Monticello, Unit 1 Subsequent License Renewal Application (SLRA)
Safety Pre-Application Meeting March 16, 2022 Marieliz Johnson Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
Meeting Agenda
- Subsequent License Renewal Review Process +
Inputs into NRC Licensing Decision
- Safety Review:
o Process Overview o Tentative Review Schedule for St. Lucie
- NRC Contact Information
- Conclusion / Questions 2
Subsequent License Renewal Review Process +
Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)
Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)
Safety ACRS Review Recommendation (10 CFR 54) (10 CFR 54.25) 3
Safety Review:
Process Overview Acceptance Review In-Office Technical Review On-Site Audit Breakout Audit Audit Issue Safety Evaluation Report (SER) 4
Monticello: Tentative Safety Review Schedule Note: The review schedule below is tentative and subject to change.
The schedule is only finalized once the application has been accepted forreview and docketing.
Activity Estimated Date Application Submission Date January 2023 Acceptance Date (Project Start Date) February 2023 In-Office Technical Review Audit February/March 2023 On-Site Audit March 2023 Breakout Audit April/May 2023 Safety Evaluation Report March 2024 Advisory Committee on Reactor Safeguards May 2024 (ACRS) Full Committee Meeting Licensing Decision TBD 5
NRC Contact Information Safety Project Managers
- Marieliz Johnson (marieliz.Johnson@nrc.gov)
Safety Branch Chief
- Lauren Gibson (Lauren.Gibson@nrc.gov)
Environmental Project Manger
- Tam Tran (Tam.Tran@nrc.gov)
Environmental Branch Chief
- Ted Smith (theodore.smith@nrc.gov) 6