- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance
|
MONTHYEARND-22-0830, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816)2022-10-26026 October 2022 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816) Project stage: Request ND-22-0689, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53)2022-11-0303 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53) Project stage: Request ND-22-0862, ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561)2022-11-0808 November 2022 ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561) Project stage: Request ND-22-0730, ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319)2022-11-10010 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319) Project stage: Request ND-22-0657, ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480)2022-11-17017 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480) Project stage: Request ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)2022-11-18018 November 2022 ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751) Project stage: Request ND-22-0714, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171)2022-11-22022 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171) Project stage: Request ND-22-0711, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2022-11-23023 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ND-22-0821, ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819)2022-11-29029 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819) Project stage: Request ML22334A0752022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 Project stage: Request ND-22-0920, ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678)2022-12-0707 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678) Project stage: Request ND-22-0899, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214) Project stage: Request ND-22-0656, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348) Project stage: Request ND-22-0600, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291)2022-12-16016 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291) Project stage: Request ND-22-0747, ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33)2022-12-21021 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) Project stage: Request ND-22-0967, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802) Project stage: Request ND-22-0964, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800) Project stage: Request ND-22-0965, Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801) Project stage: Request ND-22-0895, ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90)2022-12-28028 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90) Project stage: Request ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company Project stage: Request ND-23-1001, ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684)2023-01-0505 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684) Project stage: Request ND-22-0848, ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317)2023-01-10010 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317) Project stage: Request ND-22-0869, ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462)2023-01-12012 January 2023 ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) Project stage: Request ND-23-0030, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-23-0026, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216) Project stage: Request ND-23-0029, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762) Project stage: Request ND-22-0649, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-22-0893, ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12)2023-01-16016 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12) Project stage: Request ND-22-0700, ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248) Project stage: Request ND-22-0521, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179) Project stage: Request ND-22-0585, ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154)2023-01-23023 January 2023 ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154) Project stage: Request ND-23-0041, ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219)2023-01-26026 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219) Project stage: Request ND-23-0078, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)2023-01-27027 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133) Project stage: Request ND-22-0739, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415) Project stage: Request ND-22-0876, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776) Project stage: Request ND-23-0079, ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285)2023-02-0202 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285) Project stage: Request ND-23-0039, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181) Project stage: Request ND-23-0043, ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32) Project stage: Request ND-22-0670, ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504)2023-02-0707 February 2023 ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504) Project stage: Request ND-22-0733, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350) Project stage: Request ND-23-0130, ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408) Project stage: Request ND-22-0737, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352) Project stage: Request ND-23-0124, ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879)2023-02-13013 February 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879) Project stage: Request ND-23-0153, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421) Project stage: Request ND-23-0141, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332) Project stage: Request ND-23-0071, ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259) Project stage: Request ND-23-0118, ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396) Project stage: Request ND-22-0919, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799)2023-02-24024 February 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799) Project stage: Request ND-23-0159, ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613)2023-03-0101 March 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613) Project stage: Request 2023-01-12
[Table View] |
Text
Jamie M. Coleman 7825 River Road Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6926 tel July 14, 2023 Docket No.:
52-026 ND-23-0602 10 CFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c [Index Number 270]
Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP)
Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.05.07c [Index Number 270]. This ITAAC confirms that the heat loads within the main control room (MCR), the I&C equipment rooms, and the Class 1E dc equipment rooms are within design basis assumptions to limit the heatup of the rooms. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.2.05.07c [Index Number 270]
JMC/CMK/sfr
U.S. Nuclear Regulatory Commission ND-23-0602 Page 2 of 2 cc:
Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)
Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4
U.S. Nuclear Regulatory Commission ND-23-0602 Enclosure Page 1 of 5 Southern Nuclear Operating Company ND-23-0602 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.2.05.07c [Index Number 270]
U.S. Nuclear Regulatory Commission ND-23-0602 Enclosure Page 2 of 5 ITAAC Statement Design Commitment 7.c) The heat loads within the MCR, the I&C equipment rooms, and the Class 1E dc equipment rooms are within design basis assumptions to limit the heatup of the rooms identified in Table 2.2.5-4.
Inspections/Tests/Analyses An analysis will be performed to determine that the heat loads from as-built equipment within the rooms identified in Table 2.2.5-4 are less than or equal to the design basis assumptions.
Acceptance Criteria A report exists and concludes that: the heat loads within rooms identified in Table 2.2.5-4 are less than or equal to the specified values or that an analysis report exists that concludes:
- The temperature and humidity in the MCR remain within limits for reliable human performance for the 72-hour period.
- The maximum temperature for the 72-hour period for the I&C rooms is less than or equal to 120°F.
- The maximum temperature for the 72-hour period for the Class 1E dc equipment rooms is less than or equal to 120°F.
ITAAC Determination Basis An analysis was performed based on measured test data to confirm that the heat loads from as-built equipment within the Main Control Room (MCR), Instrument and Controls (l&C) equipment rooms, and the class 1E direct current (dc) equipment rooms are less than or equal to the design basis assumptions identified in Combined License (COL) Appendix C, Table 2.2.5-4 (Attachment A) or that an analysis report exists that concludes:
- The temperature and humidity in the MCR remain within limits for reliable human performance for the 72-hour period.
- The maximum temperature for the 72-hour period for the I&C rooms is less than or equal to 120°F.
- The maximum temperature for the 72-hour period for the Class 1E dc equipment rooms is less than or equal to 120°F.
MCR heat load testing for data collection was performed by installing 17 temperature dataloggers. MCR temperature and relative humidity were recorded for a minimum of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and access to the MCR was restricted during the test. The Nuclear Island Nonradioactive Ventilation System (VBS) system was balanced and operating normally prior to commencing the test. To test the MCR heat loads, the MCR boundary was manually isolated by actuating the MCR Emergency Habitability System (VES), causing the VBS system to secure. Designated heat loads were shed per design during the test, and temporary heat sources (as necessary) were used to simulate the heat load of 11 MCR occupants for the duration of the test. Data
U.S. Nuclear Regulatory Commission ND-23-0602 Enclosure Page 3 of 5 collection results, along with Attachment A, were used as input to perform an analysis and create an analysis report (Reference 1) that concludes that the temperature and humidity in the MCR remain within limits for reliable human performance for the 72-hour period.
The l&C equipment rooms and Class 1E dc equipment rooms heat load testing for data collection was performed by equipping each room with temperature dataloggers, access to the room was restricted, ventilation supply and exhaust dampers were closed, all equipment in the rooms was energized and temperature data was recorded for a minimum of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Data collection results, along with Attachment A, were used as input to perform an analysis and create an analysis report (Reference 1) that concludes the maximum temperature for the 72-hour period for the l&C equipment rooms and Class 1E dc equipment rooms was less than or equal to 120°F.
Heat load analysis based on test data took into account the rooms' configuration and heat transfer characteristics (design basis assumptions) to conclude that:
- The temperature and humidity in the MCR remain within limits for reliable human performance for the 72-hour period.
- The maximum temperature for the 72-hour period for the I&C rooms is less than or equal to 120°F.
- The maximum temperature for the 72-hour period for the Class 1E dc equipment rooms is less than or equal to 120°F.
The resultant analysis is documented in Reference 1 confirming that an analysis report exists and concludes that:
- The temperature and humidity in the MCR remain within limits for reliable human performance for the 72-hour period.
- The maximum temperature for the 72-hour period for the I&C rooms is less than or equal to 120°F.
- The maximum temperature for the 72-hour period for the Class 1E dc equipment rooms is less than or equal to 120°F.
Reference 1 is available for NRC inspection as part of the Unit 4 ITAAC 2.2.05.07c Completion Package (Reference 2).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there were no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.2.05.07c (Reference 2) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.2.05.07c was performed for VEGP Unit 4 and that the prescribed acceptance criteria were met.
U.S. Nuclear Regulatory Commission ND-23-0602 Enclosure Page 4 of 5 Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV4-VES-T2R-001, Vogtle Unit 4 Six Hour Main Control Room Heatup Summary Report, Rev. 0
- 2. 2.2.05.07c-U4-CP-Rev0, ITAAC Completion Package
U.S. Nuclear Regulatory Commission ND-23-0602 Enclosure Page 5 of 5 Attachment A
- Excerpt from COL Appendix C Table 2.2.5-4
- Heat Load 0 to 24 Hours (Btu/s)
- Heat Load 24 to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (Btu/s)
MCR Envelope 12401 23.5 (hour 0 to 0.5) 14.5 (hour 0.5 to 3.5) 4.75 (hour 3.5 through 24) 3.95 I&C Rooms 12301 3.50 1.10 12302 3.20 2.50 12304 4.30 3.20 12305 4.20 1.50 dc Equipment Rooms 12201 2.00 2.00 12203 3.30 3.30 12205 2.40 2.40 12207 3.45 3.45