 - Request for Additional Information for the Model No. Volunteer Package (Public) Project stage: RAI ML25056A2182025-02-25025 February 2025 NAC International - Responses to the NRCs Request for Additional Information for the Volunteer Transportation Package Project stage: Request ML25056A2202025-02-25025 February 2025 NAC International, Inc. - Volunteer (CoC 9403) RAI Responses - (R25A) - Non-Proprietary Project stage: Other ML25065A2392025-03-0606 March 2025 NAC International - Supplement to Our Responses to the NRCs Request for Additional Information for the Volunteer Transportation Package Project stage: Supplement ML25065A2432025-03-0606 March 2025 Enclosure 1: Proposed CoC Replacement Page, Volunteer Package SAR, Revision 25A, Supplement 1 (Non-Proprietary) Project stage: Supplement ML25092A1722025-04-0202 April 2025 NAC International, Inc., RAI Responses, Supplement 2 for Safety Analysis Report, Revision 25B Project stage: Supplement ML25092A1702025-04-0202 April 2025 NAC International, Inc., Supplement to Our Responses to the NRCs Request for Additional Information for the Volunteer Transportation Package Project stage: Supplement ML25098A2412025-04-0808 April 2025 NAC International, Inc., Supplement to Our Responses to the NRCs Request for Additional Information for the Volunteer Transportation Package Project stage: Supplement ML25098A2422025-04-0808 April 2025 NAC International, Inc., List of SAR Changes, Volunteer Package SAR, Revision 25C & SAR Changed Pages, Volunteer Package SAR, Revision 25C Project stage: Other ML25107A1762025-04-16016 April 2025 NAC International, Inc., Submittal of Consolidated SAR Revision 0 for the Volunteer Transportation Package Certificate of Compliance No. 9403 Project stage: Other ML25112A3032025-04-30030 April 2025 Enclosure 1: CoC No. 9403, Revision No. 0 (Letter to H. Baldner Revision No. 0 of Certificate of Compliance No. 9403 for the Model No. Volunteer Transportation Package) Project stage: Other ML25112A3042025-04-30030 April 2025 Enclosure 2: Safety Evaluation Report for Review of Revision No. 0 of the Certificate of Compliance No. 9403 for the Model No. Volunteer Transportation Package Project stage: Approval ML25112A3022025-04-30030 April 2025 Letter to H. Baldner Revision No. 0 of Certificate of Compliance No. 9403 for the Model No. Volunteer Transportation Package Project stage: Other 2025-02-25
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Heath Baldner, Director of Licensing NAC International 2 Sun Court, Suite 220 Peachtree Corners, GA 30092
SUBJECT:
APPLICATION FOR THE MODEL NO. VOLUNTEER PACKAGE -
ACCEPTANCE LETTER
Dear Heath Baldner:
By letter dated May 20, 2024 (Agencywide Documents Access and Management System Accession No. ML24142A453), NAC International (NAC) submitted an application for approval of the Model No. VOLUNTEER package.
On August 22, 2024, NAC submitted its responses (ML24235A548) to the staffs Request for Supplemental Information dated July 16, 2024 (ML24194A118). The revised application appears to contain the necessary information to begin our detailed technical review.
The schedule allows for the staff to issue a possible request for additional information on or around December 9, 2024, with responses due by January 31, 2025, and, if no additional information is needed, issue a Certificate of Compliance by the end of May 2025. The staff estimates that completing the safety review of this application will require approximately 950 staff hours and $20,000 in support contract costs.
Please reference Docket No. 71-9403 and Enterprise Project Identifier No. L-2023-NEW-0007 in future correspondence related to this request.
Sincerely, Pierre M. Saverot, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-9403 EPID L-2023-NEW-0007 September 6, 2024 Signed by Saverot, Pierre on 09/06/24