KP-NRC-2204-002 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211 April 5, 2022 Docket No. 50-7513 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Kairos Power LLC Transmittal of Kairos Power PSAR Changes Relevant to Clarification of Coolant Temperature Terminology
References:
- 1. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), September 29, 2021 (ML21272A376)
Kairos Power submitted a Construction Permit Application (CPA) for the Hermes non-power reactor which included a Preliminary Safety Analysis Report (PSAR) (Reference 1). Subsequent to the initial submittal of this document, Kairos Power has made changes to Chapters 4 and 7 correcting an inconsistency in the terminology of core outlet temperature, reactor coolant outlet temperature, and reactor coolant inlet temperature. The change also clarified the description of STAR-CCM+ in Chapter 4 of the PSAR. These changes are considered administrative clarifications and do not result in changes to the design of the Hermes test reactor. Kairos Power requests NRC review of these changes as part of continued review of the Hermes CPA.
Changes to the pages of the PSAR affected by these corrections are provided in Enclosure 1. These changes are based on the submitted document and may not reflect other changes submitted separately.
If you have any questions or need any additional information, please contact Nicole Schlichting at schlichting@kairospower.com or at (980) 215-9252 or Darrell Gardner at gardner@kairospower.com or (704) 769-1226.
I declare under penalty of perjury that the foregoing is true and correct Executed on April 5, 2022 Peter Hastings, PE Vice President, Regulatory Affairs and Quality
Enclosures:
- 1) Changes to the PSAR
KP-NRC-2204-002 Page 2 xc (w/enclosure):
William Kennedy, Acting Chief, NRR Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR Advanced Reactor and Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Samuel de Jesus Cuadrado, Project Manager, NRR Advanced Reactor Licensing Branch