Letter Sequence Other |
---|
EPID:L-2022-LLE-0007, Request for an Exemption Pursuant to 10 CFR 70.17 and 10 CFR 51.6 from the Requirements of 10 CFR 51.60(a) and 70.21(1) for Timing of Submittal of the Environmental Report for the TRISO-X Fuel Fabrication Facility (Approved, Closed) |
|
MONTHYEARML22039A0502022-02-0404 February 2022 Request for an Exemption Pursuant to 10 CFR 70.17 and 10 CFR 51.6 from the Requirements of 10 CFR 51.60(a) and 70.21(1) for Timing of Submittal of the Environmental Report for the TRISO-X Fuel Fabrication Facility Project stage: Request ML22056A0572022-02-24024 February 2022 NRC Acceptance of Triso-X Exemption Request to Submit the Safety and Safeguards Application Report in Advance of the Environmental Report for the Proposed Fuel Fabrication Facility Project stage: Acceptance Review ML22055A5612022-03-17017 March 2022 Enclosure - Safety Evaluation Report for Approval of Triso-X Exemption Request to Support Submittal of the SAR in Advance of the Er Project stage: Approval ML22055A5592022-03-17017 March 2022 Approval of Triso-X Exemption Request to Submit the SAR in Advance of the Er Project stage: Request ML22055A5602022-03-17017 March 2022 Cover Letter - Approval of Triso-X Exemption Request to Support Submittal of the SAR in Advance of the Er Project stage: Other 2022-02-04
[Table View] |
|
---|
Category:Letter
MONTHYEARML24249A3172024-09-0505 September 2024 TRISO-X, LLC, Supplemental Information for Management Measures and Quality Assurance RAI Responses ML24183A3912024-07-0101 July 2024 Supplemental Information for ISA RAI 1-9 Responses and RAI-10 Response for the TRISO-X License Application ML24089A2012024-05-0808 May 2024 Cover Letter - RAI Status Update for the Safety and Safeguards Requests for Additional Information for the TRISO-X License Application ML24101A0172024-04-23023 April 2024 Request TRISO-X, Llc. to Provide Structural Supplemental Information to Resolve Programmatic Requests for Additional Information for the TRISO-X License Application ML24095A3422024-04-0404 April 2024 Response to Request for Additional Information Part 3 for the TRISO-X Environmental Report ML24085A2702024-04-0202 April 2024 Request TRISO-X, LLC to Provide Supplemental Information to Resolve Programmatic Requests for Additional Information Regarding the Management Measures and Quality Assurance Portion of the License Application ML24082A2222024-04-0202 April 2024 Cover Letter - Request TRISO-X, Llc., to Provide Supplemental Information to Resolve Programmatic Requests for Additional Information Regarding the Integrated Safety Analysis Portion of the License Application ML24087A2352024-03-27027 March 2024 Triso-X, LLC, Response to Request for Additional Information Set 7 (Environmental Safety) for the TRISO-X License Application ML23354A1652024-03-25025 March 2024 Cover Letter - Set Eight Containing a Programmatic Request for Additional Information for the Integrated Safety Analysis Review Regarding the TRISO-X License Application ML24065A3132024-03-0404 March 2024 Response to Request for Additional Information Part 2-2 for the TRISO-X Environmental Report and License Application ML24060A2392024-02-29029 February 2024 TRISO-X, LLC, Submittal of Supplemental Information for the Electrical/I&C Review of IROFS for the TRISO-X License Application ML23321A0422024-02-26026 February 2024 Cover Letter - RAIs Set Seven for the Environmental Safety Review Regarding the TRISO-X License Application ML24046A1642024-02-15015 February 2024 Triso-X, LLC, Submittal of Environmental Report Reference in Support of the TRISO-X Fuel Fabrication Facility License Application ML24020A0102024-01-20020 January 2024 Project Update Letter Regarding the TRISO-X License Application ML23354A2882023-12-20020 December 2023 TRISO-X, LLC, Response to Request for Additional Information Part 2-1 for the TRISO-X Environmental Report and License Application ML23349A2082023-12-15015 December 2023 TRISO-X, LLC, Response to Request for Additional Information Set 6 (Structural, Material Control and Accounting, and Fire Safety) for the TRISO-X License Application ML23342A2152023-12-13013 December 2023 Letter to J Wheeler Re TRISO-X Fff Environmental Review Request for Additional Information Part 2 -2 ML23343A0022023-12-0909 December 2023 Response to Request for Additional Information Set 5 (Chemical Safety and Radiation Protection) for the TRISO-X License Application ML23324A1542023-11-21021 November 2023 Letter to TRISO-X Re Change in Back-up Project Manager ML23235A2232023-11-20020 November 2023 Letter to J Wheeler Re TRISO-X Fff EIS RAIs Part 2 -1 ML23313A1142023-11-17017 November 2023 Cover Letter - Triso-X License Application Sixth Set of RAIs for Material Control and Accounting, Fire, and Structural ML23312A3382023-11-0808 November 2023 Response to Request for Additional Information (Set 4) for the TRISO-X License Application ML23265A2622023-10-25025 October 2023 Request for Additional Information Set 5 for the Radiological and Chemical Review Regarding the TRISO-X, LLC License Application for a New Fuel Fabrication Facility (Enterprise Project Identification Number L-2022-NEW-0005 ML23290A1942023-10-13013 October 2023 Submittal of Revision 3 of the TRISO-X Fuel Fabrication Facility Physical Security Plan ML23285A3442023-10-12012 October 2023 Response to Request for Additional Information Set 3 (ISA and Security) for the TRISO-X License Application ML23293A0352023-10-12012 October 2023 20231012_2022-0019326_DOE-NRC Triso-X Fuel Fabrication Facility_Section 7 Nlaa Concurrence_Roane Co_Signed ML23254A3822023-09-29029 September 2023 Letter to Triso-X for Fourth Set of RAIs Including Geotechnical and Hydrology ML23214A2652023-09-20020 September 2023 Letter to S. Alexander TRISO-X Fff Section 7 Informal Consultation Request ML23258A1752023-09-15015 September 2023 Supplemental Response to Chapter 1 RAI-10 and RAI-11 (Set 2) for the TRISO-X License Application ML23223A2082023-09-0505 September 2023 Tn SHPO Letter Transmitting Report and Findings ML23187A6292023-08-28028 August 2023 Cover Letter - Approval of Exemption from 10 CFR 73-67(d) and (E) for Physical Security of TRISO-X ML23230B1912023-08-28028 August 2023 Cover Letter - RAI Set 3 for the ISA Summary (Programmatic) and Security Regarding TRISO-X License Application ML23237B4842023-08-25025 August 2023 Response to Request for Additional Information (Set 2) for the TRISO-X License Application ML23230B2002023-08-18018 August 2023 Triso-X, LLC, Supplemental Response to Request for Additional Information Question 3-2 (Set 1) for the TRISO-X License Application ML23209A8212023-07-28028 July 2023 Response to Request for Additional Information (Set 1) for the TRISO-X, LLC License Application for a Fuel Fabrication Facility ML23198A2592023-07-27027 July 2023 Request for Additional Information for the Triso-X, LLC License Application for a Fuel Fabrication Facility (Enterprise Project Identification Number L-2022-NEW-0005) ML23121A1512023-07-0303 July 2023 TRISO-X At-Risk Construction Letter ML23127A0122023-05-31031 May 2023 Request for Additional Information (Set 1) for the Triso-X, LLC License Application for a Fuel Fabrication Facility (Enterprise Project Identification Number L-2022-NEW-0005) ML23142A2952023-05-22022 May 2023 Submittal of Revision 3 of the TRISO-X Facility Safeguards Information Plan ML23124A2042023-05-19019 May 2023 Acceptance of TRISO-X, LLC Request for an Exemption from Portions of 10 CFR 73.67(D) and (E) for Physical Security ML23111A2632023-04-21021 April 2023 Request for an Exemption Pursuant to 10 CFR 73.5 from the Requirements of Specified Portions of 10 CFR 73.67(d) and (E) for Physical Security of the Proposed TRISO-X Fuel Fabrication Facility ML23104A4202023-04-14014 April 2023 TRISO-X, LLC, Response to Requests for Additional Information on the Environmental Report for the Proposed Fuel Fabrication Facility ML23072A4562023-03-22022 March 2023 TRISO-X Fuel Fabrication Facility EIS RAI Part 1 Letter and Enclosure ML23032A5012023-02-0202 February 2023 Letter to S. Alexander Re TRISO-X Fws Section 7 Consulation ML23012A2052023-01-12012 January 2023 TRISO-X, LLC, Fuel Fabrication Facility Online Reference Portal Information Access Agreement (Fully Executed) ML23005A0802023-01-0505 January 2023 Ltr. to Wilson Yargee, Chief, Alabama-Quassarte Tribal Town, Re., Section 106 Consultation for the TRISO-X SNM License for a Fff ML23005A1362023-01-0505 January 2023 Ltr. to Marcellus W. Osceola, Jr., Chairman, Seminole Tribe of Florida, Re., Section 106 Consultation for the TRISO-X SNM License for a Fff ML23005A0782023-01-0505 January 2023 Ltr. to Nita Battise, Chairwoman, Alabama-Coushatta Tribe of Texas, Re., Section 106 Consultation for the TRISO-X SNM License for a Fff ML23005A0732023-01-0505 January 2023 Ltr. to John Johnson, Governor, Absentee Shawnee Tribe, Re., Section 106 Consultation for the TRISO-X SNM License for a Fff ML23004A1782023-01-0505 January 2023 Ltr. to Ron Sparkman, Chief, Shawnee Tribe of Oklahoma, Re., Section 106 Consultation for the TRISO-X SNM License for a Fff 2024-09-05
[Table view] |
Text
Jennifer Wheeler, Director Regulatory Affairs, Fuel Production TRISO-X 400 Centrifuge Way Oak Ridge, TN 37830
SUBJECT:
APPROVAL OF TRISO-X EXEMPTION REQUEST TO SUPPORT SUBMITTAL OF THE SAFETY AND SAFEGUARDS ANALYSIS REPORT IN ADVANCE OF THE ENVIRONMENTAL REPORT (ENTERPRISE PROJECT IDENTIFIER (ENTERPRISE PROJECT IDENTIFIER L-2022-LLE-0007)
Dear Jennifer Wheeler:
Triso-X, LLC (Triso-X), a wholly owned subsidiary of X-Energy, LLC, submitted a letter dated February 4, 2022 (Agencywide Documents Access and Management System [ADAMS]
Accession No. ML22039A050), requesting an exemption from requirements in Title 10 of the Code of Federal Regulations (10 CFR), sections 51.60(a), "Environmental reportmaterials licenses" and 70.21(f), "Filing." The exemption request supports Triso-Xs plans to submit a license application in 2022 to possess and use special nuclear material for processing and fuel fabrication. The exemption requests authorization to submit the application in multiple parts: the safety and safeguards analysis report (SAR), followed by the environmental report (ER). Under the current regulations, an applicant must submit the ER and SAR together as a complete package.
A safety evaluation report of the U.S. Nuclear Regulatory Commission (NRC) staffs review of the exemption request is attached in the enclosure. The staff finds that granting the exemption is authorized by law, will not endanger life or property or common defense and security, and is otherwise in the public interest. Therefore, the staff grants Triso-X a temporary exemption from the requirements of 10 CFR 70.21(f) and 10 CFR 51.60(a), until one year after official receipt of the SAR in the Agencywide Documents Access and Management System. Neither granting the exemption request nor beginning a review of the SAR prior to receipt of the ER indicates a commitment by the NRC to accept the license application for docketing.
This letter concludes action on this submittal, and Enterprise Project Identifier L-2022-LLE-0007 is closed.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter and enclosures will be available electronically for public inspection in the NRC Public Document Room (PDR) and in ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. The PDR is currently closed. You may submit your request to the PDR via e-mail at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays.March 17, 2022 J. Wheeler 2 If you have any questions regarding this communication, please contact Matthew Bartlett at 301-415-7154 or via e-mail at Matthew.Bartlett@nrc.gov.
Sincerely, Shana R. Helton, Director Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-7027
Enclosure:
Safety Evaluation Report cc: xenergy@listmgr.nrc.gov Signed by Helton, Shana on 03/17/22
ML22055A559 (pkg), ML22055A560 (Ltr),
ML22055A561 (encl)
OFFICE NMSS/DFM/F NMSS/DFM/ OGC/MFW NMSS/DFM/ NMSS/DFM/
FLB/PM FFLB/LA by email REFS/BC FFLB/BC NAME MBartlett ELee PJehle JQuintero JZimmerman DATE 02/24/2022 02/24/2022 03/07/2022 03/07/2022 03/09/2022 OFFICE NMSS/DFM/D NAME SHelton DATE 03/17/2022