Similar Documents at Surry |
---|
Category:Acceptance Review Letter
MONTHYEARML24116A2822024-04-25025 April 2024 Acceptance of Requested Licensing Action: Surry TS Change Section 3.8 Containment Temperature and Pressure Requirements and Surveillances ML23311A3192023-11-0707 November 2023 Relief Request Acceptance Review Results; Surry Unit 1 and 2 IST Alternative, V-1 RCS Cold Leg Check Valves ML23030B8472023-03-10010 March 2023 Issuance of Amendment Nos. 309 and 309, License Amendment Request Regarding a 10-Day Allowed Outage Time for Opposite Unit Auxiliary Feedwater Cross-Connect Capability ML22342A1002022-12-0707 December 2022 Relief Request Acceptance Review Results; Surry ISI Alternative, Prz and SG Welds and Nozzles ML22224A1442022-08-11011 August 2022 Acceptance Email TS Change AFW Cross Connect AOT LAR ML22202A0472022-07-25025 July 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Surry Technical Specification Change Auxiliary Feedwater Allowed Outage Time ML22200A1032022-07-19019 July 2022 Acceptance of Requested Licensing Action: Surry Risk-Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML22161B0052022-06-0909 June 2022 Acceptance Email TSTF 547 LAR ML22077A0542022-03-18018 March 2022 Change in Engineering Hours Estimate Surry Ph Buffer LAR Acceptance ML21340A1642021-12-0606 December 2021 Acceptance of Requested Licensing Action Amendment ML19036A9022019-02-0505 February 2019 Acceptance of Amendment Request Revising Emergency Action Level Schemes ML18320A2362018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing Letter - v3 ML17055B6222017-02-10010 February 2017 Email - Acceptance Review, January 20, 2017 Virginia Electric and Power Company for Surry Power Station, Unit Nos. 1 and 2 ML1006103302010-03-0404 March 2010 Acceptance of Requested Licensing Action Regarding Measurement Uncertainty Recapture Power Uprate. ML0934304152009-12-0808 December 2009 Submittals Re. Dominion - Mixing Vane Grid Spacing Restriction Found Acceptable for Review 2024-04-25
[Table view] Category:E-Mail
MONTHYEARML24282A9732024-10-0808 October 2024 Temporary SW Piping LAR Acceptance Email ML24116A2822024-04-25025 April 2024 Acceptance of Requested Licensing Action: Surry TS Change Section 3.8 Containment Temperature and Pressure Requirements and Surveillances ML24102A0682024-04-10010 April 2024 IST (z)(2) Hardship RR V-1 RCS Cold Leg, Lh Safety Injection Check Valves ML24075A1762024-03-15015 March 2024 Email, Acceptance of Requested Licensing Action: Surry TSTF-577, Rev. 1 ML24144A2432024-03-0808 March 2024 002 Radiation Safety Baseline Inspection Information Request ML24065A2532024-03-0505 March 2024 RAI Issuance Surry RR IST P-1 P-2 ML23355A2722023-12-21021 December 2023 NRR E-mail Capture - Schedule Revision for Emergency Preparedness Staff Augmentation Times License Amendment Request ML23312A2022023-11-0808 November 2023 Relief Request Acceptance Review Results; IST Impracticality P-1 P-2 RHR Containment Pumps ML23312A2962023-11-0808 November 2023 Email - Surry Relief Request Acceptance Review Results; Surry Unit 1 and 2 IST P-3 P-4 Pumps ML23283A3262023-10-10010 October 2023 Update Acceptance Review Status Surry TS Change Apply RG 1.97, Rev 3 Instrumentation to Lhsi ML23255A2772023-09-12012 September 2023 Acceptance of Requested Licensing Action: Surry TS Change, Lhsi Indication and Instrumentation ML23193A9552023-07-12012 July 2023 NRR E-mail Capture - Acceptance Review for VC Summer and Surry Relief Request (L-2023-LLR-0029) ML23187A1122023-07-0606 July 2023 TSC Relocation LAR RAIs ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23107A2212023-04-10010 April 2023 Amendment Turbine Building Wind Load Basis Reclassification License Amendment Request - State Consultation No Comment ML23068A0242023-03-0808 March 2023 RAI Issuance Fuel Handling Trolley LAR ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23054A2412023-02-23023 February 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry Turbine Building Tornado Reclassification ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML23018A1642023-01-17017 January 2023 Formal Issuance of RAIs for Surry ISI Alternative for SG Welds, 30 Day Calendar Response Period (Email) ML22354A0352022-12-19019 December 2022 Acceptance Email TSC Relocations LAR ML22349A2102022-12-15015 December 2022 Formal 43-day Request for Additional Information Issuance for Surry Turbine Building License Amendment Request ML23058A1442022-12-0909 December 2022 Record of Surry Verbal Relief Request Authorization - V-01 Mechanical Agitation Vavle 1-SI-241 ML22342A1002022-12-0707 December 2022 Relief Request Acceptance Review Results; Surry ISI Alternative, Prz and SG Welds and Nozzles ML22335A4842022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for LAR North Anna Power Station - Units 1 and 2 and Surry Power Station - Units 1 and 2 Emergency Plan Staff Augmentation Times (L-2022-LLA-0166) ML22277A7252022-10-0303 October 2022 Additions to Turbine Bldg Wind Load Audit ML22256A3032022-09-13013 September 2022 Change in Completion Hours Estimate Amendment Turb Bldg. Loading Basis Change LAR ML22256A2312022-09-13013 September 2022 Acceptance Email TS Change for New Fuel Framatome Agora and SFP Criticality Review ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22224A1442022-08-11011 August 2022 Acceptance Email TS Change AFW Cross Connect AOT LAR ML22223A1182022-08-0404 August 2022 2022004 - Plant Surry RP Inspection - Document Request Letter E-mail ML22200A1032022-07-19019 July 2022 Acceptance of Requested Licensing Action: Surry Risk-Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML22193A0052022-07-11011 July 2022 Acceptance of Requested Licensing Action: Admin Changes to Technical Specifications ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22161B0052022-06-0909 June 2022 Acceptance Email TSTF 547 LAR ML22137A1622022-05-17017 May 2022 Acceptance of Requested Licensing Action Amendment Turb Bldg. Loading Basis Change License Amendment Request ML22110A2052022-04-19019 April 2022 Formal Issuance of RAIs for Post LOCA Buffer Change LAR ML22104A0252022-04-14014 April 2022 NRR E-mail Capture - Dominion Presentation Slides for April 21, 2022 Public Meeting on Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station ML22077A0542022-03-18018 March 2022 Change in Engineering Hours Estimate Surry Ph Buffer LAR Acceptance ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22012A0572022-01-11011 January 2022 Issuance of RAIs for Surry Unit 1, Spring 2021 Steam Generator Tube Inspection ML21340A1642021-12-0606 December 2021 Acceptance of Requested Licensing Action Amendment ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21272A0622021-09-28028 September 2021 NRR E-mail Capture - (External_Sender) Surry Fuel Melt Safety Limit (SL) LAR Question ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21270A0232021-07-0707 July 2021 State of Virginia Notification of Pending Amendment Issuance Ref: Surry Power Station, Units 1 and 2 - Request to Revise Technical Specifications 2.1.A.1.b ML21144A2592021-05-0606 May 2021 003 Radiation Safety Baseline Inspection Information Request 2024-04-25
[Table view] |
Text
John Klos
From: John Klos Sent: Thursday, April 25, 2024 10:00 AM To: gary.d.miller@dominionenergy.com Cc: John Klos
Subject:
FW: Acceptance of Requested Licensing Action: Surry TS change Sec. 3.8 containment temperature and pressure requirements and surveillances
- Gary,
By letter dated March 22, 2024 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML24087A208 Virginia Electric and Power Company (Dominion Energy Virginia) submitted a license amendment for Surry Power Station (Surry) Units 1 and 2. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to begin its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal the NRC staff has estimated that this licensing request will take approximately 285 hours0.0033 days <br />0.0792 hours <br />4.712302e-4 weeks <br />1.084425e-4 months <br /> to complete. The NRC staff expects to complete this review in 11 months from the end of the acceptance period on March 31, 2025 which coincides with Dominion Energy Virginias requested date. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application, and they could change, due to several factors including requests for additional information,
1 unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.
If you have any questions, please contact me.
Thanks in advance,
John Klos DORL Mcguire, Surry Licensing Project Manager U.S. NRC, Office of Nuclear Reactor Regulation (NRR),
Division of Operating Reactor Licensing (DORL),
NRC/NRR/DORL/LPL2-1, MS O80B01A Washington, DC 20555-0001 301.415.5136, John.Klos@NRC.gov
2