Summary of Closed Meeting with Framatome Inc. and the U.S. NRC for Topical Report, ANP-10339P, Rev. 0, Arita - Artemis/Relap Integrated Transient Analysis Methodology Responses to Requests for Additional Information
ML22080A158
Person / Time
Site: 99902041
Issue date: 03/29/2022
From: Ngola Otto
Licensing Processes Branch
To: Richard Chang
Licensing Processes Branch
Otto N, NRR/DORL/LLPB, 301-415-6695
Shared Package
ML22080A157 List:
References
Download: ML22080A158 (3)


Text

March 29, 2022 MEMORANDUM TO:

Richard Chang, Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM:

Ngola Otto, Project Manager

/RA/

Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF FEBRUARY 3, 2022, CLOSED MEETING WITH FRAMATOME INC. AND THE U.S. NUCLEAR REGULATORY COMMISSION FOR TOPICAL REPORT, ANP-10339P, REVISON 0, ARITA - ARTEMIS/RELAP INTEGRATED TRANSIENT ANALYSIS METHODOLOGY RESPONSES TO REQUESTS FOR ADDITIONAL INFORMATION On February 3, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed teleconference meeting via Microsoft Teams with representatives from Framatome Inc.

(Framatome). The purpose of the meeting was for the NRC staff and Framatome representatives to discuss the request for additional information (RAI) 9 response received from Framatome on March 31, 2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20097E582) regarding the Framatome Topical Report ANP-10339P, Revision 0, ARITA - ARTEMIS/RELAP Integrated Transient Analysis Methodology. The meeting notice is available in ADAMS at Accession No. ML22019A242.

During the meeting, there were discussions between Framatome representatives and the NRC staff regarding RAI 9, including several parameters in Table 9-1, Assessment Data and Associated Model Uncertainty Parameters, and Table 9-2, Model Uncertainty Parameter Treatment, and planned discussions for the next meeting. The NRC staff and Framatome representatives plan to continue discussions on a few of the Table 9-1 parameters, and RAIs 11 and 57 at the next meeting planned for February 17, 2022.

The meeting information including this meeting summary is available in ADAMS at Package Accession No. ML22080A157. A list of the attendees is enclosed.

Docket No. 99902041

Enclosure:

As stated CONTACT:

Ngola Otto, NRR/DORL 301-415-6695

Enclosure List of Attendees Closed Meeting with Framatome Inc. and the U.S. Nuclear Regulatory Commission on Topical Report ANP-10339P, Revision 0, ARITA - ARTEMIS/RELAP Integrated Transient Analysis Methodology February 3, 2022 1:00 pm - 5:00 pm NAME ORGANIZATION Buck Barner Framatome, Inc. (Framatome)

John Jones Framatome Timothy Lindquist Framatome Alan Meginnis Framatome Keith Maupin Framatome Jeffrey Moore Framatome William Walters Framatome Kevin Heller U.S. Nuclear Regulatory Commission (NRC)

John Lehning NRC Ngola Otto NRC

ML22080A157 (Package)

ML22019A242 (Notice)

ML22080A158 (Summary)

NRC-001 OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DORL/LLPB/BC NRR/DORL/LLPB/PM NAME NOtto DHarrison RChang NOtto DATE 3/21/2022 3/22/2022 3/23/2022 3/29/2022