Materials Inspection Report
U.S. NUCLEAR REGULATORY COMMISSION
Page 1 of 1
Add Continuation Page
1. Licensee/Location Inspected:
13624 South 220th Street, Suite #2
Gretna, NE 68028
Report Number(s) 2023-00
2. NRC/Regional Office
Region IV
U. S. Nuclear Regulatory Commission
1600 E. Lamar Boulevard
Arlington, TX 76011-4511
3. Docket Number(s)
030-39171
4. License Number(s)
15-35544-01
5. Date(s) of Inspection
5/4/2023
LICENSEE:
The inspection was an examination of the activities conducted under your license as they relate to radiation safety and to compliance with the
Nuclear Regulatory Commission (NRC) rules and regulations and the conditions of your license. The inspection consisted of selective
examinations of procedures and representative records, interviews with personnel, and observations by the inspector. The inspection findings
are as follows:
1. Based on the inspection findings, no violations were identified.
2. Previous violation(s) closed.
3. During this inspection, certain of your activities, as described below and/or attached, were in violation of NRC requirements, and
were assessed at Severity Level IV, in accordance with the NRC Enforcement Policy.
B. The following violation(s) is/are being cited in accordance with NRC Enforcement Policy. This form is a NOTICE OF VIOLATION,
which may be subject to posting in accordance with 10 CFR 19.11.
(Violations and Corrective Actions)
Statement of Corrective Actions
I hereby state that, within 30 days, the actions described by me to the Inspector will be taken to correct the violations identified. This statement of corrective
actions is made in accordance with the requirements of 10 CFR 2.201 (corrective steps already taken, corrective steps which will be taken, date when full
compliance will be achieved). I understand that no further written response to NRC will be required, unless specifically requested.
A. The violation(s), specifically described to you by the inspector as non-cited violations, are not being cited because they were self-
identified, non-repetitive, corrective action was or is being taken, and the remaining criteria in the NRC Enforcement Policy
were satisfied.
(Non-cited violation(s) was/were discussed involving the following requirement(s)
TITLE
NRC INSPECTOR
PRINTED NAME
SIGNATURE AND DATE
LICENSEE'S
REPRESENTATIVE
Stewart White - RSO
BRANCH CHIEF
Lizette Roldán-Otero, PhD
Leonardo F. Wardrobe
Digitally signed by Leonardo F. Wardrobe
Date: 2023.05.31 09:03:09 -05'00'
Digitally signed by Lizette Roldan-Otero
Date: 2023.08.02 12:37:38 -05'00'
ADAMS Accession no. ML23221A359
From:
Leo Wardrobe
To:
Stewart White
Subject:
NRC Inspection - Excel NDT, LLC
Date:
Wednesday, May 31, 2023 9:16:00 AM
Attachments:
IR-03039171.2023001.XCELNDTLLC.NRC 591M_signed.pdf
Mr. White,
The NRC conducted an inspection of Excel NDT, LLC on May 4, 2023. As we discussed on May 11,
2023, the inspection did not identify any violations. The enclosed report presents the results of this
inspection please review the attached report and maintain a copy for your records.
Please reply to the email acknowledging your receipt. Thank you,
Leo Wardrobe
Health Physicist
Nuclear Regulatory Commission, Region IV
Division of Nuclear Materials Safety,
Material Inspection Branch
1600 East Lamar Blvd.
Arlington, TX 76011
Office: (817) 200-1429
leonardo.wardrobe@nrc.gov