From:
Dennis Galvin Sent:
Friday, February 16, 2024 2:29 PM To:
Wendy Brost (webrost@stpegs.com)
Cc:
Thomas Byrd
Subject:
South Texas Project - Draft Request for Additional Information - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications (L-2023-LLE-0046)
Attachments:
STP 73.5 Exemption Request Draft RAI Issued 2024-02-16.pdf
Dear Ms. Brost,
By letter dated November 16, 2023 (ML23324A010), STP Nuclear Operating Company (STPNOC) requested an exemption for South Texas Project, Units 1 and 2 and the independent spent fuel storage installation (STP). In particular, STPNOC requested an exemption from the specific requirements in 10 CFR Part 73, Subpart T, and for the definitions for the terms "Contraband," and "Time of Discovery" in 10 CFR 73.2 until the later of March 31, 2025, or 180 days after publication of the final Regulatory Guides.
To complete its review, the NRC staff has prepared a request for additional information (RAI) in DRAFT form. To arrange a clarification call for the draft RAIs and to discuss the due date for the RAI response, please contact me at (301) 415-6256.
Respectfully, Dennis Galvin Project Manager U.S Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Operating Reactor Licensing Licensing Project Branch 4 301-415-6256 Docket Nos. 50-498, 50-499, and 72-1041
Hearing Identifier:
NRR_DRMA Email Number:
2401 Mail Envelope Properties (SA1PR09MB81115F4423D9E8F4EED72816FB4C2)
Subject:
South Texas Project - Draft Request for Additional Information - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications (L-2023-LLE-0046)
Sent Date:
2/16/2024 2:28:45 PM Received Date:
2/16/2024 2:28:00 PM From:
Dennis Galvin Created By:
Dennis.Galvin@nrc.gov Recipients:
"Thomas Byrd" <Thomas.Byrd@nrc.gov>
Tracking Status: None "Wendy Brost (webrost@stpegs.com)" <webrost@stpegs.com>
Tracking Status: None Post Office:
SA1PR09MB8111.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1035 2/16/2024 2:28:00 PM STP 73.5 Exemption Request Draft RAI Issued 2024-02-16.pdf 195670 Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
DRAFT REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR EXEMPTION FROM ENHANCED WEAPONS, FIREARMS BACKGROUND CHECKS, AND SECURITY EVENT NOTIFICATIONS STP NUCLEAR OPERATING COMPANY SOUTH TEXAS PROJECT, UNITS 1 AND 2 DOCKET NOS. 50-498, 50-499, AND 72-1041 EPID NO. L-2023-LLE-0046
Background:
By letter dated November 16, 2023 (ML23324A010), STP Nuclear Operating Company (STPNOC) requested an exemption for South Texas Project, Units 1 and 2 and the independent spent fuel storage installation (STP). In particular, STPNOC requested an exemption from the specific requirements in 10 CFR Part 73, Subpart T, and for the definitions for the terms "Contraband," and "Time of Discovery" in 10 CFR 73.2 until the later of March 31, 2025, or 180 days after publication of the final Regulatory Guides.
Technical Basis for Request: The licensee justification for the duration of the exemption is based on the completion of the regulatory guidance and the time necessary for STPNOC to go through the change management processes adequately to include the number of training weeks that will be required. However, the impacts identified by the licensee to the change management processes and training schedules appear to be generic to the nuclear industry and do not provide site-specific impacts and timelines to support the March 31, 2025, exemption duration date.
Request: Provide additional justification for delaying implementation of 10 CFR Part 73, Subpart T, requirements and for the terms Contraband and Time of Discovery to the March 31, 2025, exemption duration date. Include information regarding the site-specific impacts and the expected timeline needed to revise the security programs, procedures, and training for personnel in order to support STPNOCs requested duration for the exemption. Alternatively, revise the exemption request for the requested calendar date for implementation of Subpart T and the definitions of Time of Discovery and Contraband.