KP-NRC-2312-003 December 21, 2023 Docket No. 50-611 Docket No. 50-612 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Kairos Power LLC Transmittal of Changes to Hermes 2 Construction Permit Application - PSAR Chapter 3 and Chapter 5

References:

1. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Preliminary Safety Analysis Report for the Hermes 2 Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes 2), Revision 0, July 14, 2023 (ML23195A122)
2. Audit Plan, Nuclear Regulatory Commission, Plan for a General Audit of the Hermes 2 Construction Permit Application, October 3, 2023 (ML23268A446)

In July 2023, Kairos Power submitted Revision 0 of the Preliminary Safety Analysis Report (PSAR)

(Reference 1) as part of the Construction Permit Application (CPA) for the Hermes 2 non-power reactor.

This letter transmits changes to the pages of the PSAR to address NRC feedback received on PSAR Chapters 3 and 5 in the General Audit (Reference 2). Changes to the pages of the PSAR are provided in . Kairos Power requests NRC review of these changes as part of the continued review of the Hermes CPA.

If you have any questions or need any additional information, please contact Austin Clark at clark@kairospower.com or (704) 247-6310 Ext. 1337, or Darrell Gardner at gardner@kairospower.com or (704) 769-1226.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on December 21, 2023 Sincerely, Peter Hastings, PE Vice President, Regulatory Affairs and Quality

Enclosure:

Changes to PSAR Chapter 3 and Chapter 5 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211

KP-NRC-2312-003 Page 2 xc (w/enclosure):

William Jessup, Chief, NRR Advanced Reactor Licensing Branch Michael Orenak, Project Manager, NRR Advanced Reactor Licensing Branch Matthew Hiser, Project Manager, NRR Advanced Reactor Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Samuel Cuadrado de Jesus, Project Manager, NRR Advanced Reactor Licensing Branch Cayetano Santos Jr., Project Manager, NRR Advanced Reactor Licensing Branch