Maureen R. Zawalick Vice President Generation Business and Technical Services Diablo Canyon Power Plant Mail code 104/6/608 P.O. Box 56 Avila Beach, CA 93424 805.545.4242 Internal: 691.4242 A member of the STARS Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek PG&E Letter DIL-21-004 10 CFR 72.70 ATTN: Document Control Desk Director, Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Materials License No. SNM-2511, Docket No. 72-26 Diablo Canyon Independent Spent Fuel Storage Installation Biennial Submittal of Diablo Canyon Independent Spent Fuel Storage Installation Updated Final Safety Analysis Report
Dear Commissioners and Staff:
Pursuant to 10 CFR 72.70, and in accordance with 10 CFR 72.4, Pacific Gas and Electric Company (PG&E) hereby submits the Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) Updated Final Safety Analysis Report (UFSAR),
Revision 9. Revision 9 incorporates changes to the Diablo Canyon ISFSI UFSAR from February 6, 2020, through December 1, 2021. There were no changes in this revision resulting from a license amendment or a 10 CFR 72.48 evaluation.
The Enclosure contains Diablo Canyon ISFSI UFSAR, Revision 9 which includes a list of revised pages in accordance with 10 CFR 72.70(c)(2).
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.
If you have any questions regarding this submittal, please contact Mr. Jim Morris at (805) 305-9775.
This certifies that Revision 9 of the Diablo Canyon ISFSI UFSAR accurately presents changes made since the previous submittal.
Executed on ________________.
Sincerely, Maureen R. Zawalick December 15, 2021 Pacific Gas and Electric Company*
Document Control Desk Page 2 PG&E Letter DIL-21-004 A member of the STARS Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek Enclosure cc:
Diablo Canyon Distribution cc/enc:
William C. Allen, NMSS Project Manager Scott A. Morris, NRC Region IV Administrator Winston C. Smith, NRC Senior Resident Inspector