Category:License-Operator
MONTHYEARML24281A1102024-10-0707 October 2024 Requalification Program Inspection ML23334A2452023-11-30030 November 2023 75 Day and 150 Day Submittal Letters ML23334A2422023-11-30030 November 2023 Final QA Related Forms ML23298A1652023-10-26026 October 2023 Requalification Program Inspection ML23065A0682023-02-22022 February 2023 Final QA Related Forms ML23047A4142023-02-16016 February 2023 Operator Licensing Retake Examination Approval ML23040A2562023-02-0909 February 2023 Senior Reactor and Reactor Operator Initial License Examinations ML22336A1262022-12-0202 December 2022 U2 - NRC Comments on Proposed Licensee-Developed Written Exam ML22336A1112022-12-0202 December 2022 U2 - Proposed Operating Test ML22336A0792022-12-0202 December 2022 U2 - Final Qa/Related Forms ML22336A0932022-12-0202 December 2022 U2 - Proposed Written Examination ML22336A1362022-12-0202 December 2022 U2 - NRC Comments on Proposed Licensee-Developed Operating Test ML22313A0352022-11-0909 November 2022 U2 - Post Exam Comments and Technical References ML22312A5292022-11-0808 November 2022 U2 - Administered Operating Test ML22312A5222022-11-0808 November 2022 U2 - Administered Written Examination with Answer Key ML22277A2522022-10-0404 October 2022 Requalification Program Inspection ML23003A7792022-09-30030 September 2022 U2 - Administered Written Examination and Operating Test Outlines (Folder 3) ML23003A7672022-09-30030 September 2022 U2 - Handouts to Applicants (Folder 3) ML23003A7862022-09-30030 September 2022 U2 - Proposed Written Examination and Operating Test Outlines (Folder 2) ML23003A7692022-09-21021 September 2022 U2 - Miscellaneous Exam Material (Folder 3) ML22125A1762022-05-0505 May 2022 Preparation and Scheduling of Operator Licensing. ML22083A1892022-03-24024 March 2022 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML22083A1812022-03-24024 March 2022 Final Qa/Related Forms (Folder 1) ML22083A2032022-03-24024 March 2022 Draft Operating Test (Section C) (Folder 2) ML22059B0452022-01-21021 January 2022 Final Operating Test (Section C Only) ML21350A1582021-12-16016 December 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21245A0672021-09-0202 September 2021 Operator Licensing Examination Approval ML21172A2372021-06-21021 June 2021 Requalification Program Inspection ML21105A6502021-04-20020 April 2021 March 10, 2021, NRC Generic Fundamentals Examination Results for Millstone Power Station, Unit 2 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20349A2262020-12-14014 December 2020 Senior Reactor and Reactor Operator Initial License Examinations ML20307A0192020-11-0202 November 2020 Fina Qa/Related Form - Form ES-401-6 (Folder 1) ML20307A0642020-11-0202 November 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML20307A0102020-11-0202 November 2020 Final Qa/Related Forms (Folder 1) ML20302A2342020-10-15015 October 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML20303A1442020-09-18018 September 2020 NRC Comments on Draft Licensee-Developed Exam (Written) ES-401-9 ML20303A0322020-09-18018 September 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20303A0162020-09-18018 September 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20303A0112020-09-18018 September 2020 Handouts to Applicants (Folder 3) ML20302A2352020-09-18018 September 2020 Final Operating Test (Sections a, B, and C) (Folder 3) ML20303A0142020-08-0707 August 2020 Draft Written Examination (Folder 2) ML20303A0122020-07-0202 July 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20105A1592020-04-14014 April 2020 March 4, 2020, NRC Generic Fundamentals Examination Results for Millstone Power Station, Unit 3 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML20105A4342020-04-14014 April 2020 (Vcsns), Unit 1 - NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19323C9172019-11-18018 November 2019 Senior Reactor and Reactor Operator Initial License Examinations ML19238A0262019-08-22022 August 2019 Operator Licensing Examination Approval ML19120A3112019-04-29029 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for Millstone Power Station, Unit 2 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML19064B3922019-03-0505 March 2019 Senior Reactor and Reactor Operator Initial License Examinations ML19045A3702019-02-12012 February 2019 March 2019 GFE Cover Letter Ri 2024-10-07
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23334A2452023-11-30030 November 2023 75 Day and 150 Day Submittal Letters ML23334A2422023-11-30030 November 2023 Final QA Related Forms ML23065A0682023-02-22022 February 2023 Final QA Related Forms ML23047A4142023-02-16016 February 2023 Operator Licensing Retake Examination Approval ML23040A2562023-02-0909 February 2023 Senior Reactor and Reactor Operator Initial License Examinations ML22336A1362022-12-0202 December 2022 U2 - NRC Comments on Proposed Licensee-Developed Operating Test ML22336A1112022-12-0202 December 2022 U2 - Proposed Operating Test ML22336A0932022-12-0202 December 2022 U2 - Proposed Written Examination ML22336A0792022-12-0202 December 2022 U2 - Final Qa/Related Forms ML22336A1262022-12-0202 December 2022 U2 - NRC Comments on Proposed Licensee-Developed Written Exam ML22313A0352022-11-0909 November 2022 U2 - Post Exam Comments and Technical References ML22312A5292022-11-0808 November 2022 U2 - Administered Operating Test ML22312A5222022-11-0808 November 2022 U2 - Administered Written Examination with Answer Key ML23003A7862022-09-30030 September 2022 U2 - Proposed Written Examination and Operating Test Outlines (Folder 2) ML23003A7672022-09-30030 September 2022 U2 - Handouts to Applicants (Folder 3) ML23003A7792022-09-30030 September 2022 U2 - Administered Written Examination and Operating Test Outlines (Folder 3) ML23003A7692022-09-21021 September 2022 U2 - Miscellaneous Exam Material (Folder 3) ML22125A1762022-05-0505 May 2022 Preparation and Scheduling of Operator Licensing. ML22083A2032022-03-24024 March 2022 Draft Operating Test (Section C) (Folder 2) ML22083A1892022-03-24024 March 2022 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML22083A1812022-03-24024 March 2022 Final Qa/Related Forms (Folder 1) ML22059B0452022-01-21021 January 2022 Final Operating Test (Section C Only) ML21350A1582021-12-16016 December 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21245A0672021-09-0202 September 2021 Operator Licensing Examination Approval ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20349A2262020-12-14014 December 2020 Senior Reactor and Reactor Operator Initial License Examinations ML20307A0192020-11-0202 November 2020 Fina Qa/Related Form - Form ES-401-6 (Folder 1) ML20307A0642020-11-0202 November 2020 Draft Written Examination and Operating Test Outlines (Folder 2) ML20307A0102020-11-0202 November 2020 Final Qa/Related Forms (Folder 1) ML20302A2342020-10-15015 October 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML20303A1442020-09-18018 September 2020 NRC Comments on Draft Licensee-Developed Exam (Written) ES-401-9 ML20302A2352020-09-18018 September 2020 Final Operating Test (Sections a, B, and C) (Folder 3) ML20303A0322020-09-18018 September 2020 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML20303A0112020-09-18018 September 2020 Handouts to Applicants (Folder 3) ML20303A0162020-09-18018 September 2020 Final Written Examination and Operating Test Outlines (Folder 3) ML20303A0142020-08-0707 August 2020 Draft Written Examination (Folder 2) ML20303A0122020-07-0202 July 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20105A4342020-04-14014 April 2020 (Vcsns), Unit 1 - NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19323C9172019-11-18018 November 2019 Senior Reactor and Reactor Operator Initial License Examinations ML19238A0262019-08-22022 August 2019 Operator Licensing Examination Approval ML18248A2662018-09-0404 September 2018 Operator Licensing Examination Approval ML18135A0842018-04-25025 April 2018 NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations ML18106A1602018-04-12012 April 2018 March 7, 2018, NRC Generic Fundamentals Examination Results for Millstone Power Station, Unit 3 (Cover Letter Publicly Available, Enclosures Withheld from Public) IR 05000423/20173012018-02-0606 February 2018 Initial Operator Licensing Examination Report 05000423/2017301 ML18029A6512018-01-29029 January 2018 Senior Reactor and Reactor Operator Initial License Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18074A3682017-12-0101 December 2017 Handouts to Applicants, Summary of References (Folder 3) ML18074A3562017-12-0101 December 2017 Final Qa/Related Forms (Folder 1) ML18074A3582017-12-0101 December 2017 Final Qa/Related Forms - Form ES-401-6 (Folder 1) 2023-02-09
[Table view] |
Text
ES-201 Examination Preparation Checklist Form ES-201-1
Facility: MILLSTONE UNIT 3 Date of Examination: 1/20/2022
Developed by: Written: Facility NRC // Operating: Facility NRC
Target Examiners Date* Task Description (Reference) Chief Initials
-240 1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams, BJF arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3).
-210 2. NRC examiners and facility contact assigned (C.1.d; C.2.f). BJF
- 3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility BJF
-210 contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facilitys prescreening process (ES-401, D.1.b).
-210 4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3). N/A
-210 5. Corporate notification letter sent (C.2.e). BJF
- 6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or N/A
-195 ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; C.3.d-e).
-150 7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3, ES-301-1, BJF ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).
-136 8. Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee (C.2.h; BJF C.3.d-e).
- 9. Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms BJF ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3);
-75 supporting documentation (including Forms ES -301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6,
ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).
-75 10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded for BJF facility licensee review (C.1.i; C.2.h; C.3.f-g).
-60 11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES -202). BJF
-50 12. Written exam and operating test reviews completed (C.3.f). BJF
-35 13. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l; BJF C.2.h; C.3.g). The NRC and the facility licensee conduct exam preparatory week.
-30 14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398) due BJF (C.1.m; C.2.i; ES-202).
-14 15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due and BJF Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).
-7 16. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h). BJF
-7 17. Request facility licensee management feedback on the examination (C.2.l). BJF
- 18. Final applications reviewed; one or two (if more than 10) applications audited to confirm BJF
-7 qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; Attachment 5; ES-202, C.3.j; ES-204).
-7 19. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k). N/A
-7 20. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i). BJF
- Target dates are based on facility-prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted on a case -by-case basis in coordination with the facility licensee.
ES-301 Transient and Event Checklist Form ES-301-5 REV.0 Facility: Millstone 3 Date of Exam: Week of 17 Jan 22 Operating Test No.:2K21 A E Scenarios P V 1 2 3 4 T M P E O I L N CREW CREW POSITION CREW POSITION CREW POSITION N I T POSITION T I C S A B S A B S A B S A B A M A T R T O R T O R T O R T O L U N Y O C P O C P O C P O C P M(*)
T P E R I U RO-RX 0 1 1 0 SRO-I NOR 0 1 1 1 I/C 2,3,4 5 4 4 2 SRO-U,6,7 1 MAJ 5 1 2 2 1 TS 1,2 2 0 2 2 RO RX 1 1 0 SRO-I NOR 1 1 1 I/C 4 4 2 SRO-U MAJ 2 2 1 TS 0 2 2 RO RX 1 1 0 SRO-I NOR 1 1 1 I/C 4 4 2 SRO -U MAJ 2 2 1 TS 0 2 2 RO RX 1 1 0 SRO -I NOR 1 1 1 I/C 4 4 2 SRO -U MAJ 2 2 1
TS 0 2 2 Instructions:
- 1. Check the applicant level and enter the operating test number and Form ES -D -1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at -the-controls (ATC) and balance-of -plant (BOP) positions. Instant SROs (SRO -I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO -I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
- 2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional I/C malfunctions on a one-for-one basis.
- 3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
- 4. For new reactor facility licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.
ES-301 Competencies Checklist Form ES-301-6
Facility: Millstone 3 Date of Re-Examination: Week of 17 Jan 22 Operating Test No.: 2K21
APPLICANTS (Rev 0)
RO -1 RO - RO RO SRO -I SRO -I SRO -I SRO -I SRO -U1 X SRO -U SRO -U SRO -U
Competencies SCENARIO SCENARIO SCENARIO SCENARIO 5
SRO Interpret/Diagnose 1,2,3, Events and Conditions 4,5,6, 7
Comply with and 1,2,3, Use Procedures (1) 4,5,6, 7
Operate Control Boards (2)
Communicate 1,2,3, and Interact 4,5,6, 7
Demonstrate 1,2,3, Supervisory Ability (3) 4,5,6, 7
Comply with and 1,2 Use TS (3)
Notes:
(1) Includes TS compliance for an RO.
(2) Optional for an SRO-U.
(3) Only applicable to SROs.
Instructions:
Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Forms ES 303 1 and ES 303 3 describe the competency rating factors.)