From:

Vic Cusumano Sent:

Friday, February 3, 2023 3:32 PM To:

Michael Dudek Cc:

Craig Harbuck; Getachew Tesfaye

Subject:

FW: NuScale SDAA Acceptance Review Input to DNRL Attachments:

Table 2 - SDAA Acceptance Review Issues STSB.xlsx; Table 1 - SDAA Safety Review Schedule Input - STSB.xlsx

Mike, The technical specification branch has not identified any acceptance issues Regarding schedule, please note that due to dependencies on Chapters 6, 7, and 15 we recommend aligning our section with their 24-month review schedule.

Vic From: Craig Harbuck <Craig.Harbuck@nrc.gov>

Sent: Friday, February 3, 2023 11:58 AM To: Vic Cusumano <Victor.Cusumano@nrc.gov>

Subject:

FW: NuScale SDAA Acceptance Review Input to DNRL

Vic, Recommend you emailing Dudek and cc Getachew the attached links to the Tables 1 and 2. In Table 1, I suggest requesting 8 month increase to current 16 month schedule to match schedule for Chapters 6 and 15, which have 24 months. In Table 2, I indicate that no acceptance review issues were identified.

Craig From: Getachew Tesfaye <Getachew.Tesfaye@nrc.gov>

Sent: Saturday, January 21, 2023 8:47 AM To: NRCReviewer_NS_SDAA <NRCReviewer_NS_SDAA@nrc.gov>; NRCBC_NS_SDAA

<NRCBC_NS_SDAA@nrc.gov>

Cc: Michael Dudek <Michael.Dudek@nrc.gov>; NRCPMs_NS_SDAA <NRCPMs_NS_SDAA@nrc.gov>;

Brian Smith - NRR <Brian.Smith@nrc.gov>; Bernie Thomson <Bernie.Thomson@nrc.gov>

Subject:

NuScale SDAA Acceptance Review Input to DNRL Good Morning (reviewers/Branch Chiefs),

Friendly Reminder to Reviewers:

We are about halfway to the February 10th milestone for acceptance review input. If you have any issues at all, please do not hesitate to raise them as they become apparent.

Additionally, please document any acceptance review issues in the following link:

Acceptance Review Issues Acceptance Review Input to DNRL (Branch Chiefs)

1. Complete Table 1 (attached) and if applicable Table 2 (attached),
2. Submit your acceptance review input in an email or memo by attaching Table 1 and if applicable Table 2 to NRLB Branch Chief Michael Dudek by February 10,
2023,
3. Please make sure to copy the chapter PM and the lead PM when you submit your input.

As always, please reach out if you have any questions.

Thank you, Getachew Tesfaye Senior Project Manager NRC/NRR/DNRL/NRLB 301-415-8013

Hearing Identifier:

NuScale_SDA720_Doc_Public Email Number:

6 Mail Envelope Properties (MW4PR09MB9395D4C4662EFFC6C1F70E37F3D79)

Subject:

FW NuScale SDAA Acceptance Review Input to DNRL Sent Date:

2/3/2023 3:32:25 PM Received Date:

2/3/2023 3:32:26 PM From:

Vic Cusumano Created By:

Victor.Cusumano@nrc.gov Recipients:

"Craig Harbuck" <Craig.Harbuck@nrc.gov>

Tracking Status: None "Getachew Tesfaye" <Getachew.Tesfaye@nrc.gov>

Tracking Status: None "Michael Dudek" <Michael.Dudek@nrc.gov>

Tracking Status: None Post Office:

MW4PR09MB9395.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3429 2/3/2023 3:32:26 PM image00001.png 844 image00002.png 844 image00001.png 844 image00002.png 844 Options Priority:

Normal Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date: