1 to Updated Final Safety Analysis Report, Chapter 14.3, Figures 14.3.4-1 to 14.3.4-158 (Unit 2)
ML22340A169
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 11/30/2022
From:
Indiana Michigan Power Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML22340A137 List: ... further results
References
AEP-NRC-2022-62
Download: ML22340A169 (1)


Text

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised:

27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-1 Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

Steam Concentration in a Vertical Distribution Channel UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised:

27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-2 Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

D. C. Cook Unit 2 BELOCA Analysis Axial Power Shape Operating Space Envelope UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised:

27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-3 Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

Upper Compartment Compression Pressure versus Energy Release for Tests at 110% and 200% of Initial DBA Blowdown Rate UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-4 Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

Ice Melted vs. Energy Release for Tests at Different Blowdown Rates UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-5 Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

Upper Compartment Peak C ompression Pressure versus Blowdown Rate for Tests with 185 % Energy Release UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-6 Change

Description:

UCR-2147, Rev. 0 Unit: 2

Title:

LOCA Containment Integrity Containment Pressure UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 Note 1: This peak pressure is increased by 0.27 psi as described in Section 14.3.4.1.3.1.3.

The peak composite pressure is 11.43 psig.

UFSAR Figure: 14.3.4-6A Change

Description:

UCR-2147, Rev. 0 Unit: 2

Title:

LOCA Containment Integrity (Composite) Containment Pressure UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-7 Change

Description:

UCR-2147, Rev. 0 Unit: 2

Title:

LOCA Containment Integrity Upper Compartment Temperature UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 Note 1: Peak Temperature = 232.2°F.

UFSAR Figure: 14.3.4-8 Change

Description:

UCR-2147, Rev. 0 Unit: 2

Title:

LOCA Containment Integrity Lower Compartment Temperature UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-9 Change

Description:

UCR-2147, Rev. 0 Unit: 2

Title:

LOCA Containment Integrity Containment Sump Temperature Transient UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-10 Change

Description:

UCR-2147, Rev. 0 Unit: 2

Title:

LOCA Containment Integrity Ice Melt Transient UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-11A Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

102% of 3588 MWt Core Power, 1.4 sq. ft. Double Ended Rupture - MSIV Failure Upper Compartment Temperature UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-11B Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

102% of 3588 M Wt Core Power, 1.4 sq. ft. Double Ended Rupture - MSIV Failure Lower Compartment Temperature UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-12A Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

102% of 3588 M Wt Core Power, 0.86 s q. ft. Split Break - AFWRP Failure Upper Compartment Temperature UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 27.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-12B Change

Description:

UCR-2138, Rev. 0 Unit: 2

Title:

102% of 3588 M Wt Core Power, 0.86 s q. ft. Split Break - AFWRP Failure Lower Compartment Temperature UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 July 1992 Added to Unit 2 by UCR-2138, Rev. 0 UFSAR Figure: 14.3.4-13 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Worst Break-Lower Compartment Temperature Comparison UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-14 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Upper Compartment Temperature (30% Power Level)

Added to Unit 2 by UCR-2138, Rev. 0 July 1992 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-15 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Lower Compartment Pressure (30% Power Level)

Added to Unit 2 by UCR-2138, Rev. 0 July 1992 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-16 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Lower Compartment Pressure (30% Power Level)

Added to Unit 2 by UCR-2138, Rev. 0 July 1992 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-17 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Worst Break-Lower Compartment Temperature Comparison Generic Analysis Added to Unit 2 by UCR-2138, Rev. 0 July 1992 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-18 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 TMD Model Plan at Equipment Rooms Elevation Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-19 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 TMD Model Containment View Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-20 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 Plan View at Ice Condenser Elevation Ice Condenser Compartments Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Figure: 14.3.4-21 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 TMD Model Layout of Containment Shell UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Figure: 14.3.4-22 Change

Description:

UCR-2185, Rev. 0 Unit 2

Title:

Steam Generator Enclosure Above Elevation 665 ft.

UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-23 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Steam Generator Enclosure Above Elevation 665 ft.

Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-24 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Steam Generator Enclosure Cut-Open View of the Steam Generator Enclosure Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 2 UFSAR Figure: 14.3.4-25 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Schematic of the Cook Unit 1 & 2 9 Node TMD Steam Generator Enclosure Model Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

2 of 2 UFSAR Figure: 14.3.4-25 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Schematic of the Cook Unit 1 & 2 9 Node TMD Steam Generator Enclosure Model UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-26 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 Pressurizer Enclosure TMD Model Noding Network Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-27 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 TMD Model with Pressurizer Enclosure Nodalization Network Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-28 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 Fan / Accumulator Room TMD Model Plan at Equipment Rooms Elevation Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-29 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 Fan / Accumulator Room TMD Model Layout of Containment Shell Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-30 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 TMD Model with Fan / Accumulator Room Nodalization Network Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

INDIANA AND MICHIGAN POWER D. C. COOK NUCLEAR PLANT UPDATED FINAL SAFETY ANALYSIS REPORT Revised: 28.0 Chapter:

14 Sheet:

1 of 1 UFSAR Figure: 14.3.4-31 Change

Description:

UCR-2186, Rev. 0 Unit 2

Title:

Cook Unit 1 & 2 Loop Subcompartment TMD Model Nodalization Network Added to Unit 2 by UCR-2138, Rev. 0 Change

Description:

UCR-850, Rev. 17.1 UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-32 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Reactor Cavity Subcompartment TMD Model Containment Section View 51 46 38 2

53 4

Thru 37 3

52 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-33 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Reactor Cavity Subcompartment TMD Model Layout of Reactor Vessel Annulus Elements 32 37 8 13 18 21 23 25 27 29 36 17 7

12 33 14 11 9

34 15 5

10 35 16 6

11 43 42 41 40 44 39 1

45 44 31 20 26 24 22 28 30 19 3

Break Location 338 293 270 247 224.5 202 158 113 67 22 338 Circumference (Degrees)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-34 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Reactor Cavity Subcompartment TMD Model Nodalization Network 2

32 37 29 36 7

8 12 13 17 18 21 23 27 25 30 33 34 4

9 14 5

10 15 19 22 24 26 28 35 6

11 16 20 52 42 38 59 60 3

58 31 61 62 43 41 40 39 44 1

45 46 50 49 56 57 51 53 47 54 48 55 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-35 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P55-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-36 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P56-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-37 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P57-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-38 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P58-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-39 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P59-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-40 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P60-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-41 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P61-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-42 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P62-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 Revision: 19.3 Change

Description:

UCR-1748 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-43 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P63-25 )

This Figure is representative and should not be used as input in other analyses.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-44 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P55-46 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-45 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P56-47 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-46 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P57-48 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-47 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P60-51 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-48 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P61-52 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-49 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P56-58 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-50 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P57-59 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-51 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P60-62 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-52 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Steam Line Break

( P61-63 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-53 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P55-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-54 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P56-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-55 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P57-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-56 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P58-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-57 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P59-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-58 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P60-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-59 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P61-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-60 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P62-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-61 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P63-25 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-62 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P55-46 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-63 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P56-47 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-64 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P57-48 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-65 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P60-51 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-66 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P61-52 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-67 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P56-58 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-68 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P57-59 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-69 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P60-62 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-70 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Steam Generator Enclosure Feedwater Line Break

( P61-63 )

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-71 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Upper Compartment Element 25 Spray Line Break (When using this curve, the pressure time history should be increased by 10%.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-72 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Pressurizer Enclosure Element 46 Spray Line Break (When using this curve, the pressure time history should be increased by 10%.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-73 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Pressurizer Enclosure Element 47 Spray Line Break (When using this curve, the pressure time history should be increased by 10%.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-74 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressurizer Time History Pressurizer Enclosure Element 48 Spray Line Break (When using this curve, the pressure time history should be increased by 10%.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-75 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Pressurizer Enclosure Element 49 Spray Line Break (When using this curve, the pressure time history should be increased by 10%.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-76 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 27 - 29 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-77 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements : 27 - 42 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-78 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 54 - 42 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-79 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 54 - 41 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-80 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 55 -41 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-81 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 56 - 41 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-82 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 56 - 40 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-83 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 57 - 40 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-84 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 57 - 25 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-85 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 27 - 28 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-86 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 54 - 28 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-87 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 55 - 28 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-88 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 55 - 26 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-89 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 56 - 26 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-90 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 57 - 26 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-91 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 27 - 3 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-92 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 54 - 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-93 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 54 - 3 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-94 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 55 - 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-95 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 56 - 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-96 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 56 - 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-97 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Between Elements: 57 - 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-98 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Fan / Accumulator Room Element 27 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-99 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Fan / Accumulator Room Element 54 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-100 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Fan / Accumulator Room Element 55 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-101 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Fan / Accumulator Room Element 56 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-102 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Fan / Accumulator Room Element 57 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-103 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 1 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-104 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 2 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-105 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 3 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-106 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 4 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-107 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 5 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-108 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 6 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-109 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 25 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-110 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 40 for a DEHL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-111 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time Element 2 for DEHL Break in Element 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-112 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 25 for a DEHL Break in Element 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-113 Sheet 1 of 1

Title:

Plot of the Peak Compartment Pressure as a Function of Time in Element 40 for a DECL Break in Element 1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-114 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Lower Compartment (When using this figure, the differential pressure time history should be increased by an adder of 1.936.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-115 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Upper Compartment (When using this figure, the differential pressure time history should be increased by an adder of 1.936.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-116 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Lower Compartment (When using this figure, the differential pressure time history should be first increased by a factor 1.087 psi and then an adder of 0.75 psi included.)

Unit 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-117 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Upper Compartment (When using this figure, the differential pressure time history should be first increased by a factor 1.087 psi and then an adder of 0.75 psi included.)

Unit 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-118 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Ice Condenser Compartment (When using this figure, the differential pressure time history should be first increased by a factor 1.013 psi and then an adder of 0.9426 psi included.)

UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-119 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Upper Compartment (When using this figure, the differential pressure time history should be first increased by a factor 1.013 psi and then an adder of 0.9426 psi included.)

UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-120 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Lower Plenum of the Ice Condenser (When using this figure for the differential pressure time history, it should be first increased by a factor 1.06 psi and then an adder of 0.866 psi included.)

Unit 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-121 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Lower Plenum of the Ice Condenser (When using this figure, the differential pressure time history should be increased by a factor 1.15 psi.)

UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-122 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History in the Fan / Accumulator Room (When using this figure, the differential pressure time history should be increased by a factor 1.15 psi.)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-123 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-124 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-125 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-126 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-127 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-128 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-129 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-130 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-131 Sheet 1 of 1

Title:

Cook Unit 1 & 2 Differential Pressure Time History Reactor Cavity Subcompartment Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

UNIT 1 This figure is not updated because it is considered as a representative for the TMD analysis.

UCR-1923 provides details for minor increase (1.6928%) in operating deck accident pressure.

Title:

Cook Unit 1 & 2 Differential Pressure Time History Reactor Cavity Subcompartment Sheet 1 of 1 UFSAR Figure: 14.3.4-132 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN Change

Description:

UCR-1923 Revision: 22.1 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-133 Sheet 1 of 1

Title:

Hot Leg Double Ended Guillotine Full Power mh Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-134 Sheet 1 of 1

Title:

Hot Leg Double Ended Guillotine Full Power m Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-135 Sheet 1 of 1

Title:

Cold Leg Double Ended Guillotine Full Power Condition mh Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-136 Sheet 1 of 1

Title:

Cold Leg Double Ended Guillotine Full Power Condition m Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-137 Sheet 1 of 1

Title:

Hot Leg Single Ended Split Full Power Condition mh Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-138 Sheet 1 of 1

Title:

Hot Leg Single Ended Split Full Power Condition m Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-139 Sheet 1 of 1

Title:

Cold Leg Single Ended Split Full Power mh Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-140 Sheet 1 of 1

Title:

Cold Leg Single Ended Split Full Power m Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-141 Sheet 1 of 1

Title:

Pressurizer Spray Line mh Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-142 Sheet 1 of 1

Title:

Pressurizer Spray Line m Transient Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-143 Sheet 1 of 1

Title:

Comparison of Satan (Zaloudek-Moody) to Henry-Fauske Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-144 Sheet 1 of 1

Title:

Comparison of Satan (Zaloudek) to Moody Subcooled Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-145 Sheet 1 of 1

Title:

Zaloudek Measured Data versus Modified Zaloudek Corp.

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-146 Sheet 1 of 1

Title:

Zaloudek Short Tube Data Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-147 Sheet 1 of 1

Title:

Exit Plane Quality as a Function of Upstream Pressure for Saturated Liquid (Moody Model)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-148 Sheet 1 of 1

Title:

Henry ANL 7740 Data Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-149 Sheet 1 of 1

Title:

Loft Tests 809 and 813 Pressure Gage P-1 (Near Rupture)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-150 Sheet 1 of 1

Title:

Full-Scale Section Test Facility Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-151 Sheet 1 of 1

Title:

Discharge Piping Circulation Pump Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-152 Sheet 1 of 1

Title:

Receiver Vessel Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-153 Sheet 1 of 1

Title:

Instrument Location Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-154 Sheet 1 of 1

Title:

Variable Area Flow Path Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-155 Sheet 1 of 1

Title:

Illustration of Choked Flow Characteristics Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-156 Sheet 1 of 1

Title:

Experimental Critical Mass Flow / Homogeneous Thermal Equilibrium Mode A summary of experimental, two-phase, choking flow studies Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-157 Sheet 1 of 1

Title:

Upper and Lower Compartment Pressure Transient for Worst Case Break Compartment (Element 6) Having a DEHL Break (Historical)

Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0

Unit 1 Revision: 17.1 Change

Description:

UCR-850 AMERICAN ELECTRIC POWER COOK NUCLEAR PLANT NUCLEAR GENERATION GROUP BRIDGMAN, MICHIGAN UFSAR Figure: 14.3.4-158 Sheet 1 of 1

Title:

Flow Area - Pressure Differential

  • Full flow area is defined as door port area at maximum door opening Unit 2 Unit 2 Added to Unit 2 by UCR-2138, Rev. 0 l UFSAR Revision 31.0