June 22, 2022
Mr. Ken Peters, Senior Vice President
and Chief Nuclear Officer
Attention: Regulatory Affairs
Vistra Operations Company LLC
P.O. Box 1002
Glen Rose, TX 76043
SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT - NOTIFICATION OF NRC
EVALUATIONS OF CHANGES, TESTS AND EXPERIMENTS INSPECTION
(05000445/2022003 AND 05000446/2022003) AND REQUEST FOR
INFORMATION
Dear Mr. Peters:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff
will conduct the baseline inspection of changes, tests and experiments at your Comanche Peak
Nuclear Power Plant from September 19 - 23, 2022. The inspection will consist of three reactor
inspectors from the NRCs Region IV office for one week. The inspection will be conducted in
accordance with NRC Inspection Procedure 71111.17T, Evaluations of Changes, Tests and
Experiments, dated December 8, 2016.
Experience has shown that this inspection is resource intensive for both the NRC inspectors
and your staff. To minimize the impact to your onsite resources and to ensure a productive
inspection, we have enclosed a request for information needed for this inspection. Please note
that the documents are requested to be provided by September 6, 2022. Upon review of these
documents, the inspectors will select additional documentation for review upon arrival. It is
important that all documents are up-to-date and complete in order to minimize the number of
additional documents requested during the preparation and/or the onsite portions of the
inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Gary Merka of your Regulatory Affairs
organization. If there are any questions about this inspection or the material requested, please
contact the lead inspector, Gerond A. George, by telephone at 817-200-1562 or by e-mail at
Gerond.George@nrc.gov.
PAPERWORK REDUCTION ACT STATEMENT
This letter contains mandatory information collections that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011).
K. Peters 2
Send comments regarding this information collection to the Information Services Branch, Office
of the Chief Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk
Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of
Management and Budget, Washington, DC 20503.
PUBLIC PROTECTION NOTIFICATION
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
for information or an information collection requirement unless the requesting document
displays a currently valid OMB control number.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
Signed by Gaddy, Vincent
on 06/23/22
Vincent G. Gaddy, Chief
Engineering Branch 1
Division of Reactor Safety
Dockets: 50-445; 50-446
Enclosure:
Request for Information
Cc w/ encl: Distribution via LISTSERV
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: GAG Yes No Publicly Available Sensitive NRC-002
OFFICE DRS/EB1 DRS/EB1
NAME GGeorge VGaddy
SIGNATURE /RA/ /RA/
DATE 6/22/2022 6/22/2022
Request for Information
Evaluations of Changes, Tests and Experiments Inspection
Comanche Peak Nuclear Power Plant
Inspection Report: 05000445/2022003; 05000446/2022003
Inspection Dates: September 19-23, 2022
EPID ID: I-2022-003-0003
Inspection Procedure: IP 71111.17T, Evaluations of Changes, Tests and Experiments
Lead Inspector: Gerond A. George, Senior Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
format (preferred) by September 6, 2022, to the attention of Gerond A. George. We request that
you categorize the documents in your response with the numbered list below. If only hard
copies of the requested documents are available or if the electronic format is too large, please
inform the lead inspector and provide the documents on the first day of the onsite inspection.
Also, the inspectors will select specific items from the information requested below and request
from your staff additional documents needed during the onsite inspection weeks. We ask that
the specific items requested be available and ready for review on the first day of inspection. If
you have any questions regarding this information request, please contact the lead inspector as
soon as possible.
1. A copy of any procedures for conducting 10 CFR 50.59 applicability determinations,
screenings, and evaluations and any other 10 CFR 50.59 program-related documents.
These documents, for example, may include procedures for implementation of alternate
processes or screening criteria such as for replacement part evaluations, design
equivalent changes, long-term configuration control, etc.
2. A list with descriptions of all 10 CFR 50.59 applicability determinations of fully
implemented changes, tests and experiments performed since the last triennial 10 CFR
50.59 inspection that did not result in a screening.
3. A list with descriptions of all 10 CFR 50.59 screenings of fully implemented changes,
tests and experiments performed since the last triennial 10 CFR 50.59 inspection that
did not result in an evaluation.
4. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,
tests and experiments performed since the last triennial 10 CFR 50.59 inspection that
did not result in an application for a license amendment.
5. A list with descriptions of all fully implemented changes, tests and experiments where an
alternate process or screening criteria was applied since the last triennial 10 CFR 50.59
inspection.
Enclosure
6. A list with descriptions of all temporary plant modifications implemented since the last
triennial 10 CFR 50.59 inspection. Please note whether these temporary modifications
remain in effect.
7. A list with descriptions of all compensatory actions for degraded or non-conforming
conditions implemented since the last triennial 10 CFR 50.59 inspection.
8. A list with descriptions of all normal, abnormal, and emergency operating procedure
changes implemented since the last triennial 10 CFR 50.59 inspection.
9. A list with descriptions of all corrective action documents related to 10 CFR 50.59
applicability determinations, screenings, and evaluations since the last triennial 10 CFR
50.59 inspection.
10. A list including qualification dates of personnel qualified to prepare, review, or approve
10 CFR 50.59 applicability determinations, screenings, and evaluations.
11. A copy of the current updated final safety analysis report, technical specifications, and
technical specification bases.
12. A copy of any self-assessments or audits performed of 10 CFR 50.59 programs since
the last triennial 10 CFR 50.59 inspection.
13. A copy of the most recent submittal of the report containing a brief description of any
changes, tests and experiments, including a summary of the evaluation of each, required
14. A list of systems and system designators and a set of one-line (i.e., simplified) system
diagrams.
Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can
determine the safety and/or risk significance of the screenings, evaluations, and modifications.
Inspector Contact Information:
Gerond A George Jonathan Braisted, Ph.D. Dustin Reinert, Ph.D.
Senior Reactor Inspector Reactor Inspector Reactor Inspector
817-200-1562 817-200-1469 817-200-1534
Gerond.George@nrc.gov Jonathan.Braisted@nrc.gov Dustin.Reinert@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Gerond A. George
1600 East Lamar Blvd.
Arlington, TX 76011-4125
2