Summary of September 27, 2022, Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 2
ML22272A507
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 09/29/2022
From: Samson Lee
Plant Licensing Branch IV
To:
Lee S, 301-415-3158
References
EPID L-2022-LRM-0066
Download: ML22272A507 (4)


Text

September 29, 2022 LICENSEE: Pacific Gas and Electric Company FACILITY: Diablo Canyon Nuclear Power Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF SEPTEMBER 27, 2022, CLOSED MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY REGARDING PLANNED SECURITY PLAN CHANGES FOR DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 (EPID L-2022-LRM-0066)

On September 27, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with representatives of Pacific Gas and Electric Company (the licensee). The purpose of the meeting was for the licensee to provide information to the NRC staff regarding planned changes to the Security Plan for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Diablo Canyon), in accordance with Title 10 of the Code of Federal Regulations (10 CFR)

Section 50.54(p). The meeting was closed to public participation due to discussion of safeguards information (SGI). The meeting notice and agenda dated September 7, 2022, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML22250A627. A list of attendees is enclosed. By letter dated September 21, 2022 (ML22264A220), the licensee indicated that the licensees attendees are authorized to access SGI.

During the meeting, the licensee provided an overview and the intent of the planned Security Plan changes at Diablo Canyon. The changes are the outcome of the licensees implementation of the Reasonable Assurance of Protection Time (RAPT), which is described in SECY-20-0070 (ML20126G265) and Revision 1 to Regulatory Guide 5.76, Physical Protection Programs at Nuclear Power Reactors, dated November 2020 (the regulatory guide is not publicly available and is controlled as SGI; the transmittal letter is publicly available at ML20329A359). The licensee has determined that these changes do not decrease the safeguards effectiveness of the plan and can be made without prior NRC approval in accordance with 10 CFR 50.54(p)(2).

The NRC staff asked clarifying questions.

No regulatory decisions were made at the meeting.

Please direct any inquiries to me at 301-415-3168 or Samson.Lee@nrc.gov.

/RA/

Samson S. Lee, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES SEPTEMBER 27, 2022, CLOSED MEETING PLANNED SECURITY PLAN CHANGES PACIFIC GAS AND ELECTRIC COMPANY DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 U.S. Nuclear Regulatory Commission Rebecca Richardson, Deputy Director, NSIR1/DPCP2 Anthony Bowers, Chief NSIR/DPCP/RSB3 Jefferson Clark, Chief, NSIR/DSO4/SPEB5 Todd Keene, Chief, NSIR/DSO/SOSB6 Lou Cubellis, Senior Security Specialist, NSIR/DPCP/RSB Pete S. Lee, Senior Security Specialist, NSIR/DPCP/RSB Phil Negrete, Security Specialist, NSIR/DSO/SPEB Jeremiah Rey, Security Specialist, NSIR/DSO/SOSB Steve Vitto, Security Specialist, NSIR/DPCP/RSB Pacific Gas and Electric Company Shawn Kirven, Director, Security and Emergency Services Robert Zimkowski, Manager, Nuclear Security Strategy Dustin ONeill, Principal, Nuclear Security Strategy 1

Office of Nuclear Security and Incident Response (NSIR) 2 Division of Physical and Cyber Security Policy (DPCP) 3 Reactor Security Branch (RSB) 4 Division of Security Operations (DSO) 5 Security Performance Evaluation Branch (SPEB) 6 Security Oversight and Support Branch (SOSB)

Enclosure

ML22272A507 *by email OFFICE NSIR/DPCP/RSB* NRR/DORL/LPL4/PM* NRR/DORL/LPL4/LA* NSIR/DPCP/RSB/BC*

NAME LCubellis SLee PBlechman ABowers DATE 09/28/2022 09/28/2022 9/29/2022 09/28/2022 OFFICE NRR/DORL/LPL4/BC* NRR/DORL/LPL4/PM*

NAME JDixon-Herrity SLee DATE 09/29/2022 09/29/2022