Rulemaking - Proposed Rule - 10 CFR Part 53 Burden Table Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (Part 53)
ML24220A060
Person / Time
Issue date: 10/30/2024
From: Robert Beall
Office of Nuclear Reactor Regulation
To:
References
NRC-2019-0062, RIN 3150-AK31, 10 CFR Part 53
Download: ML24220A060 (1)


Text

Rule Section Description Type of Change New (N)

Amended (A)

Removed (R)

Change in Respondents (CR)

Number of Respondents Responses per Respondent Total Responses Burden Hours per

Response

Total Burden Hours Total Cost at

$300/hour Notes Impact of Proposed Rule on Existing Clearance Burden Hour Estimates Burden Basis N/A Pre-application activities N

2.0 1.0 2.0 25,000.0 50,000.0

$15,000,000 Part 53 applicants Part 52 53.070 Notify NRC within 2 working days of identifying information related to regulated activities that has significant implications for public health and safety or common defense and security N

2.0 1.0 2.0 4.0 8.0

$2,400 Part 53 applicants and licensees 50.9 53.080 Applications for exemptions from part 53 regulations N

0.0 1.0 0.0 360.0 0.0

$0 Applications from any interested person 50.12 53.605 Notify the NRC of a failure to comply, defect, or breakdown in the quality assurance program N

0.0 1.0 0.0 10.0 0.0

$0 CP, COL, and ML holders 50.55(e)

Table 1 Annual Reporting

53.720 Consult with the Commission and propose a plan for timely, safe shutdown of the CNP in response to seismic events, if SSCs necessary for safe shutdown are not available. Prior to resuming operations, demonstrate features necessary for safety or necessary to maintain the licensing basis of the CNP were either not functionally damaged or have been repaired.

N 0.0 1.0 0.0 900.0 0.0

$0 OL and COL holders Appendix S, Earthquake Engineering

Criteria, Operating
Reactors, and 50.54(ff) 53.780
Training, examination, and proficiency programs N

1.0 1.0 1.0 711.0 711.0

$213,300 Applicants for and holders of OLs and COLs 55.40, 55.41, 55.43, 55.45(b);

55.47(f);

55.53(e) and (f) 53.785(h)

Notify the NRC within 30 days of a conviction for a felony N

0.0 1.0 0.0 4.0 0.0

$0 Each operator or senior operator 55.53(g)

53.805(a)(5

)

Report annually to the NRC the identity of all GLROs N

0.0 1.0 0.0 6.0 0.0

$0 OL and COL licensees of self-reliant mitigation facilities that have not certified the permanent cessation of operations and permanent removal of fuel from reactor 53.810(g)

Notify the NRC within 30 days of a conviction for a felony N

0.0 1.0 0.0 4.0 0.0

$0 Each GLRO under Part 53 55.53(g) 53.890(e)

Provide at least biennial updates and revisions to the FSP and obtain NRC approval for any proposed changes that would require an exemption N

0.0 0.0 0.0 0.0 0.0

$0

53.1010(b)(

1)(ii)

After the Commission issues the notice of intended operation, the licensee must update the decommissioning report to certify that it has provided financial assurance for decommissioning in the amount proposed in the application and approved by the NRC.

N 0.0 1.0 0.0 20.0 0.0

$0 COL applicants 53.1010(b)(

4)

Submit a copy of the financial instrument obtained to satisfy the requirement of 53.1040 to the NRC as part of application for an OL, or as required by 53.1060(b) for a COL.

N 0.0 1.0 0.0 2.0 0.0

$0 OL applicants and COL applicants/h olders 50.75(b)(4) 53.1020 Submit site-specific decommissioning cost estimates.

N 1.0 1.0 1.0 30.0 30.0

$9,000 Applicants for COLS and OLs 50.75 53.1030 Annually adjust the cost estimate for decommissioning N

0.0 1.0 0.0 15.0 0.0

$0 Holders of an OL or COL 50.75(b)(2) and (c)(2)

53.1045(b)(

3)

Provide the text of any proposed amendment to the account used to segregate and manage the funds and a statement of the reason for the proposed amendment.

N 0.0 1.0 0.0 5.0 0.0

$0 Licensees that are not "electric utilities" as defined in § 53.020 that use prepayment or an external sinking fund to provide financial assurance 50.75(h)(1)(i ii) 53.1045(b)(

4)

Written notice of the intention to make a disbursement or payment must be provided, except for withdrawals being made under paragraph (a) of this section or for payments of ordinary administrative costs and other incidental expenses of the fund in connection with the operation of the fund.

N 0.0 1.0 0.0 3.0 0.0

$0 Licensees that are not "electric utilities" as defined in § 53.020 that use prepayment or an external sinking fund to provide financial assurance 50.75(h)(1)(i v)

53.1045(c) Provide written notice of the intention to make a disbursement or payment.

N 0.0 1.0 0.0 3.0 0.0

$0 Licensees that are "electric utilities" under § 53.020 that use prepayment or an external sinking fund to provide financial assurance 50.75(h)(2) 53.1060(a)

Report, at least every two years, on the status of the certification of decommissioning funding for each reactor of part of a reactor. Certain licensees are required submit this report annually.

N 0.0 1.0 0.0 6.0 0.0

$0 Holders of an OL, and holders of a COL for which the Commission has made a finding under 53.1452(g) 50.75(f)(1)/(

2)

53.1060(b) 2 years and 1 year before initial fuel loading or intitiating the physical removal of any one of the independent mechanisms to prevent criticality required under § 53.620(d)(1) for a fueled manufactured reactor, submit a report to the NRC containing a certification updating the decommissioning cost estimates and a copy of the financial instrument. 30 days after the Commission publishes a notice in the FR under 53.1452(a), submit a report certifying that financial N

0.0 3.0 0.0 10.0 50.75(e)(3)

COL holders

$0 0.0

a report certifying that financial assurance for decommissioning is being provided in an amount specified in the licensee's most recent updated certification, including a copy of the financial instrument obtained to satisfy § 53.1040 53.1060(d)

About 5 years prior to end of operations, submit a preliminary decommissioning cost estimate to the NRC N

0.0 1.0 0.0 15.0 0.0

$0 OL and COL holders 50.75(f)(3) 53.1060(e);

53.1070(d)(

1)

Prior to or within 2 years following the permanent cessation of operations, submit a PSDAR to the NRC, including a site-specific DCE.

N 0.0 1.0 0.0 120.0 0.0

$0 OL and COL holders 50.82(a)(4)(i

)

53.1060(g)

After the DCE required by paragraph (e) is submitted and until the licensee has completed the final radiation survey and demonstrated that residual radioactivity has been reduced to a level permitting termination of the license, annually submit to the NRC a financial assurance status report.

N 0.0 1.0 0.0 40.0 0.0

$0 Holders of an OL or COL 50.82(a)(8)(

v) 53.1060(h)

After the DCE required by paragraph (e) of this section is submitted, annually submit to the NRC a report on the status of funding for managing irradiated fuel.

N 0.0 1.0 0.0 40.0 0.0

$0 Holders of an OL or COL 50.82(a)(8)(

vii) 53.1070(a)(

1)

Submit a written certification to the NRC within 30 days of determining to permanently cease operations N

0.0 1.0 0.0 20.0 0.0

$0 OL or COL holders 50.82(a)(1)(i

)

53.1070(a)(

2)

Make appropriate submittals to the NRC in accordance with §53.1510 to request any changes to technical specifications needed to support decommissioning.

N 0.0 1.0 0.0 40.0 0.0

$0 OL or COL holders 53.1070(a)(

3)(i)

Submit a written certification to the NRC once fuel has permanently been removed from the reactor vessel N

0.0 1.0 0.0 20.0 0.0

$0 OL or COL holders 50.82(a)(1)(i i) 53.1070(i)(

1)-(i)(2)

Submit an application for termination of license in accordance with 53.1575, and a license termination plan.

N 0.0 1.0 0.0 200.0 0.0

$0 OL and COL holders 50.82(a)(9)

53.1080(a)

Obtain prior written NRC approval to release part of a commercial nuclear plant or site for unrestricted use at any time before receiving approval of a license termination plan.

N 0.0 1.0 0.0 100.0 0.0

$0 OL and COL holders 53.1080(b)

For release of non-impacted areas, licensees may submit a written request for NRC review and approval of the release if a license amendment is not otherwise required.

N 0.0 1.0 0.0 100.0 0.0

$0 OL and COL holders 53.1080(d)

For release of impacted areas, submit an application for amendment of license N

0.0 1.0 0.0 100.0 0.0

$0 OL and COL holders 53.1100(a)(

2)

Upon notification by the presiding officer, update the application and serve the updated copies N

0.0 1.0 0.0 10,000.0 0.0

$0 CP, ESP, COL, or ML applicants 50.30(a)(3)

53.1130 Submit a request for a limited work authorization as part of a complete application for a CP, COL, or ESP; or as part of a partial application for CP or COL, including a Safety Analysis

Report, environmental report, and plan for redress of activities N

0.0 1.0 0.0 1,000.0 0.0

$0 Any person to whom the Commission may otherwise issue either a license or permit related to a commercial nuclear plant 50.10 53.1140 (53.1100(a)

(1);

53.1109; 53.1144; Application for early site permit N

0.0 1.0 0.0 33,750.0 0.0

$0 ESP applicants 50.30(a)(1);

52.16; 52.17 53.1173(a)

Submit application for renewal of ESP.

N 0.0 1.0 0.0 6,000.0 0.0

$0 ESP holders 52.29(a) 53.1182 Provide notice to the Director of NRR at least 30 days prior to any significant uses of the site for purposes that have not been approved in the ESP N

0.0 1.0 0.0 40.0 0.0

$0 ESP holders 52.35

53.1188(b)

Update the emergency preparedness information provided under 53.1146(b) and discuss whether it materially changes the bases for compliance with NRC requirements.

N 0.0 1.0 0.0 200.0 0.0

$0 Applicants for CPs, OLs, and COLs who have filed an application referencing an ESP issued under Subpart H.

52.39(b) 53.1188(d)

Request a variance from one or more site characteristics, design parameters, or terms or conditions of the ESP or Site Safety Analysis Report N

0.0 1.0 0.0 120.0 0.0

$0 Applicants for CPs, OLs, and COLs referencing an ESP.

52.39(d) 53.1188(e)

Request a change to the ESP through a license amendment application N

0.0 1.0 0.0 313.0 0.0

$0 ESP holders 52.39(e)

53.1200 (53.240(a)-

(c),

53.450(a)-

(b), (e)-(g),

53.480(f),

53.480(g);

53.410, 53.420, 53.425, 53.430; 53.440(n)(4

);

53.1100(a)(

1); 53.1109; 53.1206; 53.1209; 53.1210)

Application for standard design approval.

N 0.0 1.0 0.0 23,760.0 0.0

$0 Applicants for a standard design approval 50.30(a)(1);

52.136; 52.137

53.1230 (53.240(a)-

(c),

53.450(a)-

(b), (e)-(g),

53.480(f),

53.480(g);

53.410, 53.420, 53.425, 53.430; 53.440(n)(4

);

53.1100(a)(

1); 53.1109; 53.1236; 53.1239; 53.1241; 53.1257)

Application for standard design certifications.

N 0.0 1.0 0.0 269,092.5 0.0

$0 Applicants for a standard design certification 50.30(a)(1);

52.46; 52.47(a);

52.47(b) and (d); 52.59(c) 53.1254 Submit application for renewal of SDC. N 0.0 1.0 0.0 10,000.0 0.0

$0 "Any person may apply for renewal" 52.57(a) 53.1263(b)

Applicant may request exemption from elements of the certification information.

N 0.0 1.0 0.0 360.0 0.0

$0 Applicants referencing a design certification rule.

52.63(b)

53.1270 (53.240(a)-

(c),

53.450(a)-

(b), (e)-(g),

53.480(f),

53.480(g);

53.410, 53.420, 53.425, 53.430; 53.440(n)(4

);

53.1100(a)(

1); 53.1109; 53.1276; 53.1279; 53.1282)

Application for manufacturing license N

0.0 1.0 0.0 69,300.0 0.0

$0 Applicants for a ML 50.30(a)(1);

52.156; 52.157; 52.158 53.1288 Applicants may request a departure from the design characteristics, site parameters, terms and conditions, or approved design of the manufactured reactor module.

N 0.0 1.0 0.0 313.0 0.0

$0 Applicants for MLs that reference or use a manufacture d reactor of manufacture d reactor module manufacture d under a ML 52.171(b)(2) 53.1295 Application for renewal of MLs N

0.0 1.0 0.0 10,000.0 0.0

$0 ML holders 52.177

53.1300 (53.240(a)-

(c),

53.450(a)-

(b), (e)-(g),

53.480(f),

53.480(g);

53.410, 53.420, 53.425, 53.430; 53.440(n)(4

);

53.1100(a)(

1); 53.1109; 53.1306; 53.1309; 53.1312)

Application for construction permit N

1.0 1.0 1.0 67,500.0 67,500.0

$20,250,000 Applicants for a CP 50.30(a)(1);

50.33; 50.34(a) and (e) and 100.21(f);

50.30(f),

50.10(d)(2),

52.79(b),

(c), and (d),

portions of

§§ 52.63(b)(1),

52.79(b)(2),

52.80, and 52.93 53.1327 Have an approved site redress plan to implement if the application for the CP is withdrawn or denied after an applicant has performed the activities authorized under § 53.1130 N

0.0 1.0 0.0 100.0 0.0

$0 Applicants for a CP 52.91

53.1330(a)

Applicants may include requests for exemptions from the Commission's regulations.

N 0.0 1.0 0.0 360.0 0.0

$0 Applicants for a CP or amendment to a CP 52.93(a) 53.1330(b)

Applicants may include requests for exemptions, departures, or variances related to the referenced NRC approval, permit, or certification.

N 0.0 1.0 0.0 216.5 0.0

$0 Applicants for CPs that have filed an application that references an NRC

approval, permit or certification 52.39(d) and 52.93(b)-(c) 53.1333(b)

Periodic reports of the progress and results of research and development programs designed to resolve safety questions N

1.0 1.0 1.0 100.0 100.0

$30,000 Applicants for CPs and amendments to CPs 50.35(b) 53.1336 Applicants may request approval of the safety of specific design features or specifications in the CP or amendment to the CP.

N 0.0 1.0 0.0 500.0 0.0

$0 Applicants for a CP or amendment to a CP 50.35(b)

53.1348 When a permit holder has determined to permanently cease construction, the holder must, within 30 days, submit a written certification to the NRC.

N 0.0 1.0 0.0 20.0 0.0

$0 CP holders 52.3(b)(8) and 52.110(a)(1) 53.1360 (53.240(a)-

(c),

53.450(a)-

(b), (e)-(g),

53.480(f),

53.480(g);

53.410, 53.420, 53.425, 53.430; 53.440(n)(4

); 53.730; 53.890(d);

53.1100(a)(

1); 53.1109; 53.1366; 53.1369; 53.1372)

Application for operating license N

0.0 1.0 0.0 30,000.0 0.0

$0 Applicants for an OL 70.62(c)(3)(i

);

50.30(a)(1);

50.33, 50.33(f),

50.75; 50.34(b);

51.53(b) 53.1384(a)

Applicants may include requests for exemptions from the Commission's regulations.

N 0.0 1.0 0.0 360.0 0.0

$0 Applicants for an OL or amendment to an OL 52.93(a)

53.1384(b)

Applicants may include requests for exemptions, departures, or variances related to the referenced NRC approval, permit, license or certification.

N 0.0 1.0 0.0 216.5 0.0

$0 Applicants for OLs that have filed an application that references an NRC

approval, permit, license or certification 52.39(d) and 52.93(b)-(c) 53.1402 File an application for a renewal of a OL N

0.0 1.0 0.0 10,000.0 0.0

$0 OL licensees 53.1410 (53.240(a)-

(c),

53.450(a)-

(b), (e)-(g),

53.480(f),

53.480(g);

53.410, 53.420, 53.425, 53.430; 53.440(n)(4

); 53.730; 53.890(d);

53.1100(a)(

1); 53.1109; 53.1413; 53.1416; 53.1419)

Application for combined license N

1.0 1.0 1.0 94,524.0 94,524.0

$28,357,200 Applicants for a COL 50.30(a)(1);

70.62(c)(3)(i

); 52.77; 52.79; 52.80(a),(b)

53.1437(a)

Applicants may include requests for exemptions from the Commission's regulations.

N 0.0 1.0 0.0 360.0 0.0

$0 Applicants for a COL or amendment to a COL 52.93(a) 53.1437(b)

Applicants may include requests for variance from one or more site characteristics, design parameters, or terms and conditions of the permit, or from the Site Safety Analysis Report.

N 0.0 1.0 0.0 120.0 0.0

$0 Applicants for a COL that reference an ESP in their application 52.39(d) and 52.93(b) 53.1437(c)

Applicants may include requests for a departure from one or more design characteristics, site parameters, terms and conditions, or approved design of the manufactured reactor.

N 0.0 1.0 0.0 313.0 0.0

$0 Applicants for a COL that reference a manufacture d reactor in their application 52.93(c)

53.1449(a)

Submit a schedule for completing the proposed ITAAC to the NRC within one year of obtaining a COL or starting construction.

Submit updates to the ITAAC schedules every 6 months after submitting the initial schedule and, within 1 year of the scheduled date for initial loading of fuel, submit updates to the ITAAC schedule every 30 days until the final notification is provided to the NRC under paragraph (c)(1).

N 0.0 1.0 0.0 20.0 0.0

$0 Holders of a CP or COL 52.99(a) 53.1449(c)(

1)

ITAAC closure notification N

0.0 206.0 0.0 49.0 0.0

$0 COL holders 52.99(c)(1) 53.1449(c)(

2)

ITAAC post-closure notifications N

0.0 3.0 0.0 20.0 0.0

$0 COL holders 52.99(c)(2) 53.1449(c)(

3)

Uncompleted ITAAC notification N

0.0 62.0 0.0 40.0 0.0

$0 COL holders 52.99(c)(3) 53.1449(c)(

4)

All ITAAC complete notification N

0.0 1.0 0.0 8.0 0.0

$0 COL holders 52.99(c)(4)

53.1449(d)

Request an exemption from the standard design certification ITAAC or a license amendment under subpart I if the licensee has not demonstrated that the prescribed acceptance criteria have been met N

0.0 1.0 0.0 336.5 0.0

$0 COL holders 52.99(d) 53.1452(a)

Notify the NRC of the scheduled date for initial loading of fuel N

0.0 2.0 0.0 10.0 0.0

$0 COL licensees 52.103(a) 53.1458 File an application for a renewal of a COL N

0.0 1.0 0.0 10,000.0 0.0

$0 COL licensees 52.107 53.1470 Contents of applications that request to construct and license nuclear power reactors of identical design at multiple sites.

N 0.0 1.0 0.0 50.0 0.0

$0 CP, OL, and COL applicants appendix N of parts 50 and 52

53.1505(b)

Propose changing licensing basis information established by NRC regulations by requesting an exemption in accordance with 53.080 N

0.0 1.0 0.0 4.0 0.0

$0 Licensees 53.1510; 53.1515(a)(

5)(vi)

(53.1257)

File an application for a license amendment with the NRC; explain exigencies N

0.0 1.0 0.0 313.0 0.0

$0 Licensees 50.59(c),

50.90, 50.91(a),

(b); 52.59(c) 53.1525(a)-

(c)

Request an exemption if proposing to change elements of the certification information, and submit a license amendment request; Evaluate changes to the design as described in the FSAR not involving changes to the certification information using the criteria in

§53.1550.

N 0.0 1.0 0.0 40.0 0.0

$0 OL and COL holders that reference a design certification rule

53.1530(a)

Obtain amendment before making changes to the design of the manufactured reactor or manufactured reactor module authorized to be manufactured N

0.0 1.0 0.0 10.0 0.0

$0 ML licensees

53.1530(b)

Request approval for any proposed departure from the design characteristics, site parameters, terms and conditions, or approved design of the manufactured reactor. If the ML references a design certification rule, the amendment application must also request an exemption from the design certification rule if elements of the certification information are adversely affected by the change.

Evaluate changes to the commercial nuclear plant as described in the FSAR but outside of the scope of the N

0.0 1.0 0.0 10.0 0.0

$0 COL holders that reference or use a manufacture d reactor referenced manufacturing license using the criteria in § 53.1550.

53.1535(a)-

(b)

Request an amendment to the CP or LWA to gain NRC approval of the safety of selected design features or specifications in accordance with 53.1510 and 53.1520. For COLs in which the NRC has not yet made a finding under 53.1452(g), request amendments required by 53.1525 or 53,1550 no later than 45 days from the date the licensee begins construction of the SSCs to implement the change or departure.

N 0.0 1.0 0.0 100.0 0.0

$0 Holders of a CP or LWA 50.35(b)

53.1540 (53.1545; 53.1550; 53.1560; 53.1565)

Modify licensing basis information, including updating the FSAR, and evaluate potential changes to facilities, procedures, programs, and organizations to determine if NRC approval is required.

N 0.0 1.0 0.0 1,353.6 0.0

$0 Holders of an OL or COL.

Holder of a license authorizing operation of a nuclear power reactor that has submitted the certification of permanent cessation of operations required under § 53.1070(a)(1

) or a reactor licensee whose license has been amended to allow possession 50.71(e),

50.71; 50.59(c) and (d) of nuclear fuel but not operation of the facility.

53.1570 Application for transfer of a license N 0.0 1.0 0.0 580.0 0.0

$0 Licensees 50.80(b) 53.1575(a),

(b), and (d)

Submit a written certification to the NRC within 30 days of determining to permanently cease operations. Submit a written certification to the NRC once fuel has permanently been removed from the reactor vessel; Licenseholder may request termination of the license and licensees issued under parts 30, 40, or 70 prior to plant operations N

0.0 1.0 0.0 680.0 0.0

$0 Holder of an OL or COL 50.82 53.1580 Upon request of the Commission, submit written statements to enable the Commission to determine whether or not the license should be modified, suspended, or revoked N

0.0 1.0 0.0 50.0 0.0

$0 Licensees

53.1620(e)

Notify the Commission of successfully completing power ascension testing or startup testing as applicable N

0.0 1.0 0.0 2.0 0.0

$0 Licensees 53.1630 Immediate and Followup notification requirements N

0.0 2.0 0.0 5.9 0.0

$0 Holder of an OL or a COL after the Commission makes the finding under 53.1452(g) 50.72(a)

53.1645 Submit annual effluent reports to the NRC N

0.0 1.0 0.0 84.0 0.0

$0 Holder of an OL or a COL after the Commission makes the finding under 53.1452(g)

States that 53.1645 would be equivalent to the reporting requirement s in 50.36a, but that instead of requiring licensees to address conditions where the dose to the maximally exposed individual could be significantly above design objectives, the requirement would refer to a

design objective of 10mrem/ye ar instead of referring to the design objectives in appendix I to part 50.

Therefore, the burden estimate is loosely scaled from the 50.36,50.36 A, 50.36B &

Appendix I row in the part 50 burden table.

53.1680 Submit annual financial reports N

0.0 1.0 0.0 1.0 0.0

$0 Licensees and CP holders 50.71(b) and Appendix C

53.1690(a)

Prior to ceasing to be an electric utility, provide the NRC with the financial qualifications information that would be required for obtaining an initial operating license or combined license under Framework A of this part.

0.0 1.0 0.0 10.0 0.0

$0 Electric utility licensee holding an OL or COL (including a renewed license) 53.1690(b)

Notify the appropriate NRC Regional Administrator immediately following the filing of a voluntary or involuntary petition for bankruptcy N

0.0 1.0 0.0 1.0 0.0

$0 Licensees 50.54(cc) 53.1720(c)

Report current levels of insurance or financial security maintained and its source N

0.0 1.0 0.0 212.0 0.0

$0 Licensees 50/54(w)(3)

53.1720(d)(

2)

Following an accident, inform the Director of the Office of NRR in writing when the plant is in safe and stable condition; within 30 days of this notification, prepare and submit a cleanup plan N

0.0 1.0 0.0 2,000.0 0.0

$0 Licensees 50.54(w)(4)

Total 2.0 9.0 212,873.0 $63,861,900

Rule Section Description Type of Change New (N)

Amended (A)

Removed (R)

Change in Respondents (CR)

Number of Recordkeepers Burden Hours Per Recordkeepers Total Burden Hours Total Cost at

$300/hour Notes Impact of Proposed Rule on Existing Clearance Burden Hour Estimates Burden Basis 53.450(c)

Maintenance and upgrade of probabilistic risk assessment N

0.0 1,000.0 0.0

$0 Licensees 53.440(a)

Demonstrate that each design featured required by § 53.400 meets the functional design criteria required by §§ 53.410 and 53.420. In the design processes for SR and NSRSS SSCs, include administrative procedures for evaluating operating, design, and construction experience and for considering applicable important industry experience in the design of those SSCs.

N 2.0 100.0 200.0

$60,000 Licensees and applicants?

50.43(e) 53.440(k)

Define design features and related functional design criteria such that analyses present a low risk of permanent injury to the public due to the health effects of chemical hazards of licensed material.

N 2.0 1,200.0 2,400.0

$720,000 Licensees and applicants?

53.500(a)

Siting assessment N

2.0 700.0 1,400.0

$420,000 Licensees and applicants?

53.540 Supporting analyses to demonstrate that design features and programmatic controls address site characteristics and meet the safety criteria in §§ 53.210 and 53.220.

N 2.0 700.0 1,400.0

$420,000 Licensees and applicants?

Table 3 One-Time Recordkeeping

53.605(c);

53.605(i)

Adopt procedures for evaluating, identifying, and reporting deviations and failures to comply associated with a substantial safety hazard. Adopt procedures to ensure a director or responsible officer of a licensee is informed as soon as practicable, and within 5 working days, of any failures to comply, defects, or breakdown in the QA program. Prepare and retain records related to the requirements of this section.

N 0.0 100.0 0.0

$0 Holders of a construction

permit, combined license, or manufacturin g license 50.55(e) 53.610(b)

Develop programs and procedures as appropriate, considering the amount and types of radioactive materials onsite (SNM MC&A

program, measurement control program, procedures to receive, possess, use, and store source, byproduct, or SNM, plant staff training programs, procedures to mitigate hazards to SSCs, security programs)

N 0.0 1,000.0 0.0

$0 Licensees 53.610(b)

Maintain programs and procedures as appropriate, considering the amount and types of radioactive materials onsite (SNM MC&A

program, measurement control program, procedures to receive, possess, use, and store source, byproduct, or SNM, plant staff training programs, procedures to mitigate hazards to SSCs, security programs)

N 0.0 250.0 0.0

$0 Licensees

53.620(a)

Develop plans, programs, and procedures to manage and control manufacturing activities.

N 0.0 1,666.7 0.0

$0 ML licensees 53.620(a)

Implement plans, programs, and procedures to manage and control manufacturing activities.

N 0.0 416.7 0.0

$0 ML licensees 53.620(b)(3Establish a post-manufacturing inspection and acceptance process.

N 0.0 100.0 0.0

$0 ML licensees 53.620(b)(3Implement access controls, and a post-manufacturing inspection and acceptance process N

0.0 25.0 0.0

$0 ML licensees 53.620(c)

Establish programs and procedures as appropriate, considering the amount and types of radioactive materials brought into the manufacturing facility (procedures to receive, transfer, and use source, byproduct, and SNM, a fire protection program, emergency plans, staff training, procedures and processes to minimize contamination of the facility and environment)

N 0.0 200.0 0.0

$0 ML licensees 53.620(c)

Implement programs and procedures as appropriate, considering the amount and types of radioactive materials brought into the manufacturing facility (procedures to receive, transfer, and use source, byproduct, and SNM, a fire protection program, emergency plans, staff training, procedures and processes to minimize contamination of the facility and environment)

N 0.0 50.0 0.0

$0 ML licensees

53.620(d)

Maintain a physical security plan and establish a physical security program per the requirements of 73.67 for all MLs, regardless of fuel type, enrichment, and quantity.

N 0.0 15.0 0.0

$0 ML licensees 53.620(e)(

3)

Prior to transport, procedures for transporting the manufactured reactor of major portions thereof must be documented and approved N

0.0 5,000.0 0.0

$0 ML licensees 53.700 Develop controls for plant SSCs, responsibilities of plant personnel, and plant programs during the operating life of the CNP N

0.0 100.0 0.0

$0 OL and COL licensees 53.700 Implement and maintain controls for plant SSCs, responsibilities of plant personnel, and plant programs during the operating life of the CNP N

0.0 25.0 0.0

$0 OL and COL licensees 53.710 Develop technical specifications that define conditions or limitations on plant operations N

0.0 1,664.0 0.0

$0 Licensees 50.36 53.710 Implement and maintain technical specifications that define conditions or limitations on plant operations N

0.0 416.0 0.0

$0 Licensees 50.36 53.715(a)

Develop a program to control maintenance activities and monitor the performance and condition of SR and NSRSS SSCs N

0.0 3,452.0 0.0

$0 Licensees 50.65 53.715(a)

Implement and maintain a program to control maintenance activities and monitor the performance and condition of SR and NSRSS SSCs N

0.0 863.0 0.0

$0 Licensees 50.65

53.715(c)

Evaluate performance and condition monitoring activities at least every 24 months.

N 0.0 863.0 0.0

$0 Licensees 50.65 53.730 Develop certain measures including human factors engineering design requirements, human system interface design requirements, concept of operations, functional requirements analysis and function allocation, operating experience, staffing plan, and training, examination, and proficiency programs N

0.0 400.0 0.0

$0 Holders of an OL or COL 53.730 Implement and maintain certain measures including human factors engineering design requirements, human system interface design requirements, concept of operations, functional requirements analysis and function allocation, programmatic requirements, staffing plan, and training, examination, and proficiency programs N

0.0 400.0 0.0

$0 Holders of an OL or COL 53.780

Training, examination, and proficiency programs N 1.0 1,422.0 1,422.0

$426,600 OL and COL licensees and applicants 55.40, 55.41, 55.43, 55.45(b); 55.46(b);

55.47(f); 55.53(e) and (f); 55.59(c)

53.805(a)(

2)

Develop facility technical specifications N

0.0 700.0 0.0

$0 OL and COL licensees of self-reliant mitigation facilities that have not certified the permanent cessation of operations and permanent removal of fuel from reactor vessel 53.805(a)(

2)

Implement and maintain facility technical specifications N

0.0 175.0 0.0

$0 OL and COL licensees of self-reliant mitigation facilities that have not certified the permanent cessation of operations and permanent removal of fuel from reactor vessel 53.815 (53.805(a)

(3))

Develop generally licensed reactor operator training, examination, and proficiency programs N 0.0 568.8 0.0

$0 OL and COL licensees of self-reliant mitigation facilities that have not certified the permanent cessation of operations and permanent removal of fuel from reactor vessel

53.815 (53.805(a)

(3))

Implement and maintain generally licensed reactor operator training, examination, and proficiency programs N

0.0 142.2 0.0

$0 OL and COL licensees of self-reliant mitigation facilities that have not certified the permanent cessation of operations and permanent removal of fuel from reactor vessel 53.830 Establish a training and qualification program for CNP personnel N

0.0 390.0 0.0

$0 Holders of an OL or COL 50.120 53.830 Implement, maintain, and periodically evaluate and revise a training and qualification program for CNP personnel N

0.0 97.5 0.0

$0 Holders of an OL or COL 50.120 53.850(a)-

(c)

Establish a Radiation Protection Program.

Develop a program for the control of radioactive effluents and a process control program.

N 0.0 1,871.8 0.0

$0 Licensees 53.850(a)-

(c)

Implement and maintain a Radiation Protection Program.

Implement and maintain a program for the control of radioactive effluents and a process control program.

N 0.0 935.9 0.0

$0 Licensees 53.855 Develop an emergency response plan N

0.0 545.0 0.0

$0 Holders of an OL or COL 50.47, 50.54(q & t),

Appendix E 53.855 Implement and maintain an emergency response plan N

0.0 136.3 0.0

$0 Holders of an OL or COL 50.47, 50.54(q & t),

Appendix E 53.870 Develop an integrity assessment program to monitor, evaluate, and manage the capabilities, availability, and reliability of SR and NSRSS SSCs N

0.0 674.3 0.0

$0 Holders of an OL or COL

53.870 Implement and maintain an integrity assessment program to monitor, evaluate, and manage the capabilities, availability, and reliability of SR and NSRSS SSCs N

0.0 100.0 0.0

$0 Holders of an OL or COL 53.875(a)-

(b)

Develop a fire protection plan and program N

0.0 60.0 0.0

$0 Holders of an OL or COL 50.48, Appendix R 53.880 Develop programs for inservice inspection and inservice testing N

0.0 1,155.0 0.0

$0 Holders of an OL or COL 50.55a 53.880 Implement and maintain a program for In-Service Inspection and In-Service Testing N

0.0 288.8 0.0

$0 Holders of an OL or COL 50.55a 53.890(a), (

Develop a facility safety program N

0.0 0.0 0.0

$0 53.890(a), (

Implement and maintain a facility safety program N

0.0 0.0 0.0

$0 53.910 Develop procedures and guidelines to support normal plant operations and respond to unplanned events N

0.0 400.0 0.0

$0 Holders of an OL or COL 53.910 Implement and maintain procedures and guidelines to support normal plant operations and respond to unplanned events N

0.0 100.0 0.0

$0 Holders of an OL or COL 53.1010(b) Prepare a plan, and prepare an associated decommissioning report, that ensures that adequate funding will be available for decommissioning.

N 1.0 50.0 50.0

$15,000 Applicants for an OL or COL 50.75(b), 50.82(a)(9) 53.1010(b)

Implement and maintain a plan, and an associated decommissioning report, that ensures that adequate funding will be available for decommissioning.

N 2.0 23.0 46.0

$13,800 Applicants for an OL or COL 50.75(b), 50.82(a)(9)

53.1010(b)

(1)(i)

Before the Commission issues the license, update the decommissioning report to certify the applicant has provided financial assurance for decommissioning in the amount proposed in the application and approved by the NRC N

0.0 5.0 0.0

$0 Applicants for OLs and COLs 53.1060(c) Keep records of information important to the safe and effective decommissioning of the facility N

0.0 5.0 0.0

$0 Licensees 50.75(g) 53.1075 Establish a decommissioning fire protection program.

N 0.0 40.0 0.0

$0 OL and COL holders that have submitted the certifications required under § 53.6075 53.1075 Maintain a fire protection program during decommissioning N

0.0 10.0 0.0

$0 Licensees that have submitted certifications under 53.1575 53.1115 Agreement limiting access to classified information N

2.0 5.0 10.0

$3,000 Applicants for a license or standard design approval 50.37 53.1221 Make engineering documents available for the NRC to audit for a standard design approval N

0.0 500.0 0.0

$0 Applicants for a standard design approval 52.145 53.1263(c) Make engineering documents available for the NRC to audit, if the more detailed information is necessary for the Commission to verify the information in the application and make its safety determination N

2.0 500.0 1,000.0

$300,000 Applicants for a CP, COL, OL, or ML that reference a design certification rule 52.63

53.1540 (53.1545; 53.1550; 53.1560; 53.1565)

Modify licensing basis information, including updating the FSAR, and evaluate potential changes to facilities, procedures, programs, and organizations to determine if NRC approval is required.

N 0.0 338.4 0.0

$0 Holders of an OL or COL.

Holder of a license authorizing operation of a nuclear power reactor that has submitted the certification of permanent cessation of operations required under § 53.1070(a)(1) or a reactor licensee whose license has been amended to allow possession of nuclear 50.59(c) and (d) fuel but not operation of the facility.

53.1805, 53.1810 (53.610(a);

53.610(c);

53.865; 53.1815)

Establish and execute the QA program.

N 0.0 0.0 0.0

$0 53.1825 Develop documented instructions for activities affecting quality N

0.0 0.0 0.0

$0 53.1830 Review and approve changes to documents N

0.0 0.0 0.0

$0 53.1835 Make available and retain documentary evidence that materials and equipment conform to the procurement requirements.

Periodically assess effectiveness of the control of quality by contractors and subcontractors N

0.0 0.0 0.0

$0

53.1845 Establish measures to ensure that special processes (welding, heat treating, and nondestructive testing) are controlled and accomplished by qualified personnel N

0.0 0.0 0.0

$0 53.1850 Establish and execute a program for inspection of activities affecting quality.

N 0.0 0.0 0.0

$0 53.1855 Establish a test program. Document and evaluate test results.

N 0.0 0.0 0.0

$0 53.1860 Establish measures for control of measuring and test equipment N

0.0 0.0 0.0

$0 53.1865 Establish measures to control handling, storage, and shipping of material and equipment N

0.0 0.0 0.0

$0 53.1870 Establish measures to indicate status of inspections, tests, and operating status.

N 0.0 0.0 0.0

$0 53.1875 Establish measures to control materials, parts, or components which do not conform to requirements N

0.0 0.0 0.0

$0 53.1880 Establish measures for corrective actions and document and report corrective actions to management N

0.0 0.0 0.0

$0 53.1885 Maintain records to furnish evidence of activities affecting quality, and establish record retention requirements N

0.0 0.0 0.0

$0 53.1890 Document and review audit results.

N 0.0 0.0 0.0

$0 Total 2

7,928.0 $2,378,400

Rule Section Description Type of Change New (N)

Amended (A)

Removed (R)

Change in Respondents (CR)

Number of Respondents Responses per Respondent Total Responses Burden Hours Per

Response

Total Burden Hours Total Cost at

$300/hour Notes Annual or one-time burden Impact of Proposed Rule on Existing Clearance Burden Hour Estimates Burden Basis 53.605(b)

(2)

Licensees may post a notice describing the regulations of this section and 10 CFR Part 21 and procedures adopted under them, including the name of the individual to whom reports may be made, and states where they may be examined, if posting of the regulation and procedures themselves is not practical.

N 0.0 50.0 0.0 0.25 0.0

$0 Each construction permit and manufacturing license is subject to the terms and conditions of § 53.605(b)(2), and each combined license issued under this part until the NRC makes the finding under § 53.1452(g).

both annual and one-time 50.55(e) 53.610(b)

(2)(iii)

Formal letter of agreement with local fire department prior to receipt of fuel N

0.0 1.0 0.0 1.0 0.0

$0 Holders of an OL or COL one-time 53.1060(e

)

Submit a copy of the PSDAR to the affected states prior to or within 2 years of the permanent cessation of operations N

0.0 1.0 0.0 1.0 0.0

$0 Holders of an OL or COL one-time 50.82(a)(4)(i) 53.1515(

b)(1)

Notify the State where the facility is located of amendment requests N

0.0 1.0 0.0 5.0 0.0

$0 Holders of an OL or COL one-time Total 0

0.0 0.0

$0 Table 5 One-Time Third Party Disclosure

Table Description Burden Hours Cost of $300/hr 1

Reporting 212,873

$63,861,900 2

Recordkeeping 7,928

$2,378,400 3

Third Party Disclosure 0

$0 220,801

$66,240,300 2024-2026 Burden Totals TOTAL