Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval
Date released: 10/18/2023 Download: ML23283A021


Inservice Testing Program for Pumps and Valves - Part 12: IST Program Pump Basis Revision 1
ML23283A035
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A035
Inservice Testing Program for Pumps and Valves - Part 11: IST Program Valve Basis Revision 1
ML23283A034
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A034
Inservice Testing Program for Pumps and Valves - Part 10: IST Program Technical Positions Revision 2
ML23283A032
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A032
Inservice Testing Program for Pumps and Valves - Part 9: IST Program Refueling Outage Justifications Rev. 4
ML23283A031
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A031
Inservice Testing Program for Pumps and Valves - Part 8: IST Program Cold Shutdown Justifications Rev. 4
ML23283A030
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A030
Inservice Testing Program for Pumps and Valves - Part 7: IST Program Relief Request Revision 3
ML23283A029
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A029
Inservice Testing Program for Pumps and Valves - Part 6: IST Check Valve Condition Monitoring Plans Rev. 3
ML23283A028
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A028
Inservice Testing Program for Pumps and Valves - Part 5: IST Valve Scope Table Revision 4
ML23283A027
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A027
Inservice Testing Program for Pumps and Valves - Part 4: IST Valve Testing Program (Revision 3)
ML23283A026
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A026 (13)
Inservice Testing Program for Pumps and Valves - Part 3: IST Pump Scope Table (Revision 4)
ML23283A025
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A025
Fermi 2 - Inservice Testing Program for Pumps and Valves - Part 2: IST Pump Testing Program (Revision 3)
ML23283A024
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
NRC-23-0063
Download: ML23283A024 (6)
Inservice Testing Program Fourth Ten-Year Interval
ML23283A023
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From:
DTE Electric Company
To:
Office of Nuclear Reactor Regulation
References
NRC-23-0063
Download: ML23283A023
Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval
ML23283A022
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/09/2023
From: Frank E
DTE Electric Company
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
NRC-23-0063
Download: ML23283A022