PG&E Letter DCL-22-075 Shawn P. Kirven Director Nuclear Security and Emergency Services Diahlo Canyon Power Plant Mail code 104/5/502 P.O. Box 56 Avila Beach, CA 93424 805.545.3088 Shawn.Kirven@pge.com U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 10 CFR 50.54(p)
Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Upcoming Meeting with Nuclear Security and Incident Response Staff
Dear Commissioners and Staff:
Pacific Gas and Electric Company (PG&E) has a meeting scheduled with the Nuclear Regulatory Commission (NRC) staff on September 27, 2022, to provide information regarding planned changes to the Security Plan for Diablo Canyon Nuclear Power Plant (DCPP), Units 1 and 2, in accordance with 1 O CFR 50.54(p).
The following individuals from PG&E intend to attend the meeting:
Mr. Shawn Kirven, Director, Security and Emergency Services Mr. Robert Zimkowski, Manager, Nuclear Security Strategy Mr. Dustin O'Neill, Principal, Nuclear Security Strategy As requested by the NRC Project Manager for DCPP, PG&E has verified that the above individuals are qualified to discuss Safeguards Information.
If there are questions regarding this update, please contact me at (805) 545-4005.
Sincerely, rntt/51164450 cc:
Mahdi 0. Hayes, NRC Senior Resident Inspector Samson S. Lee, NRC Project Manager Scott A. Morris, NRC Region IV Administrator A member of the STARS Allia nee Callaway