MONTHYEARML24219A2082024-08-0606 August 2024 Ile Form 5.1-1 Postexamination Check Sheet IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 ML24173A1272024-06-12012 June 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Final SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter ML24173A1802024-06-12012 June 2024 Ile Post Exam Comments ML24173A1792024-06-12012 June 2024 Ile Form 2.1-1 Examination Prep Checklist ML24173A1782024-06-12012 June 2024 Ile Form 1.3-1 Examination Security Agreement ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 ML24173A1552024-05-14014 May 2024 Ile Form 2.3-2 Operating Test Quality Checklist ML24173A1562024-05-0202 May 2024 Ile Form 2.3-4 Written Examination Quality Checklist SVP-24-023, Ile Outline Submittal Letter2024-03-29029 March 2024 Ile Outline Submittal Letter SVP-24-018, Ile Proposed Exam Submittal Letter2024-03-13013 March 2024 Ile Proposed Exam Submittal Letter ML24173A1262024-01-23023 January 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Draft ML24173A1252024-01-23023 January 2024 Ile Form 2.3-1 Examination Outline Quality Checklist ML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23079A2262023-03-20020 March 2023 Form 5.1-1 Post-Examination Check Sheet (Quad Cities, 2023) IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 ML23079A2192023-02-21021 February 2023 Form 1.3-1 Exam Security Agreement ML23079A2222023-02-21021 February 2023 Form 2.1-1 Examination Preparation Checklist SVP-23-007, Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023)2023-02-0909 February 2023 Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023) ML23079A2282023-02-0808 February 2023 Post-Exam Review Comments (None) ML23020A4132023-01-23023 January 2023 Operator License Examination Approval - Quad Cities Nuclear Power Station, January 2023 ML23079A2072023-01-13013 January 2023 Form 2.3-4 Written Examination Quality Checklist (Quad Cities, 2023) ML23079A2042023-01-13013 January 2023 Form 2.3-2 Operating Test Quality Checklist (Quad Cities, 2023) ML23079A2032022-11-11011 November 2022 Licensee Proposed Exam Cover Letter (SVP-22-065, Quad Cities, 2023) ML23079A0842022-10-17017 October 2022 Form 3.4-1 Events and Evolutions Checklist (Quad Cities, 2023) ML23079A0432022-10-17017 October 2022 Form 2.3-1 Examination Outline Quality Checklist (Quad Cities, 2023).pdf ML23079A0272022-10-0505 October 2022 Licensee Outline Submittal Email (Quad Cities, 2023) ML22188A1752022-07-11011 July 2022 Confirmation of Initial License Examination RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21281A1242021-10-0808 October 2021 GFE Results, September 2021 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 ML22192A1932021-07-0909 July 2021 2021 QC Ile ES-201-3 Security Agreement-Final ML22192A1922021-07-0909 July 2021 2021 QC Ile ES-201-1 ML22192A2052021-07-0909 July 2021 2021 QC Ile ES-401-9 Written Examination Review Worksheet-Final ML22192A2062021-07-0909 July 2021 2021 QC Ile Outline Submittal Comments ML22192A1952021-07-0909 July 2021 2021 QC Ile ES-403-1 Written Exam Quality Checklist ML22192A2032021-07-0909 July 2021 2021 QC Ile ES-301-7 Operating Test Review Worksheet-Final ML22192A2042021-07-0909 July 2021 2021 QC Ile ES-401-4 Rejected KAs ML22192A1962021-06-22022 June 2021 2021 QC Ile Post-Exam Submittal Letter-06-22-2021 ML22193A1052021-06-14014 June 2021 2021 QC Ile Administered Simulator and Inplant JPMs-Final ML22193A1072021-06-14014 June 2021 2021 QC Ile Administered Simulator Scenarios-Final ML22193A2862021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Written Exam-Final ML22193A2872021-06-14014 June 2021 2021 QC Ile Administered RO and SRO List of Reference Handouts-Final ML22193A0932021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Admin JPMs-Final ML21152A1022021-06-0202 June 2021 Operator Licensing Examination Approval ML22193A3102021-05-0505 May 2021 2021 QC Ile Proposed Simulator and Inplant JPMs ML22193A2992021-05-0505 May 2021 2021 QC Ile ES-301-3 Operating Test Quality Checklist ML22193A3122021-05-0505 May 2021 2021 QC Ile Proposed Written Exam-RO and SRO 2024-08-06
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24219A2082024-08-0606 August 2024 Ile Form 5.1-1 Postexamination Check Sheet IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 ML24173A1792024-06-12012 June 2024 Ile Form 2.1-1 Examination Prep Checklist SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter ML24173A1272024-06-12012 June 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Final ML24173A1782024-06-12012 June 2024 Ile Form 1.3-1 Examination Security Agreement ML24173A1802024-06-12012 June 2024 Ile Post Exam Comments ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 ML24173A1552024-05-14014 May 2024 Ile Form 2.3-2 Operating Test Quality Checklist ML24173A1562024-05-0202 May 2024 Ile Form 2.3-4 Written Examination Quality Checklist SVP-24-023, Ile Outline Submittal Letter2024-03-29029 March 2024 Ile Outline Submittal Letter SVP-24-018, Ile Proposed Exam Submittal Letter2024-03-13013 March 2024 Ile Proposed Exam Submittal Letter ML24173A1252024-01-23023 January 2024 Ile Form 2.3-1 Examination Outline Quality Checklist ML24173A1262024-01-23023 January 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Draft ML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23079A2262023-03-20020 March 2023 Form 5.1-1 Post-Examination Check Sheet (Quad Cities, 2023) IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 ML23079A2222023-02-21021 February 2023 Form 2.1-1 Examination Preparation Checklist ML23079A2192023-02-21021 February 2023 Form 1.3-1 Exam Security Agreement SVP-23-007, Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023)2023-02-0909 February 2023 Licensee Post-Exam Submittal Letter (SVP-23-007, Quad Cities, 2023) ML23079A2282023-02-0808 February 2023 Post-Exam Review Comments (None) ML23020A4132023-01-23023 January 2023 Operator License Examination Approval - Quad Cities Nuclear Power Station, January 2023 ML23079A2072023-01-13013 January 2023 Form 2.3-4 Written Examination Quality Checklist (Quad Cities, 2023) ML23079A2042023-01-13013 January 2023 Form 2.3-2 Operating Test Quality Checklist (Quad Cities, 2023) ML23079A2032022-11-11011 November 2022 Licensee Proposed Exam Cover Letter (SVP-22-065, Quad Cities, 2023) ML23079A0432022-10-17017 October 2022 Form 2.3-1 Examination Outline Quality Checklist (Quad Cities, 2023).pdf ML23079A0842022-10-17017 October 2022 Form 3.4-1 Events and Evolutions Checklist (Quad Cities, 2023) ML23079A0272022-10-0505 October 2022 Licensee Outline Submittal Email (Quad Cities, 2023) ML22188A1752022-07-11011 July 2022 Confirmation of Initial License Examination RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 ML22192A2052021-07-0909 July 2021 2021 QC Ile ES-401-9 Written Examination Review Worksheet-Final ML22192A2062021-07-0909 July 2021 2021 QC Ile Outline Submittal Comments ML22192A2032021-07-0909 July 2021 2021 QC Ile ES-301-7 Operating Test Review Worksheet-Final ML22192A1922021-07-0909 July 2021 2021 QC Ile ES-201-1 ML22192A2042021-07-0909 July 2021 2021 QC Ile ES-401-4 Rejected KAs ML22192A1932021-07-0909 July 2021 2021 QC Ile ES-201-3 Security Agreement-Final ML22192A1952021-07-0909 July 2021 2021 QC Ile ES-403-1 Written Exam Quality Checklist ML22192A1962021-06-22022 June 2021 2021 QC Ile Post-Exam Submittal Letter-06-22-2021 ML22193A1072021-06-14014 June 2021 2021 QC Ile Administered Simulator Scenarios-Final ML22193A2872021-06-14014 June 2021 2021 QC Ile Administered RO and SRO List of Reference Handouts-Final ML22193A0932021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Admin JPMs-Final ML22193A2862021-06-14014 June 2021 2021 QC Ile Administered RO and SRO Written Exam-Final ML22193A1052021-06-14014 June 2021 2021 QC Ile Administered Simulator and Inplant JPMs-Final ML21152A1022021-06-0202 June 2021 Operator Licensing Examination Approval ML22193A3112021-05-0505 May 2021 2021 QC Ile Proposed Simulator Scenarios ML22193A3012021-05-0505 May 2021 2021 QC Ile ES-301-6 Competencies Checklist ML22193A2992021-05-0505 May 2021 2021 QC Ile ES-301-3 Operating Test Quality Checklist ML22193A3002021-05-0505 May 2021 2021 QC Ile ES-301-4 Simulator Scenario Quality Checklist 2024-08-06
[Table view] |
Text
Form 2.3-2 Operating Test Quality Checklist
Facility: Date of Examination: Operating Test Number:
General Criteria (Y)es / (N)o a b* c #
- a. The operating test meets the criteria on the associated test outline. Y
- b. There are enough test items so that test items will not be repeated on more than 1 day of Y the operating test.
- c. The operating test does not duplicate items from the applicants audit test(s). Y
- d. Overlap with the written examination and between different parts of the operating test is Y minimized.
- e. It appears that the operating test will differentiate between competent and Y less-than-competent applicants at the designated license level.
Walkthrough Criteria F
- a. Each job performance measure (JPM) includes the following, as applicable:
- references and tools, including associated procedures
- reasonable and validated time limits (average time allowed for completion) and specific designation if the facility licensee deems it to be time critical
- alternate path JPMs are labeled as alternate path Y
- operationally important specific performance criteria that include the following:
- detailed expected actions with exact criteria and nomenclature
- system response and other examiner cues
- statements describing important observations to be made by the applicant
- criteria for successful completion of the JPM task standard
- identification of critical steps and their associated performance standards
- restrictions on the sequence of steps, if applicable
- b. Ensure that any changes from the previously approved JPM outlines (Forms 3.2-1 and 3.2-2) have not caused the test to deviate from any of the acceptance criteria (e.g., item Y distribution, bank use, repetition from the last two NRC examinations) specified on those forms.
Simulator Scenario Set Criteria for Scenario Numbers: / /
QUALITATIVE ATTRIBUTES (r 02pFyiycyoCF 3ihycy3inFoepFepoCyncy FyiFc2ocFn3tpFpEgyOtpicFoih13eFyincegtpicocy3iFtoUF-p Y 3gcF3aFnpe/y pfF-gcFycFh3pnFi3cF gpFc2pF3Opeoc3enFyic3FpVOp cphFp/picnr Gr 02pFn pioey3nF 3inyncFt3ncCUF3aFepCocphFp/picnr Y
Br mo 2Fp/picFhpn eyOcy3iF 3inyncnF3aFc2pFa3CC3kyiSN the point in the scenario when it is to be initiated Y the malfunction(s) or conditions that are entered to initiate the event the symptoms/cues that will be visible to the crew the expected operator actions (by shift position) the event termination point (if applicable)
QUALITATIVE ATTRIBUTES (continued) (Y)es / (N)o a b* c#
- 4. The events are valid with regard to physics and thermodynamics. Y
- 5. The sequencing and timing of events is reasonable and allows the examination team to Y observe and evaluate applicant performance.
- 6. If time compression techniques are used, the scenario summary clearly so indicates. Y Operators have sufficient time to carry out expected activities without undue time constraints. Cues are given.
- 7. The simulator modeling is not altered. Y
- 8. The scenarios have been validated. Pursuant to 10 CFR 55.46(d), any open simulator Y performance deficiencies or deviations from the referenced plant have been evaluated to ensure that functional fidelity is maintained while running the planned scenarios.
- 9. Scenarios are new or significantly modified in accordance with ES-3.4. Y
- 10. Scenarios (as grouped) allow each applicant to be significantly involved in the minimum Y number of transients, events, and evolutions specified on the version of Form 3.4-1 submitted with the scenario set.
- 11. Applicants are evaluated on a similar number of preidentified critical tasks across Y scenarios, when possible.
- 12. The level of difficulty is appropriate to support licensing decisions for each crew position. Y
Actual Attributes by (Y)es / (N)o TARGET QUANTITATIVE ATTRIBUTES per Scenario (See ES-3.4) Scenario No.
/ / a b* c#
- 1. Malfunctions after emergency operating procedure (EOP) 2 / /
entry (1-2) Y
- 2. Abnormal events (2-4) / / 44 Y
- 3. Major transients (1-2) / / Y
- 4. EOPs entered/requiring substantive actions (1-2) / / 2 Y
- 5. Entry into a contingency EOP with substantive actions / /
(> 1 per scenario set; set is the entire set of scenarios Y prepared for the scheduled exam)
- 6. Preidentified critical tasks (> 2) / / 33 Y
Printed Name/Signature Date
- a. Author ______________________________________________________________
- b. Facility Reviewer (*) ______________________________________________________________
- c. NRC Reviewer (#) ________________________________________________________________
NRC Chief Examiner _________________________________________________________________
NRC Supervisor _________________________________________________________________
- The facility licensee signature is not applicable for NRC-developed tests.