- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance
|
MONTHYEARND-22-0830, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816)2022-10-26026 October 2022 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816) Project stage: Request ND-22-0689, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53)2022-11-0303 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53) Project stage: Request ND-22-0862, ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561)2022-11-0808 November 2022 ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561) Project stage: Request ND-22-0730, ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319)2022-11-10010 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319) Project stage: Request ND-22-0657, ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480)2022-11-17017 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480) Project stage: Request ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)2022-11-18018 November 2022 ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751) Project stage: Request ND-22-0714, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171)2022-11-22022 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171) Project stage: Request ND-22-0711, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2022-11-23023 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ND-22-0821, ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819)2022-11-29029 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819) Project stage: Request ML22334A0752022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 Project stage: Request ND-22-0920, ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678)2022-12-0707 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678) Project stage: Request ND-22-0899, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214) Project stage: Request ND-22-0656, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348) Project stage: Request ND-22-0600, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291)2022-12-16016 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291) Project stage: Request ND-22-0747, ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33)2022-12-21021 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) Project stage: Request ND-22-0967, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802) Project stage: Request ND-22-0964, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800) Project stage: Request ND-22-0965, Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801) Project stage: Request ND-22-0895, ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90)2022-12-28028 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90) Project stage: Request ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company Project stage: Request ND-23-1001, ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684)2023-01-0505 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684) Project stage: Request ND-22-0848, ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317)2023-01-10010 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317) Project stage: Request ND-22-0869, ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462)2023-01-12012 January 2023 ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) Project stage: Request ND-23-0030, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-23-0026, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216) Project stage: Request ND-23-0029, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762) Project stage: Request ND-22-0649, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-22-0893, ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12)2023-01-16016 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12) Project stage: Request ND-22-0700, ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248) Project stage: Request ND-22-0521, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179) Project stage: Request ND-22-0585, ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154)2023-01-23023 January 2023 ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154) Project stage: Request ND-23-0041, ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219)2023-01-26026 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219) Project stage: Request ND-23-0078, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)2023-01-27027 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133) Project stage: Request ND-22-0739, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415) Project stage: Request ND-22-0876, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776) Project stage: Request ND-23-0079, ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285)2023-02-0202 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285) Project stage: Request ND-23-0039, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181) Project stage: Request ND-23-0043, ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32) Project stage: Request ND-22-0670, ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504)2023-02-0707 February 2023 ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504) Project stage: Request ND-22-0733, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350) Project stage: Request ND-23-0130, ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408) Project stage: Request ND-22-0737, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352) Project stage: Request ND-23-0124, ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879)2023-02-13013 February 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879) Project stage: Request ND-23-0153, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421) Project stage: Request ND-23-0141, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332) Project stage: Request ND-23-0071, ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259) Project stage: Request ND-23-0118, ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396) Project stage: Request ND-22-0919, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799)2023-02-24024 February 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799) Project stage: Request ND-23-0159, ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613)2023-03-0101 March 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613) Project stage: Request 2023-01-12
[Table View] |
Text
Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel May 18, 2023 Docket No.:
52-026 ND-23-0404 10 CFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of ITAAC 2.1.03.13 [Index Number 88]
Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP)
Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.1.03.13 [Index Number 88]. This ITAAC verified that the fuel assemblies and rod cluster control assemblies intended for the initial core load and listed in the COL Appendix C Table 2.1.3-1 have been designed and constructed in accordance with the principal design requirements. The closure process for this ITAAC is based on the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52 (Reference 1), which is endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 4 ITAAC Closure Notification on Completion of 2.1.03.13 [Index Number 88]
JMC/MKO/sfr
U.S. Nuclear Regulatory Commission ND-23-0404 Page 2 of 2 cc:
Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)
Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4
U.S. Nuclear Regulatory Commission ND-23-0404 Enclosure Page 1 of 5 Southern Nuclear Operating Company ND-23-0404 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 ITAAC Closure Notification on Completion of ITAAC 2.1.03.13 [Index Number 88]
U.S. Nuclear Regulatory Commission ND-23-0404 Enclosure Page 2 of 5 ITAAC Statement Design Commitment:
- 13. The fuel assemblies and rod cluster control assemblies intended for initial core load and listed in Table 2.1.3-1 have been designed and constructed in accordance with the established design requirements.
Inspections, Tests, Analyses:
An analysis is performed of the reactor core design.
Acceptance Criteria:
A report exists and concludes that the fuel assemblies and rod cluster control assemblies intended for the initial core load and listed in Table 2.1.3-1 have been designed and constructed in accordance with the principal design requirements.
ITAAC Determination Basis Analyses of the reactor core design were performed to demonstrate that the fuel assemblies (FAs) and the rod cluster control assemblies (RCCAs) intended for the initial core load and listed in Combined License Appendix C (Reference 2) Table 2.1.3-1 (Attachment 1) were designed and constructed in accordance with the principal design requirements. The fuel and rod cluster control assembly's principal design requirements are identified in the Updated Final Safety Analysis Report (UFSAR, Reference 3) Section 4.1.1.
References 4 and 5 document the design closeout activities performed by Westinghouse to finalize the AP1000 fuel assembly design and the Rod Cluster Control Assembly (RCCA) design. These design closeout documents ensure that the Principal Design Requirements listed in the Updated Final Safety Analysis Report Chapter 4.1.1 are met. Following the completion of the design closeouts of References 4 and 5, additional changes were made to the AP1000 fuel assembly and RCCA designs. These changes were provided in Reference 6, the AP1000 Core Reference Report. References 7 and 8 were added as references in Section 4.1.1 of the UFSAR Revision 8.1. Together, these five documents, along with the associated UFSAR requirements, define the licensing basis for the Vogtle 3 & 4 fuel assembly and RCCA designs. References 4 through 8 were reviewed and it was confirmed that the NRC-approved fuel assembly and RCCA designs meet the UFSAR Chapter 4.1.1 Principal Design Requirements. Furthermore, references 4 through 8 document design compliance with the applicable UFSAR Chapter 4 requirements (including fuel damage and material compatibility principal design requirements).
Reference 9 documents the Initial Core Safety Analysis Checklist and is specific to the Vogtle 3 &
4 First Core design as documented in Reference 6. Reference 9 confirms that the initial core load safety analysis performed by Westinghouse for Cycle 1 meets the Principal Design Requirements listed in the UFSAR Chapter 4.1.1, and the applicable UFSAR Chapter 4 requirements.
Verification of the design and construction of fuel and RCCAs is documented in ITAAC Technical Report SV4-RXS-ITR-800088 (Reference 10). Construction of the fuel and RCCAs was performed in accordance with the Westinghouse Columbia Fuel Fabrication Facility Quality Management System (Reference 11). Construction of fuel assemblies was in accordance with NRFE-10-59, DR
U.S. Nuclear Regulatory Commission ND-23-0404 Enclosure Page 3 of 5 08-3, AP1000 Fuel Design Finalization Review Meeting (Reference 4). Construction of RCCAs was in accordance with NRFE-11-29, NRFE-11 NG RCCA DESIGN CLOSEOUT PACKAGE Revision 2 (Reference 5). A letter was provided by Westinghouse (Reference 12) at the completion of the fabrication process attesting that the fuel assemblies and RCCAs for the Vogtle Unit 4 initial core load were constructed in accordance with the principal design requirements.
The reviews and technical reports described above demonstrate that the fuel assemblies and rod cluster control assemblies intended for the initial core load and listed in the COL Appendix C Table 2.1.3-1 have been designed and constructed in accordance with the principal design requirements.
References 4 through 10 are available for NRC inspection as part of the Unit 4 ITAAC 2.1.03.13 Completion Package (Reference 13).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.1.03.13 (Reference 13) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.1.03.13 was performed for VEGP Unit 4 and that the prescribed acceptance criteria are met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. NEI 08-01 Rev. 5 corrected 6-30-2014, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52
- 2. Unit 4 VEGP Combined License Appendix C, Amendment 191
- 3. VEGP UFSAR, Revision 11.2
- 4. NRFE-10-59 Rev. 0, DESIGN CLOSEOUT Package, DR 08-3, AP1000 Fuel Design Finalization Review Meeting, as archived in Westinghouse PRIME document repository
- 5. NRFE-11-29 Rev. 2, NRFE-11 NG RCCA DESIGN CLOSEOUT PACKAGE Revision 2, as archived in Westinghouse PRIME document repository
- 6. APP-GW-GLR-153/WCAP-17524-P Rev. 1, AP1000 Core Reference Report, as archived in Westinghouse PRIME document repository
- 7. APP-GW-GLR-059/WCAP-16652-NP Rev. 0, AP1000 Core & Fuel Design Technical Report, as archived in Westinghouse PRIME document repository
- 8. WCAP-16943-NP Rev. 0, Enhanced GRCA Rodlet Design, as archived in Westinghouse PRIME document repository
- 9. APP-SSAR-F5-001, Rev. 1, AP1000 Safety Analysis Checklist, as archived in Westinghouse PRIME document repository
U.S. Nuclear Regulatory Commission ND-23-0404 Enclosure Page 4 of 5
- 10. SV4-RXS-ITR-800088, Rev. 0, ITAAC Technical Report, Unit 4 Verification of Fuel and RCCA Construction: ITAAC 2.1.03.13, NRC Index Number: 88
- 11. Westinghouse Columbia Fuel Fabrication Facility Quality Management System, Rev. 8
- 12. NF-GP-23-038, from Westinghouse to SNC, SOUTHERN NUCLEAR OPERATING COMPANY VOGTLE ELECTRIC GENERATING PLANT UNIT 4, Notification of Fabrication of Fuel and RCCAs, 5/17/2023
- 13. 2.1.03.13-U4-CP-Rev0, ITAAC Completion Package
U.S. Nuclear Regulatory Commission ND-23-0404 Enclosure Page 5 of 5
- Excerpt Combined License Appendix C Table 2.1.3-1
- ASME Code Section III Classification
- Seismic Cat. I Fuel Assemblies (157 locations)
RXS-FA-A07/A08/A09/B05/B06/B07/B08/
B09/B10/B11/C04/C05/C06/C07/C08/C09/C10/
C11/C12/D03/D04/D05/D06/D07/D08/D09/
D10/D11/D12/D13/E02/E03/E04/E05/E06/E07/
E08/E09/E10/E11/E12/E13/E14/F02/F03/F04/
F05/F06/F07/F08/F09/F10/F11/F12/F13/F14/
G01/G02/G03/G04/G05/G06/G07/G08/G09/
G10/G11/G12/G13/G14/G15/H01/H02/H03/
H04/H05/H06/H07/H08/H09/H10/H11/H12/
H13/H14/H15/J01/J02/J03/J04/J05/J06/J07/J08/
J09/J10/J11/J12/J13/J14/J15/K02/K03/K04/
K05/K06/K07/K08/K09/K10/K11/K12/K13/
K14/L02/L03/L04/L05/L06/L07/L08/L09/L10/
L11/L12/L13/L14/M03/M04/M05/M06/M07/
M08/M09/M10/M11/M12/M13/N04/N05/N06/
N07/N08/N09/N10/N11/N12/P05/P06/P07/P08/
P09/P10/P11/ R07/R08/R09 No(1)
Yes Rod Cluster Control Assemblies (RCCAs)
(minimum 53 locations)
RXS-FR-B06/B10/C05/C07/C09/C11/D06/
D08/D10/E03/E05/E07/E09/E11/E13/F02/F04/
F12/F14/G03/G05/G07/G09/G11/G13/H04/
H08/H12/J03/J05/J07/J09/J11/J13/K02/K04/
K12/K14/L03/L05/L07/L09/L11/L13/M06/
M08/M10/N05/N07/N09/N11/P06/P10 No(1)
Yes (1) Fuel assemblies are designed using ASME Section III as a general guide