LTR-NRC-2024-01 Mackson-Duke 10CFR Part 21 Final Notification and Closure 2.2.2024
ML24037A020
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 02/02/2024
From: Echols S
Mackson Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LTR-NRC-2024-01
Download: ML24037A020 (1)


Text

Mackson Nuclear, LLC 2346 Southway Drive Rock Hill, SC 29730 803-634-8176 fax TO:

U.S. Nuclear Regulatory Commission Document Control Desk FAX:

301-816-5151 PHONE: 301-816-5100 RE:

Final Report Notification Pursuant to 10 CFR Part 21.21 FROM:

Shannon Echols, Mackson Nuclear, LLC PAGES:

9 (including this cover page)

DATE:

February 2, 2024 CC:

N/A Comments: Please see the attached Final Notification and Closure of our previous Interim Notification Pursuant to 10 CFR Part 21.21. The information contained within this notification was also submitted by Tioga Pipe, Inc. on February 2, 2024.

1WACK$ON 2346 Southway Drive Rock Hill, SC 29730 February 2, 2024 LTR-NRC-2024-01 Revision 0 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001 Phone: (301) 816-5100 Fax: (301) 816-5151 E-Mail: hoo.hoc@nrc.gov

SUBJECT:

Closure of Interim Report Notification Pursuant To 10 CFR Part 21.21 Regarding Supply Of 1" Sch. 80 (0.180" Wall) SB466 UNS C71500 Buttweld Long Radius 90 Degree Elbow; Manufacturer: Flowline; 27 pieces - Heat Code: 127514, Fitting IDs: 16836-1-1 through 27; 1 piece -

Heat Code: 127976, Fitting ID: 16836-1-28.

This letter is being provided to update the status of a recent interim report submitted by Mackson Nuclear, LLC in accordance with 10CFR 21.21. The interim report was provided on Mackson letter, LTR-NRC-2023-01, dated December 11, 2023 (a duplicate Part 21 notification to one made by Tioga Pipe, Inc., Event Notification 56882, NRC Log No. 2023-26-00, Accession No. ML23352A238).

The licensee, Duke Energy-Brunswick Nuclear Plant, evaluated the installed elbows for acceptability in accordance with their corrective action program. Brunswick inspectors performed UT thickness evaluations of the installed nonconforming elbows (Fitting IDs: 16836-1-3, -14, and -20) and the results were used to confirm that the subject system remained operable. The remaining six nonconforming elbows (Fitting IDs: 16836-1-1, -6, -7, -11, -15, and -21) have been returned to the manufacturer, Flowline, and are being processed and controlled under Flowline's nonconforming items program. Please see the attached Enclosure, "Tioga Pipe, Inc.

LTR-TP-24-03 dated January 30, 2024" for more details of the evaluation and determination.

If you have any questions, please feel free to contact me at (215) 701-1203 or our Quality Assurance Manager, Shannon Echols, at (803) 992-8202.

Page 1 of 2

.\\JJ.\\JA CK SON A

Ccr,r:.in,.

2346 Southway Drive Rock Hill, SC 29730

Regards,
J /;

0.(~

General Manager Mackson Nuclear, LLC

Enclosure:

1) Attachment 1, Tioga Pipe, Inc. LTR-TP-24-03 dated January 30, 2024 Cc:

Andrew Keiser, Tioga Pipe, Inc.

David Keiser, Tioga Pipe, Inc.

William Kotcher, Tioga Pipe, Inc.

Bryan Nichols, Tioga Pipe, Inc.

Shannon Echols, Mackson Nuclear, LLC Page 2 of2

ATTACHMENT 1 LTR-TP-24-03 U.S. Nuclear Regulatory Commission Document Control Desk Washington, O.C.

20555-0001 Phone: (301)816-5100 Fax: (301) 816-5151 E-Mail: EIE@nrc.gov January 30, 2024

SUBJECT:

Closure of Interim Report Notification Pursuant To 10 CFR Part 21.21, Regarding Supply Of 1" Sch. 80 (0.180" Wall) 58466 UNS C71500 Buttweld Long Radius 90 Degree Elbow; Manufacturer: Flowllne; Heat No: 27668; 27 pieces - Heat Code: 127514, Fitting IDs: 16836-1-1 through 27; 1 piece -

Heat Code: 127976, Fitting ID: 16836-1-28.

This letter is bejng provided to update the status of a recent interim report submitted by Tioga Pipe Co In accordance with 10CFR 21.21. The Interim report was provided on Tioga letter, L TR-TP-23-35, dated December 8, 2023 (NRC Log No. 2023-26-00, Accession No. ML23352A238 ).

The licensee, Duke Energy - Brunswick Nuclear Plant, evaluated the Installed elbows for acceptablllty In accordance with their corrective action program. Brunswick inspectors performed UT thickness evaluations of the Installed nonconforming elbows (Fitting IDs:

16836-1-3, 14, and 20) and the results were used to confirm that the subject system remained operable. The remaining six nonconforming elbows (Flttlng IDs: 16836-1-1, 6, 7, 11, 15, and 21) have been returned to the manufacturer, Flowline and are being processed and controlled under Flowllne's nonconfonnlng Items program.

Please see Enclosure, "Email Chain - Part 21 Response for RHR Pump Seal Cooler Elbows" and "Email Chain - PO 608670 SO 16836-1" for more details of the evaluation and determination, If you have any questions, please feel free to contact me at (713) 512-3569 or our Quality Director, Bryan Nichols, at {484) 546-5613.

R7lf'

~Kotcher" President Tioga Pipe Inc.

Enclosures:

1) Email Chain - Part 21 Response for RHR Pump Seal Cooler Elbows Page 1 of 2 File Location: \\ \\FILESVR 1 \\Pubhc\\fORKS\\QA\\Lcttcrs and Corresponi;te.ni:c.s

ATTACHMENT 1 LTR-TP-24-0l

2) Emall Chain - PO 608670 so 16836-1 Cc:

Andrew Keiser, Tioga David Keiser, Tioga Bryan Nichols, lloga Richard Crowley, lloga Glenn Reigel, Tioga Shannon Echols, Mackson Page 2 or 2 FIie Location: \\ \\Fl l.f SVIU \\Public\\fORKS\\QA \\Le.tt~,~ anct <;qrrcspor,Jfcn,;_es

Nichols, Bryan From:

Sent:

To:

Cc:

Subject:

ATTACHMENT 1 Banker, Christopher Brent <Christopher.Banker@duke energy.com>

Friday, December 15, 2023 10:12 AM Pickens, Matthew William; Echols, Shannon; Nichols, Bryan; Reigel, Glenn; Simmons, Rick Denny, Jacob; Thomas, Jonathan; Yodersmith, Stephen B RE: [EXTERNAL] RE: EXTERNAL:FW: Part 21 Response for RHR Pump Seal Cooler Elbows Some people who received this message don't often get email from christopher.banker@duke-energy.com. Learn why this is m1portant ATTENTION: This email came from an external source. Do not open attachments or click on links from unknown senders or unexpected emails.

That is correct, UT readings on the installed elbows show that they exceed nominal thickness, and we are leaving them installed.

Thanks, Chris Banker BNP Design Support Engineering From: Pickens, Matthew William <Matthew.Pickens@duke-energy.com>

Sent: Thursday, December 14, 2023 4:53 PM To: Echols, Shannon <SEchols@mackson.biz>; Nichols, Bryan <bnichols@tiogapipe.com>; Reigel, Glenn

<greigel@tiogapipe.com>; Simmons, Rick <Rick.Simmons@duke-energy.com>; Banker, Christopher Brent

<Christopher.Banker@duke-energy.com>

Cc: Denny, Jacob <Jacob.Denny@duke-energy.com>; Thomas, Jonathan <Jonathan.Thomas@duke-energy.com>;

Yodersmith, Stephen B <Stephen.Yodersmith@duke-energy.com>

Subject:

RE: [EXTERNAL] RE: EXTERNAL:FW: Part 21 Response for RHR Pump Seal Cooler Elbows Hi Shannon, Rick's group has the remaining elbows in hand. Rick would you look into this for Mackson?

Regarding the installed elbows, my understanding is that based on the UT results the installed elbows do not pose an operability concern. Including Chris Banker to validate.

Matt Pickens Engineering Technologist, PE Support Cell 919-738-5224

~-.., DUKE

~"ENERGY.

From: Echols, Shannon <SEchols@mackson.biz>

Sent: Thursday, December 14, 2023 3:18 PM To: Pickens, Matthew William <Matthew.Pickens@duke-energy.com>; Nichols, Bryan <bnichols@tiogapipe.com>;

Reigel, Glenn <greigel@tiogapipe.com>

Cc: Denny, Jacob <Jacob.Denny@duke-energy.com>; Thomas, Jonathan <Jonathan.Thomas@duke-energy.com>;

ATTACHMENT 1 Yodersmith, Stephen B <Stephen.Yodersrnith@duke-energy.com>; Simmons, Rick <Rick.Simrnons@Qgl<e-energy~>

Subject:

RE: [EXTERNAL] RE: EXTERNAL:FW: Part 21 Response for RHR Pump Seal Cooler Elbows Good afternoon, Matt, I'm just following up to see if you're planning on returning the elbows referenced on RMA# 212 that weren't installed. Have you decided if you'll be returning any of the other elbows that haven't been installed? Has there been a decision made about what you're going to do with the elbows that have been installed?

Best regards, Shannon Echols Quality Assurance Manager

-,~:~/ A1ACKSON' f

-,.-,4*1 Mackson Nuclear, LLC 2346 Southway Drive, Rock Hill, SC 29730 Office 1-803-992-8202 Fax 803-329-1077 Email sechols@mackson.biz mackson.biz From: Pickens, Matthew William <Matthew.Pickens@duke-energy.com>

Sent: Tuesday, December 12, 2023 4:35 PM To: Echols, Shannon <SEchols@mackson.biz>; Nichols, Bryan <bnichols@tiogapipe.com>; Reigel, Glenn

<greigel@tiogapipe.com>

Cc: Denny, Jacob <Jacob.Denny@duke-energy.com>; Thomas, Jonathan <Jonathan.Thomas@duke-energy.com>;

Yodersmith, Stephen B <Stephen.Yodersmith@duke-energy.com>; Simmons, Rick <Rick.Simmons@duke-energy.com>

Subject:

RE: [EXTERNAL] RE: EXTERNAL:FW: Part 21 Response for RHR Pump Seal Cooler Elbows ATTENTION: This email came from an external source. Do not open attachments or click on links from unknown senders or unexpected emails.

Hey Shannon, Appreciate your response.

Originally, when we first were looking into the issue and as we were determining the correct interpretation of the spec the best case scenario was that 3 were installed. Once we determined that the.180 min wall was the actual minimum, the scope increased to 9.

Here is the sample ID information you requested. Thank you, Rick.

Fitting ID#

16836-1-2 16836-1-3 16836-1-4 16836-1-10 13836-1-14 16836-1-16 2

ATTACHMENT 1 Nichols, Bryan From:

Nichols, Bryan Sent:

To:

Wednesday, January 10, 2024 11 :24 AM Tidy, Robert Cc:

Reigel, Glenn; Shackelford, Nicole; Echols, Shannon

Subject:

RE: EXTERNAL:Fwd: EXTERNAL:Fwd: PO 608670 SO 16836-1

Rob, Good morning. Those are the three nonconforming fittings that were installed by Duke. No, Flowline can keep the nonconforming fittings. I will follow-up with them regarding the supplier corrective action. Please let me know if you have any questions.

Thank you, Bryan Nichols Director I Quality Assurance 100 Mort Drive, Easton, PA 18040 484-546-5613 Office 610-252-7473 Email bnichols@tiogapipe.com I tm From: Tidy, Robert <rtidy@tiogapipe.com>

Sent: Wednesday, January 10, 2024 11:17 AM 215-435-2806 To: Shackelford, Nicole <NShackelford@mackson.biz>; Echols, Shannon <SEchols@mackson.biz>

Cc: Reigel, Glenn <greigel@tiogapipe.com>; Nichols, Bryan <bnichols@tiogapipe.com>

Subject:

FW: EXTERNAL:Fwd: EXTERNAL:Fwd: PO 608670 SO 16836-1 Importance: High Please have Duke advise on the 3 pieces not received at Flowline. 3,14,20.

Bryan, do we need Flowline to send these to Tioga?

Regards, Robert B Tidy Account Manager I Nuclear 2450 Wheatsheaf Lane, Philadelphia, PA 19137 Office 215-831-0700 Direct 215-701-1271 Mobile 215-287-0656 Ema i ! ru_cJ__y_@.l;j_Qg_a~.com

ATTACHMENT 1 From: Brad Seidel <BradSeidel@flowlinefittings.cQm>

Sent: Wednesday, January 10, 202411:12 AM To: Tidy, Robert <rtidy@tiogapipe_,_fQ.!ll>; Caroline Lemay <lemayc@ezeflow.com>; Margaret Hunt

<rnargaretc@flowlinefittings.com>; Renee Wise <reneew@flowlinefittings.com>

Cc: Bernard Stabile <stabile-b@ezeflow.com>; Marty Capoferri <capoferrim@flowlinefittings.com>; Pat Fiello

<patf@flowlinefittings.com>

Subject:

RE: EXTERNAL:Fwd: EXTERNAL:Fwd: PO 608670 SO 16836-1 A ITENTION: This email came from an external source. Do not open attachments or click on links from unknown senders or unexpected emails.

Rob, We received 6 of the 9 pcs back. They are PCS# 1, 6, 7, 11, 15, 21.

B rcuL S elilelt From: Tidy, Robert <rtidy@tiogapipe.com>

Sent: Wednesday, January 10, 2024 10:37 AM To: Caroline Lemay <lemayc@ezeflow.com>; Margaret Hunt <margaretc@flowlinefittings.com>; Renee Wise

<reneew@flowlinefittings.com>

Cc: Brad Seidel <BradSeidel@flowlinefittings.com>; Bernard Stabile <stabile-b@ezeflow.com>; Marty Capoferri

<capoferrim@flowlinefittings.com>; Pat Fiello <patf@flowlinefittings.com>

Subject:

RE: EXTERNAL:Fwd: EXTERNAL:Fwd: PO 608670 SO 16836-1 Importance: High Good day, Per Duke, these fittings were delivered to Flow line on January 5th. Please confirm.

Regards, Robert B Tidy Account Manager I Nuclear 2450 Wheatsheaf Lane, Philadelphia, PA 19137 Office 215-831-0700 Direct 215-701-1271 Mobile 215-287-0656 Email rtidy@tiogaQlle&om tiogapipe.com ! l:ffl From: Caroline Lemay <lemayc@ezeflow.com>

Sent: Monday, December 4, 2023 3:44 PM 2