ADP CR3, LLC Crystal River 3 Decommissioning Project

Crystal River Unit 3 Milestones

  • Construction Permit Issued September 1968
  • Operating License Issued December 1976
  • Commercial Operation began March 1977
  • Final Reactor Shutdown September 2009
  • Final Removal of Fuel from Reactor Vessel May 2011
  • Announcement of Permanent Cessation of Operation February 2013
  • Completion of Spent Fuel Transfer to Independent Spent Fuel Storage Installation January 2018
  • NRC approval of Partial Site Release of 3,854 non-impacted acres in January 2020
  • License Transfer from Duke Energy to ADP CR3 effective October 2020

Crystal River Unit 3 - Simple Priorities SAFETY with all we do - Target Zero (0 Accidents)

Do It Right, Do It Safe SAFETY:

  • Environmental Safety & Health
  • Project metric as of 3rd Quarter 2023: exemplary, Zero OSHA Lost Workday cases with over 1,020,007 person hours worked onsite since 2020
  • Radiological Control/Nuclear
  • As-Low-As-Reasonably-Achievable (ALARA) metric - in Compliance
  • 191 Rad waste shipments - no violations REGULATORY: (Federal, State, Local)
  • Good - Zero NRC Cited Violations for all of 2020, 2021, 2022, 2023 to date
  • Good - Zero Violations for General regulatory PRODUCTION:

Acceptable - The decommissioning project is proceeding on-time and within budget, currently 60% complete.

Crystal River Unit 3 - Simple Priorities SAFETY with all we do - Target Zero (0 Accidents)

Do It Right, Do It Safe DISPOSAL/SALVAGE:

Recycled Metals, as of 3rd Quarter 2023:

19,221,860 pounds 725 loads via rail or highway to recycling centers Radiological as of 3rd Quarter of 2023: 99% of Curie content removed or packaged for disposition Shipments removed offsite for disposal

15,140,430 pounds

578 Curies Reactor Vessel Packaged for future shipment

934, 761 pounds

20,094 Curies

Skyline Changes - Administration "Rusty" Building and Transformers

Skyline Changes - Machine Hot/Cold Shops

Skyline Changes - Maintenance Building

Skyline Changes - Emergency Feed Pump Building

Skyline Changes - South Berm Structures

Skyline Changes - Turbine Building Interior Systems Demolition

Skyline Changes - Turbine Building Panels Demolition

Skyline Changes - Turbine Building Superstructure Demolition

Skyline Changes - Turbine Building Superstructure Removed

Auxiliary Building - Interior Systems Removal

Auxiliary Building - Interior Systems Removal

Auxiliary Building-Interior Demolition

Auxiliary Building-Material Removal

Reactor Building-Systems Removal

Reactor Building-Systems Removal

Reactor Vessel Segmentation and Packaging Completed

Ultimate cradle to grave - WCS in Texas - disposal by truck, rail, and barge

Demolition Complete Skyline Crystal River Unit 3 Beginning Decommissioning Independent Spent Fuel Storage Installation Alone