FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
Dear Mr. Brown:
On June 6, 2022, the U.S. Nuclear Regulatory Commission (NRC) will begin a Post-Approval
Site Inspection for License Renewal at Davis-Besse Nuclear Power Station. This inspection will
be performed in accordance with NRC Inspection Procedure 71003. This Phase 3 inspection
will focus on the station actions related to commitments not closed during the Phase 2 license
renewal inspection (05000346/2017009).
In order to minimize the inspection impact on the site and to ensure a productive inspection for
both parties, we have enclosed a request for information needed for the inspection. It is
important that all of these documents are up to date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
the inspection. Insofar as possible, this information should be provided electronically to the lead
inspector. These documents have been divided into two groups.
The first group identifies information necessary to ensure that each inspector is adequately
prepared. The second group identifies the information that each inspector will need throughout
the inspection.
During the in-office preparation activities, the team will identify as much as possible the
information and activities to be reviewed during the inspection. This information should be
provided to the lead inspector by May 23, 2022.
The lead inspector for this inspection is Mr. J. Bozga. We understand that our licensing contact
for this inspection is Ms. G. Ellithorpe of your organization. If there are any questions about the
inspection or the material requested in the enclosure, please contact the lead inspector at
630-829-9613.
April 4, 2022
Mr. Terry Brown
Site Vice President
Energy Harbor Nuclear Corp.
Davis-Besse Nuclear Power Station
5501 N. State Rte. 2, Mail Stop A-DB-3080
Oak Harbor, OH 43449-9760
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - INFORMATION REQUEST
T. Brown
- 2 -
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of
this letter, its enclosure, and your response (if any) will be available electronically for public
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
Sincerely,
John V. Bozga, Senior Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket No. 50-346
License No. NPF-3
Enclosure:
Post-Approval Site Inspection License
Renewal Document Request
cc: Distribution via LISTSERV
Signed by Bozga, John
on 04/04/22
T. Brown
- 3 -
Letter to Terry Brown from John V. Bozga dated April 4, 2022.
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - INFORMATION REQUEST
FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
DISTRIBUTION:
RidsNrrDorlLpl3
RidsNrrPMDavisBesse Resource
RidsNrrDroIrib Resource
DRPIII
DRSIII
ADAMS Accession Number: ML22094A086
Publicly Available
Non-Publicly Available
Sensitive
Non-Sensitive
OFFICE
RIII
NAME
JBozga:mb
DATE
04/04/2022
OFFICIAL RECORD COPY
POST-APPROVAL SITE INSPECTION LICENSE RENEWAL DOCUMENT REQUEST
Enclosure
Inspection Report: 05000346/2022012
Inspection Dates:
June 6-June 10, 2022
Inspection Procedure:
Inspection Procedure 71003, Post-Approval Site
Inspection for License Renewal
Lead Inspector:
John V. Bozga
630-829-9613
I.
Information Requested Prior to the Onsite Inspection Week on May 23, 2022.
The following information (electronic copy) is requested by May 23, 2022, or sooner, to
facilitate inspection preparation. Each inspector will select specific items from the
information requested below and may request a list of additional documents needed to
complete the inspection. We request that the specific items selected be available and ready
for review. If you have any questions regarding this information, please call the inspector as
soon as possible.
1.
Provide (if applicable) aging management program documents, drawings, plant procedures,
work orders, design calculations, industry guidance documents, inspection results,
engineering reports/evaluations, technical reports, specifications, engineering changes,
commitment changes, updated safety analysis report change reports and corrective action
documents associated with the closure of open commitments Nos. 12, 20, 21, 37, 42, 51,
and 53 identified during the Phase II inspection (05000346/2017009)
2.
Provide current management and license renewal organizational charts.
3.
Provide electronic copies of Updated Final Safety Analysis Report, Technical Specifications,
Technical Specifications Bases, and Technical Requirements Manual.
4.
Provide copies of any internal/external self-assessments and associated corrective action
documents generated in preparation for the inspection.
II.
Information Requested to be Provided Throughout the Inspection
1.
Copies of any corrective action documents generated as a result of the teams questions
or queries during this inspection.
2.
Copies of the list of questions submitted by the team members and the status/resolution
of the information requested (provide daily during the inspection to each team member).
If you have questions regarding the information requested, please contact the lead inspector.