LICENSEE:
DTE Electric Company FACILITY:
Fermi Nuclear Power Plant, Unit 2
SUBJECT:
SUMMARY
OF THE JUNE 21, 2023, PUBLIC OUTREACH TO DISCUSS THE NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF FERMI NUCLEAR POWER PLANT, UNIT 2 On June 21, 2023, from 5:30 p.m. to 6:30 p.m. (EDT), an information meeting was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2022 end-of-cycle plant performance assessment of the Fermi Nuclear Power Plant, Unit 2, and with general information on the NRC. The meeting was held at the Monroe County Board of Commissioners Chambers, Monroe County Courthouse in Monroe, Michigan. The NRC representatives were available to discuss plant performance with members of the public. Representatives from DTE were also present at the event.
The NRC discussed their assessment of Fermi Nuclear Power Plant, Unit 2 performance during the public outreach. The assessment information was documented in the March 1, 2023, end-of-cycle assessment letter (ADAMS Accession Number ML23055B132). Members of the public were given the opportunity to ask questions of NRC staff and DTE representatives.
Karla Stoedter, Branch Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket Nos. 50-341 License No. NPF-43 cc: Distribution via LISTSERV July 6, 2023 Signed by Stoedter, Karla on 07/06/23
SUBJECT:
SUMMARY
OF THE JUNE 21, 2023, PUBLIC OUTREACH TO DISCUSS THE NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF FERMI NUCLEAR POWER PLANT, UNIT 2 DISTRIBUTION:
Jeffrey Josey RidsNrrDorlLpl3 RidsNrrPMFermi2 Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML23187A456 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII NAME JMasse:gmp KStoedter DATE 07/06/2023 07/06/2023 OFFICIAL RECORD COPY
Enclosure PUBLIC MEETING ATTENDEES June 21, 2023 U.S. Nuclear Regulatory Commission K. Stoedter, Chief, Reactor Projects Branch 2 T. Taylor, Senior Resident Inspector, Fermi J. Gewargis, Resident Inspector, Fermi H. Logaras, Government Liaison Officer A. Barker, Government Liaison Officer P. Chandrathil, Public Affairs Officer D. Bogedain, Resident Inspector Office Assistant DTE S. Gatter E. Frank M. Murphy E. Olson S. Banker S. Tait Members of the Public L. Taylor R. Taylor