1LOT23 NRC Examination Student Questions During Exam and Proctor Responses Beaver Valley 1LOT23 Page 1 of 2 Time Individual Question/Response 0800 Start Exam 0819 Question #_18_
Question: Are the three procedures listed after How will the crew respond to the given plant conditions? part of the given plant conditions?
Are they only there to give the procedure title?
Response: You have enough information to answer the question.
0839 Question # 33 Question: Does the output failing hi mean that the PCV is open?
Response: You have enough information to answer the question.
0904 Question # 36 Question: Are the breaker positions indicating prior to the trip signal or after the signal was received?
Response: You have enough information to answer the question.
0919 Question # 68 Question: Is this saying the rad monitor failed to its High-High setpoint?
Response: You have enough information to answer the question.
0929 Question # 36 Question: Is the turbine tripped?
Response: You have enough information to answer the question.
1LOT23 NRC Examination Student Questions During Exam and Proctor Responses Beaver Valley 1LOT23 Page 2 of 2 Time Individual Question/Response 1010 Question # 23/63 Question: Can I get the FLOC for the East & West Cable Vaults (e.g. CV- )?
Response: You have enough information to answer the question.
1019 Question #_ 9 Question: Should answer B also say and after verifying AC emergency buses energized?
Response: You have enough information to answer the question.
1112 Question #
68 Question: Is the stem stating the Rad monitor failed high offscale or to the High setpoint?
Response: You have enough information to answer the question.
1213 Question #
96 Question: States a monthly surveillance has not been performed, is monthly implied to mean 28 days (4 weeks) or is a different interval implied?
Response: You have enough information to answer the question.
1218 Question #
68 Question: Is RM-1LW-104 failed at the HIGH alarm, or is the reading failed high?
Response: You have enough information to answer the question.
Question #
Question: Response:
1700 Exam completed
BVPS 1LOT23 EXAM PROVIDED REFERENCES AOP 1.10.1, Attachments 7 and 8 1BRTK4A, 4B Tank Curve Technical Specification 3.8.4 Technical Specification 3.8.6 1/2ADM1900, Attachment B, Sections 3.a.2 and 3.b.2 EPPI 1a.F01 (redacted)