MONTHYEARML23004A1962023-01-0404 January 2023 Global Nuclear Fuel Americas (GNF-A) Request for Exemption from Supplemental Environmental Report Timing Requirement of 10 CFR 51.60(a) Project stage: Supplement ML23039A1522023-03-0303 March 2023 Enclosure - SER for Approval of GNF-A Exemption Request to Support Submittal of the Er in Advance of the LAR Project stage: Approval ML23039A1502023-03-0303 March 2023 Approval of GNF-A 10 CFR 51.60 a Exemption Request Project stage: Request ML23039A1512023-03-0303 March 2023 Cover Letter - Approval of GNF-A Er Exemption Request Project stage: Other 2023-01-04
[Table View] |
|
---|
Category:Letter
MONTHYEARML24017A1602024-01-31031 January 2024 Global Nuclear Fuel - Americas - Core Inspection Report 07001113-2023004 ML24030A5182024-01-30030 January 2024 Global Nuclear Fuel - Americas, LLC (GNF-A), Submittal of Revised ISA Summary Per 10CFR70.72(d) ML24008A2892024-01-10010 January 2024 Global Nuclear Fuel-Americas - NRC Inspection Report 07001113/2023006 ML24003A6832024-01-0404 January 2024 Global Nuclear Fuel - Americas, L.L.C. Material Control and Accounting Program Inspection Report 07001113-2023401 - Public ML23311A3802023-12-11011 December 2023 Cover Letter - Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed ML23276B3952023-10-13013 October 2023 the U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML24005A2842023-09-18018 September 2023 23-004 M230129 GNF-A 2023 Biennial Exercise Supplement NRC Cover Letter 9-18-2023 ML23255A2902023-09-13013 September 2023 Global Nuclear Fuel Americas, L.L.C. Inspection Schedule for Calendar Year 2024 ML23230A3942023-08-18018 August 2023 GNF-A Semi-Annual Effluent Monitoring Report ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23213A1452023-08-0202 August 2023 Global Nuclear Fuel Americas, LLC Core Inspection Report 07001113/2023002 ML23209A6762023-07-28028 July 2023 GNF-A Response to NRC Request for Additional Information ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML24005A2782023-07-27027 July 2023 23-030 M230100 GNF-A 2023 Biennial Exercise NRC Cover Letter 7-27-23 ML23195A0942023-07-14014 July 2023 GNF-A Written Follow-up Report Fire System Impairment ML23192A5162023-07-11011 July 2023 GNF-A Natrium Fuel Fabrication Facility Schedule Update ML23156A1832023-07-0303 July 2023 Request for Additional Information Regarding GNF-A License Amendment Request for 8 Weight Percent Uranium 235 ML23178A0992023-06-27027 June 2023 GNF-A Additional Response to Nrg Request for Supplemental Information - Decommissioning Funding Plan (DFP) ML23177A0892023-06-26026 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 2 ML23171A9762023-06-20020 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 1 ML23159A1342023-06-0808 June 2023 Global Nuclear Fuel - Americas, LLC, Physical Inventory Summary Reports ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals ML23116A3212023-04-27027 April 2023 Public Meeting Summary Licensee Performance Review of Global Nuclear Fuel Americas, LLC, Docket Number 07001113 ML23116A1842023-04-26026 April 2023 GNF-A Response to NRC Request for Supplemental Information - Decommissioning Funding Plan (DFP) ML23089A2392023-04-10010 April 2023 Global Nuclear Fuel Americas, LLC, Triennial - 2022 Update to Decommissioning Funding Plan - Supplemental Information Needed - Enterprise Project Identification Number L-2022-DDP-0002 ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML23065A0722023-03-0606 March 2023 Global Nuclear Fuel Americas (GNF-A), Supplemental Environmental Report Information and Request to Begin Construction ML23060A0862023-03-0303 March 2023 Global Nuclear Fuel - Americas, LLC Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 07001113/2023005) ML23039A1512023-03-0303 March 2023 Cover Letter - Approval of GNF-A Er Exemption Request ML23058A2232023-02-27027 February 2023 GNF-A Semi-Annual Effluent Monitoring Report ML23044A4522023-02-13013 February 2023 Global Nuclear Fuel - Americas, L.L.C. (GNF-A), Submittal of Revision to GNF-A Radiological Contingency & Emergency Plan (Rc&Ep) ML23033A5422023-02-0202 February 2023 Global Nuclear Fuel - Americas, LLC - Submittal of FOCI Information Update ML23030A8022023-01-30030 January 2023 Submittal of GNF-A Natrium Fuel Fabrication Facility Pre-Application - Meeting Slides ML23027A0522023-01-27027 January 2023 Global Nuclear Fuel- Americas, LLC, Revised ISA Summary Per 10CFR70.72(d) ML23032A3722023-01-17017 January 2023 Concurrence from Nc Shpo - January 17 2023 ER-08-0036 ML23017A0102023-01-17017 January 2023 Global Nuclear Fuel-Americas, LLC - Core Inspection Report 07001113/2022004 ML23004A1962023-01-0404 January 2023 Global Nuclear Fuel Americas (GNF-A) Request for Exemption from Supplemental Environmental Report Timing Requirement of 10 CFR 51.60(a) ML22355A1622022-12-20020 December 2022 GNF-A Submittal of FOCI Information Update ML22346A0702022-12-12012 December 2022 GNF-A Written Follow-up Report - Fire System Impairment ML22346A2482022-12-12012 December 2022 Notice of Global Nuclear Fuel Americas, LLC (GNF-A) Facility Manager Change 2024-01-04
[Table view] |
Text
March 3, 2023 Mr. Scott P. Murray, Licensing Manager Global Nuclear Fuel-Americas 3901 Castle Hayne Road P.O. Box 780 Wilmington, NC 28402
SUBJECT:
APPROVAL OF GLOBAL NUCLEAR FUEL - AMERICAS EXEMPTION REQUEST TO SUPPORT SUBMITTAL OF THE SUPPLEMENTAL ENVIRONMENTAL REPORT IN ADVANCE OF THE SAFETY AND SAFEGUARDS PORTION OF THE LICENSE AMENDMENT REQUEST (ENTERPRISE PROJECT IDENTIFIER (ENTERPRISE PROJECT IDENTIFIER L-2023-LLE-0002)
Dear Scott Murray:
Global Nuclear Fuel-Americas, LLC (GNF-A) submitted a letter dated January 4, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23004A196), requesting an exemption from requirements in Title 10 of the Code of Federal Regulations (10 CFR), Sections 51.60(a), "Environmental reportmaterials licenses." The exemption request supports GNF-As plans to submit a license amendment request in 2023 to possess and use special nuclear material for processing and fuel fabrication at a proposed facility at its Wilmington, North Carolina location. The exemption request seeks authorization to submit the license amendment application in two parts: the supplemental environmental report (ER) followed by the safety and safeguards portion of the license amendment request (LAR).
Under the regulations at 10 CFR 51.61(a), an applicant must submit the ER and LAR together as a complete package.
A safety evaluation report of the U.S. Nuclear Regulatory Commission (NRC) staffs review of the exemption request is enclosed. The staff finds that granting the exemption is authorized by law, will not endanger life or property or common defense and security, and is otherwise in the public interest. Therefore, the staff grants GNF-A a temporary exemption from the requirements of 10 CFR 51.60(a), until one year after official receipt of the supplemental ER in the ADAMS database. Neither granting the exemption request nor beginning a review of the supplemental ER prior to receipt of the LAR indicates a commitment by the NRC to accept the license application for docketing.
In its Request for Exemption, GNF-A states, [t]he exemption and subsequent NRC review would allow GNF-A to initiate construction activities of the 10 CFR Part 70 components of the NFFF even if the 10 CFR 51.60 timing requirement is not met. As an initial matter, the staff notes that 10 CFR 51.60(a) does not include a specific timing requirement. Furthermore, the granting of the exemption from 10 CFR 51.60(a) does not exclude GNF-A from compliance with all applicable NRC requirements. For example, 10 CFR 70.23(a)(7) states, in relevant part, that commencement of construction prior to the NRC making a determination on issuance of the
S. Murray 2 amendment is grounds for denial to possess and use special nuclear material in the plant or facility. Commencement of construction as defined in section 70.4 may include non-construction activities if the activity has a reasonable nexus to radiological safety and security.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter and enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) and in ADAMS. The ADAMS database is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. The PDR is currently closed. You may submit your request to the PDR via e-mail at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays.
If you have any questions regarding this communication, please contact Jonathan Rowley at 301-415-4053 or via email at Jonathan.Rowley@nrc.gov.
Sincerely, Downs, James signing on behalf of Soto Lugo, Soly on 03/03/23 Soly Soto Lugo, Acting Chief Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-1113
Enclosure:
Safety Evaluation Report cc: gnfa@listmgr.nrc.gov
ML23039A150; Ltr ML23039A151 NMSS/MSST OGC/GCRPS OFFICE NMSS/DFM/FFLB NSIR/DPR
/MSEB /HLWFCNS/NLO NAME JRowley JR JGoodridge JG RSun RS PJehle PJ DATE Feb 8, 2023 Feb 9, 2023 Feb 24, 2023 Mar 3, 2023 OFFICE NMSS/REFS SSoto NAME JDowns for JD DATE Mar 3, 2023