ITAAC Closure Notification on Completion of ITAAC C.2.6.09.02 (Index Number 659)
ML23146A179
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 05/26/2023
From: Coleman J
Southern Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
ND-23-0123
Download: ML23146A179 (1)


Text

Jamie M. Coleman 7825 River Road Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6926 tel

May 26, 2023

Docket No: 52-026 ND-23-0123 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001

Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.02 [Index Number 659]

Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item C.2.6.09.02 [Index Number 659]. This ITAAC confirms that the physical barriers at the perimeter of the protected area are separated from any other barrier designated as a vital area barrier. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted,

Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC C.2.6.09.02 [Index Number 659]

JMC/SRV/sfr

U.S. Nuclear Regulatory Commission ND-23-0123 Page 2 of 2

cc: Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)

Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4

U.S. Nuclear Regulatory Commission ND-23-0123 Enclosure Page 1 of 3

Southern Nuclear Operating Company ND-23-0123 Enclosure

Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC C.2.6.09.02 [Index Number 659]

U.S. Nuclear Regulatory Commission ND-23-0123 Enclosure Page 2 of 3

ITAAC Statement Design Commitment

2. Physical barriers for the protected area perimeter are not part of vital area barriers.

Inspections/Tests/Analyses An inspection of the protected area perimeter barrier will be performed.

Acceptance Criteria Physical barriers at the perimeter of the protected area are separated from any other barrier designated as a vital area barrier.

ITAAC Determination Basis An inspection of the VEGP Unit 4 protected area perimeter barrier was performed to verify that physical barriers at the perimeter of the Unit 4 protected area are separated from any other Unit 4 barrier designated as a vital area barrier and satisfy the applicable protected area perimeter physical barrier physical separation requirements of the VEGP Units 1-4 Physical Security Plan associated with 10 CFR 73.55(e)(8)(i)(C). The VEGP Unit 4 Plant Security System ITAACs only cover the Unit 4 plant security system design commitment scope.

The inspection was performed per Principal Closure Document SV4-SES-ITR-800659 (Reference 1) and involved a review of approved construction drawings and performance of a walkdown to verify that the Unit 4 protected area perimeter physical barriers are physically separated from Unit 4 vital area barriers.

The results of the inspection are documented in Reference 1 and verify that the Unit 4 physical barriers at the perimeter of the protected area are separated from any other Unit 4 barrier designated as a vital area barrier.

Reference 1 is available for NRC inspection as part of the Unit 4 ITAAC C.2.6.09.02 Completion Package (Reference 2).

ITAAC Finding Review

In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC C.2.6.09.02 (Reference 2) and is available for NRC review.

ITAAC Completion Statement

Based on the above information, SNC hereby notifies the NRC that ITAAC C.2.6.09.02 was performed for VEGP Unit 4 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

U.S. Nuclear Regulatory Commission ND-23-0123 Enclosure Page 3 of 3

References (available for NRC inspection)

1. SV4-SES-ITR-800659, Rev. 0, Unit 4 ITAAC 659 Walkdown Inspection: ITAAC C.2.6.09.02
2. C.2.6.09.02-U4-CP-Rev 0, ITAAC Completion Package