Text
entergy GNRO2022-00027 September 8, 2022 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Entergy Operations, Inc.
P.O, Box 756 Port Gibson, Mississippi 39150 Bradley T. Kapellas Site Vice President Grand Gulf Nuclear Station Tel: 601-437-7500 10 CFR 50.71(e) 10 CFR 54.37(b)
SUBJECT:
Grand Gulf Nuclear Station, Unit 1 Updated Final Safety Analysis Report Submittal Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 Renewed License No. NPF-29 Pursuant to the requirements of §10 CFR 50.71(e) and 50.4(b)(6), Entergy Operations Inc.
hereby submits one pdf copy on CD-ROM (Enclosure) of the Grand Gulf Nuclear Station (GGNS) Updated Final Safety Analysis Report (UFSAR). The UFSAR pdf is a complete copy of the 1 O CFR 50 Appendix B controlled copy of the UFSAR. This revision of the UFSAR includes changes made to the facility as described in the UFSAR during the period of March 1, 2022 through July 19, 2022. Two CDs are enclosed and labeled GGNS UFSAR-Full and GGNS UFSAR-Redacted.
In addition to the requirements of §1 O CFR 54.37(b) and the guidance specified in Regulatory Issue Summary 2007-16, Revision 1, this update must include any Structures, System, or Components (SSCs) with newly identified Aging Management evaluations in accordance with §1 O CFR 54.21. There were no newly identified SSCs subject to aging management review or evaluation during the specified period.
This letter contains no new Regulatory Commitments. Should you have any questions concerning the content of this letter, please contact Jeff Hardy, Manager Regulatory Assurance at 802-380-5124. This certifies the GGNS UFSAR accurately presents the changes made since the last submittal. Executed on September 8, 2022.
GNRO2022-00027 Page 2 of 2
Enclosure:
1, GGNS UFSAR-Full 2, GGNS UFSAR - Redacted cc:
NRC Region IV - Regional Administrator NRC Senior Resident Inspector, Grand Gulf Nuclear Station NRR Project Manager (See Next Page)