GE-Hitachi Nuclear Energy Americas LLC - Vallecitos Nuclear Center, Closure of Confirmatory Action Letter No NRR 03 016 on the Site-Specific Compensatory Measures Implementation Plan
ML22229A583
Person / Time
Site: Vallecitos Nuclear Center
Issue date: 09/06/2022
From: Renee Taylor
Office of Nuclear Reactor Regulation
To: Martinez C
GE Hitachi Nuclear Energy
Tate T
References
Download: ML22229A583 (4)


Text

September 6, 2022 Mr. Carlos Martinez, Site Manager GE-Hitachi Nuclear Energy Americas LLC Vallecitos Nuclear Center 6705 Vallecitos Road Sunol, CA 94586

SUBJECT:

GE-HITACHI NUCLEAR ENERGY AMERICAS LLCVALLECITOS NUCLEAR CENTER, CLOSURE OF CONFIRMATORY ACTION LETTER NO. NRR-03-016 ON THE SITE-SPECIFIC COMPENSATORY MEASURES IMPLEMENTATION PLAN

Dear Mr. Martinez:

The purpose of this letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) has closed Confirmatory Action Letter (CAL) No. NRR-03-016. The NRC issued CAL No. NRR-03-016 on December 5, 2003 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML032721552). This CAL formalized commitments to implement site-specific compensatory measures related to security and safeguards.

By letter dated April 4, 2022 (ML22132A272cover letter only), the NRC received a revised physical security plan (PSP) for the GE-Hitachi Nuclear Energy Americas LLC (GEH) research reactor, in support of license renewal for Facility Operating License No. R-33. In response to this letter, the NRC staff reviewed the GEH PSP and found it to be in compliance with the applicable regulations contained in Title 10 of the Code of Federal Regulations (10 CFR)

Part 73, Physical Protection of Plants and Materials, as stated in the NRC letter dated May 26, 2022 (ML22144A196). In addition, the NRC staff found that the GEH PSP incorporates the site-specific compensatory measures committed to in CAL No. NRR-03-016. Therefore, the NRC considers CAL No. NRR-03-016 closed.

Under 10 CFR 2.390, Public inspections, exemptions, requests for withholding, the NRC will make a copy of this letter available electronically for public inspection in the NRC Public Document Room located at NRC Headquarters in Rockville, Maryland. The public can also access this letter in the NRCs document system, ADAMS, on the NRCs website at https://www.nrc.gov/reading-rm/adams.html.

C. Martinez If you have any questions, please contact Mr. Travis L. Tate, Chief of the Non-Power Production and Utilization Facility Oversight Branch, at 301-415-3901 or by sending an email to Travis.Tate@nrc.gov.

Sincerely, Signed by Taylor, Robert on 09/06/22 Robert M. Taylor, Deputy Office Director For New Reactors Office of Nuclear Reactor Regulation Docket No.50-073 License No. R-33 cc: See next page

GE Hitachi Nuclear Energy Americas LLC Docket No.50-073 cc:

Jeffrey Smyly, Manager Regulatory Compliance GE Hitachi Nuclear Energy Vallecitos Nuclear Center 6705 Vallecitos Road Sunol, CA 94586 Thomas McConnell, Manager Nuclear Test Reactor GE Hitachi Nuclear Energy Vallecitos Nuclear Center 6705 Vallecitos Road Sunol, CA 94586 Scott Murray, Manager Facility Licensing GE Hitachi Nuclear Energy 3901 Castle Hayne Road Wilmington, NC 28401 David Heckman, Vallecitos Reg Affairs & Licensing Lead GE Hitachi Nuclear Energy Vallecitos Nuclear Center 6705 Vallecitos Road Sunol, CA 94586 Commissioner California Energy Commission 1516 Ninth Street, MS-34 Sacramento, CA 95814 California Department of Health ATTN: Chief Radiologic Health Branch P.O. Box 997414, MS 7610 Sacramento, CA 95899-7414 Test, Research and Training Reactor Newsletter Attention: Ms. Amber Johnson Dept of Materials Science and Engineering University of Maryland 4418 Stadium Drive College Park, MD 20742-2115

ML22229A583 NRR-106 OFFICE NRR/DANU/UNPO/SS Tech Editor NRR/DANU/UNPO/LA NRR/DANU/UNPO/BC NAME MTakacs JDougherty NParker TTate DATE 8/18/2022 8/29/2022 8/31/2022 8/31/2022 OFFICE NRR/DANU/D NRR/DD NAME MShams RTaylor DATE 9/1/2022 9/6/2022