ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)

From kanterella
(Redirected from ML22322A232)
Jump to navigation Jump to search

ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)
ML22322A232
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 11/18/2022
From: Coleman J
Southern Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
ND-22-0898, ITAAC 3.2.00.04
Download: ML22322A232 (1)


Text

1~

Southern Nuclear November 18, 2022 Docket No.:

52-026 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel ND-22-0898 10 CFR 52.99(c)(1)

ITAAC Closure Notification on Completion of 3.2.00.04 [Index Number 751]

Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRG) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.2.00.04 [Index Number 751]. This ITAAC confirms the human-system interface resources are available to the main control room operators. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRG regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

JMC/CMK/sfr Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 3.2.00.04 [Index Number 751]

U.S. Nuclear Regulatory Commission ND-22-0898 Page 2 of 2 cc:

Regional Administrator, Region II Director, Office of Nuclear Reactor Regulation (NRR)

Director, Vogtle Project Office NRR Senior Resident Inspector-Vogtle 3 & 4

U.S. Nuclear Regulatory Commission ND-22-0898 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-22-0898 Enclosure Vogtle Electric Generating Plant {VEGP) Unit 4 Completion of ITAAC 3.2.00.04 [Index Number 751]

U.S. Nuclear Regulatory Commission ND-22-0898 Enclosure Page 2 of 3 IT AAC Statement Design Commitment

4. The HSI resources available to the MGR operators include the alarm system, plant information system (nonsafety-related displays), wall panel information system, nonsafety-related controls (soft and dedicated), and computerized procedure system.

Inspections/Tests/ Analyses An inspection of the HSI resources available in the MGR for the MGR operators will be performed.

Acceptance Criteria The HSI (at the time of plant startup) includes an alarm system, plant information system (nonsafety-related displays), wall panel information system, nonsafety-related controls (soft and dedicated), and computerized procedure system.

IT AAC Determination Basis An inspection of the Human-System Interface (HSI} resources available in the Main Control Room (MGR) for the MGR operators was performed to verify that the HSI (at the time of plant startup) includes an alarm system, plant information system (nonsafety-related displays), wall panel information system, nonsafety-related controls (soft and dedicated), and computerized procedure system.

The inspection of the HSI resources discussed above was performed per ITAAC Technical Report (ITR) SV4-HSI-ITR-800751 (Reference 1) to confirm that the HSI resources available in the MGR for the MGR operators at the time of plant startup include an alarm system, plant information system (nonsafety-related displays), wall panel information system, nonsafety-related controls (soft and dedicated), and computerized procedure system.

The results of the inspection are documented in the ITR and confirm that the HSI resources available in the MGR for the MGR operators at the time of plant startup include an alarm system, plant information system (nonsafety-related displays), wall panel information system, nonsafety-related controls (soft and dedicated), and computerized procedure system. This report is available for NRG inspection as part of the ITAAC Completion Package (Reference 2).

IT AAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject IT AAC and associated corrective actions. This review found there were no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 3.2.00.04 (Reference 2) and is available for NRG review.

U.S. Nuclear Regulatory Commission ND-22-0898 Enclosure Page 3 of 3 IT AAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 3.2.00.04 was performed for VEGP Unit 4 and that the prescribed acceptance criteria are met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References (available for NRC inspection)

1. SV4-HSI-ITR-800751, Revision Number 0, HFE Human Systems lnterface_Resources Available (ITAAC# 3.2.00.04)
2. 3.2.00.04-U4-CP-Rev0, ITAAC Completion Package