NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b
ML22196A006
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/15/2022
From: Robert Kuntz
NRC/NRR/DORL/LPL3
To: Jennifer Davis
Point Beach
References
L-2022-LLA-0074
Download: ML22196A006 (3)


Text

From: Kuntz, Robert Sent: Friday, July 15, 2022 6:16 AM To: Davis, J.Michael Cc: Wall, Scott

Subject:

Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Re: TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b (EPID: L-2022-LLA-0074)

Mr. Davis, By letter dated May 20, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML22140A131), as supplemented by letter dated July 11, 2022 (ML22192A152) NextEra Energy Point Beach, LLC (NextEra), submitted a license amendment for Point Beach Nuclear Plant, Units 1 and 2, to change the Technical Specifications (TSs) to adopt TS Task Force (TSTF) Traveler TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment.

The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, as supplemented, the NRC staff has estimated that this licensing request will take approximately 1600 hours0.0185 days <br />0.444 hours <br />0.00265 weeks <br />6.088e-4 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is July 15, 2023. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

If you have any questions, please contact me.

Robert F. Kuntz, Senior Project Manager Plant Licensing Branch III

Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Hearing Identifier: NRR_DRMA Email Number: 1712 Mail Envelope Properties (SA9PR09MB46406E088B643713E7F8B1C4998B9)

Subject:

Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Re: TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b (EPID: L-2022-LLA-0074)

Sent Date: 7/15/2022 6:16:02 AM Received Date: 7/15/2022 6:16:00 AM From: Kuntz, Robert Created By: Robert.Kuntz@nrc.gov Recipients:

"Wall, Scott" <Scott.Wall@nrc.gov>

Tracking Status: None "Davis, J.Michael" <J.Michael.Davis@nexteraenergy.com>

Tracking Status: None Post Office: SA9PR09MB4640.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2930 7/15/2022 6:16:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: