Cover Letter for the U.S. NRC Final Safety Evaluation for Westinghouse Electric Company Topical Report WCAP-18446-P/WCAP-18446-NP, Revision 0, Incremental Extension of Burnup Limit for Westinghouse and Combustion Engineering Fuel Designs
ML24107B159
Person / Time
Site: Westinghouse
Issue date: 06/26/2024
From: Gerond George
Licensing Processes Branch
To: Zozula C
Westinghouse
Shared Package
ML24107B157 List:
References
EPID L-2020-TOP-0064, WCAP-18446-P, WCAP-18446-NP, Rev. 0
Download: ML24107B159 (3)


Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION June 26, 2024 Camille Zozula Manager, Infrastructure & Facilities Licensing Westinghouse Electric Company 1000 Westinghouse Drive, Building 1, Suite 165 Cranberry Township PA 16066

SUBJECT:

FINAL SAFETY EVALUATION FOR WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-18446-P/WCAP-18446-NP, REVISION 0, INCREMENTAL EXTENSION OF BURNUP LIMIT FOR WESTINGHOUSE AND COMBUSTION ENGINEERING FUEL DESIGNS (EPID: L-2020-TOP-0064)

Dear Camille Zozula,

By letter dated December 14, 2020, Westinghouse Electric Company (Westinghouse) submitted to the U.S. Nuclear Regulatory Commission (NRC) Westinghouse Topical Report (TR)

WCAP-18446-P/WCAP-18446-NP, Revision 0, Incremental Extension of Burnup Limit for Westinghouse and Combustion Engineering Fuel Designs. By the letter dated February 26, 2024, the U.S. Nuclear Regulatory Commission (NRC) staff issued its draft safety evaluation (SE) (Agencywide Documents Access and Management System Accession No. ML23278A058).

The NRC staff has found the TR acceptable for referencing in licensing applications for nuclear power plants to the extent specified and under the limitations delineated in the TR and in the NRC final SE. The final SE defines the basis for our acceptance of the TR.

Our acceptance applies only to material provided in the subject TR. We do not intend to repeat our review of the accepted material described in the TR. When the TR appears as a reference in license applications, our review will ensure that the material presented applies to the specific plant involved. License amendment requests that deviate from this TR will be subject to a plant-specific review in accordance with applicable review standards.

NOTICE: Enclosure 2 to this letter contains Proprietary Information. Upon separation from Enclosure 2, this letter is DECONTROLLED.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION In accordance with the guidance provided on the NRC website, we request that Westinghouse publish accepted versions of the proprietary and non-proprietary TR within three months of receipt of the date of this letter. The accepted proprietary version shall incorporate this letter and the proprietary final SE (Enclosure 2), and the accepted non-proprietary version shall incorporate this letter and the non-proprietary final SE (Enclosure 1) after the title page. Also, the accepted versions must contain historical review information, including NRC requests for additional information (RAIs) and your responses after the title page. The accepted version shall include an -A (designating accepted) following the TR identification symbol.

As an alternative to including the RAIs and RAI responses behind the title page, if changes to the TRs were provided to the NRC staff to support the resolution of RAI responses, and the NRC staff reviewed and approved those changes as described in the RAI responses, there are two ways that the accepted version can capture the RAIs:

1. The RAIs and RAI responses can be included as an Appendix to the accepted version.
2. The RAIs and RAI responses can be captured in the form of a table (inserted after the final SE) which summarizes the changes as shown in the approved version of the TR. The table should reference the specific RAIs and RAI responses which resulted in any changes, as shown in the accepted version of the TR.

If future changes to the NRCs regulatory requirements affect the acceptability of this TR, Westinghouse will be expected to revise the TR appropriately. Licensees referencing this TR would be expected to justify its continued applicability or evaluate their plant using the revised TR.

If you have any questions, please contact the Project Manager for the review, Ekaterina Lenning at 301-415-3151 or via electronic mail at Ekaterina.Lenning@nrc.gov.

Sincerely,

/RA/

Gerond A. George, Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902038

Enclosures:

1. Final SE (Non-Proprietary)
2. Final SE (Proprietary)

ML24107B157 (Package)

ML24107B159 (Cover Letter)

ML24176A258 (Non-Proprietary Final SE Enclosure 1)

ML24107B158 (Proprietary Final SE Enclosure 2)

NCP-2023-006: ML24053A348 OFFICE NRR/DORL/LLPB/

PM NRR/DORL/LLPB/

LA NRR/DSS/SFNB NRR/DSS/SFNB NRR/DSS/SFNB/

BC NAME ELenning DHarrison JLehning Nonconcur KHeller Nonconcur SKrepel DATE 5/15/2024 5/22/2024 12/06/2023 12/06/2023 5/23/2024 OFFICE OGC - NLO NRR/DORL/LLPB/